2. Background 1 of 2. Currently, NOAA's ability to dump POES satellite GAC/LAC data exists only at Fairbanks and Wallops (CDAs)We encounter 2-3 blind orbits/day on each satellite with the CDAsThe number of satellites currently being operated can compound the data latency issuesCDAs experience delays in transferring some satellite data due to limitations on the DOMSAT transfer bandwidthImprovements are pending in this area.We wanted the ability to minimize/eliminate data latency.
E N D
1. 1
2. 2 Background1 of 2 Currently, NOAAs ability to dump POES satellite GAC/LAC data exists only at Fairbanks and Wallops (CDAs)
We encounter 2-3 blind orbits/day on each satellite with the CDAs
The number of satellites currently being operated can compound the data latency issues
CDAs experience delays in transferring some satellite data due to limitations on the DOMSAT transfer bandwidth
Improvements are pending in this area.
We wanted the ability to minimize/eliminate data latency
3. 3 Background 2 of 2
Primary satellites (NOAA-17, 18) have anomalies that require instrument data from the secondary satellites for product development:
N16 HIRS vs. N18 HIRS
N15 AMSU vs. N17 AMSU
Overall constellation continuity
N15, N16, N17 gyro 3 issues
N15 antenna issues
N15, N16, N17 tape recorder issue
EUMETSATs Svalbard ground station (SVL) is handling the blind orbits for NOAA-18
Approached by IPO who offered the Svalbard ground station for POES use
Conducted a feasibility study and developed a proof of concept in the Spring 2006
Users have a clear interest in getting the data from NOAA-17s blind orbit 2-3 orbits earlier
4. 4 Objectives for Using NPOESS Svalbard (NSV) for POES Decrease/Eliminate Data latency
Eliminates blind orbits which minimizes the delays in data recovery
Provide continuous coverage when there are outages (planned and unplanned) at the CDA stations
Develop an economical solution(s)
Utilize existing resources
5. 5 Proposed Enhancements for OSO to Address Data Latency on the POES program Usage of NPOESS Svalbard (NSV) Antenna for GAC dumps only
No commanding
Increased bandwidth of the DOMSAT link to SOCC
6. 6 Planned Usage of NSV1 of 2 Usage for NOAA-17 and NOAA-15 GAC dumps
NOAA-17 and 15 blind orbit GACS would be transferred, on average, 150 minutes sooner than is currently possible
Currently 2-3 orbits of data are dumped when the satellite comes out the CDA blind
Integrated using current IJPS resources and configuration
Testing efforts benefited both IJPS and NSV
7. 7 DOMSAT Enhancements Upgrade the bandwidth from 1.33 Mbps to 2.66 Mbps
Expected in Spring 2007
Substantially improves transfers between CDAs to SOCC but does not eliminate blind orbits
8. 8 Benefits of using NSV1 of 2 Retrieving blind orbit data from the NOAA-17, NOAA-15 satellites at NSV should never interfere with NOAA-18 blind orbit retrieval from IJPS Svalbard (SVL) due to orbit plane differentials.
NOAA-18 blind orbits typically 0100-0500z
NOAA-17 blind orbits typically 0930-1330z
NOAA-15 blind orbits typically 0600-1000z
Note: Should an operational overlap occur on IJPS resources (interfaces into SOCC), priority would be on NOAA-18 (IJPS spacecraft), N17, then N15 according to the POES Scheduling algorithms. These algorithms (POES Scheduling System) have already been modified to schedule resources at NSV on a non-interference basis with IJPS SVL.
9. 9 Benefits of Using NSV2 of 2 Timeliness of data recovery would approach 100%
Currently, data latency (data processed less than 3 hours from observation) for orbital GACs on the operational Satellites can never be better than ~83% (average 2.5 blind orbits
IPO antenna at Svalbard is NOAA controlled property
10. 10 NSV Dataflow
11. 11 Proposed Concept of Operations Data recorded as normal
POES would have priority over Coriolis once operational
SOCC will not perform health and safety prior to NSV
SOCC conveys spacecraft anomalies through NSV or TNOC
Minimal support would be required by operational staff
Blind orbits dumped scheduled at NSV through POES Scheduling System
Data is transferred to SOCC after LOS as scheduled, no call needed
Test indicate a throughput of ~15mins to receive data
NOAA-18 contacts have priority on transfers resolved through POES Scheduling System
During test period data would be dumped over the CDA only if noisy or not received at NSV.
Must avoid repeated transfers to IPD
Preserve an opportunity to playback data over CDAs on N-17 is managed through scheduling
JORP under development
12. 12 Issues1 of 2 POES will have priority over Coriolis once operational until NPP launched
NPP will out prioritize at NSV POES when it launches
this will affect the POES data flow because the IPOs NSV antenna currently available (being paid for by NESDIS) allows for any of the KLMNN' satellites, using any of the operational HRPT downlink frequencies, whereas IJPS actually requires a special STX4 configuration with AIP data for every pass, i.e., operational reliability decreases and data latency increases.
NPP's launch date has slipped to NET FY09, so overall impact and mitigation efforts can occur now.
13. 13 Issues 2 of 2 NSOF move prevents further end-to-end testing at this time
Need to develop procedure(s) to prevent multi-transfers to products group of the same data
Blind orbit data would no longer be transferred over the DOMSAT link.
AFWA, Univ. of Wisc, Monterey, etc. would need to get data directly from IPD, i.e., the same process/path they will have to use when N18 starts dumping at IJPS SVL.
14. 14 Remaining Implementation Items and Dates Verify changes in the POES Scheduling system to incorporate NSV
Generation and distribution of satellite recorder schedules
Redumps at the CDA if needed
Generation and distribution of integrated LEO-T schedule
Demonstrate KSATs ability to use POES Scheduling System products
Perform ETE: November- February with N-15
Perform ETE: January-March with NOAA-17, 15
Train Operational crew: December March
Regression test at NSOF: December
15. 15 Conclusion Testing and analysis to date have shown that NSV is a viable, inexpensive solution to resolving SOCCs current data latency issues
We are using existing NESDIS resources
If no major issues encountered during ETE test then we should be operational in April 2007