10 likes | 155 Views
FRCC Planning Timeline. FRCC Annual Regional Transmission Planning Cycle. FRCC Long Range Study Starts. Plan Modified for CEERTS (Tentative). FRCC Annual Plan Publish. Plan Modified for CEERTS (Final). Technical Review (Long Range Study). New CEERTS Project Proposed (by June 1).
E N D
FRCC Planning Timeline FRCC Annual Regional Transmission Planning Cycle FRCC Long Range Study Starts Plan Modified for CEERTS (Tentative) FRCC Annual Plan Publish Plan Modified for CEERTS (Final) Technical Review (Long Range Study) New CEERTS Project Proposed (by June 1) Technical Review (CEERTS) Benefit Review Developer Selection & Contracts FRCC New CEERTS Project Planning Cycle • Note: • FRCC must develop a Transmission Plan each year, and the plan is issued at the end of the technical review • New CEERTS projects are evaluated along with the roll up submittals • CEERTS projects have extra steps and the plan is modified to include them when the steps are completed