An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Citizen’s Information Meeting November 19, 2013 I-495 Northern Section Shoulder use Project UPC 105130 State Project No. 0495-029-123, P101, C501

  2. Location Map Project Location

  3. Proposed Shoulder Use • Northbound Inside Shoulder (no work on Southbound) • All traffic will be allowed to use shoulder lane in peak periods (no flexible delineators) • AM and PM peak hours to alleviate traffic queues and improve merging • Static and dynamic signing, lane markings, and overhead lane-use system included

  4. Typical Section

  5. Pavement Work • Mill and overlay, restripe Northbound I-495 within project limits • Reconstruct outside shoulder to full depth pavement • Widen right shoulder at Georgetown Pike Interchange to provide emergency pull off • Pavement joint repairs for improved ride and longer pavement life

  6. Structures • No major bridge work anticipated. • Sound wall/retaining wall impacts under evaluation. • Pier protection will be upgraded at overpasses within project limits • Overhead dynamic and static sign structures along median barrier and outside barrier

  7. Concept of Operations • Advance DMS signs, static signs, overhead lane control signs, and striping to delineate shoulder lane • Light gray color for shoulder lane to provide contrast • Additional camera coverage and traffic detectors along Northbound I-495

  8. Other Items • During construction, no lane/shoulder closures during peak hours. • Minor drainage work anticipated • Median barrier modifications to upgrade to meet current standards • No right-of-way or utility relocations anticipated

  9. Schedule • Citizen’s Information Meeting - November 19, 2013 • NEPA Document - January 2014 • Notice to Proceed for Construction - May, 2014 • Open for traffic - December, 2014