An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Metropolitan Unified Fiber Network (MUFN) Silly name – SERIOUS fiber

  2. Agenda • Introductions • Phase 1 construction schedule • Phase 2 fiber construction bid results • Phase 2 construction schedule • Phase 3 construction schedule • Construction process notes • NTIA feedback • MUFN Phase 4

  3. Phase 1 construction schedule • What is MUFN phase 1 again? • E. Washington backbone + laterals, S. Park St/John Nolen/Rimrock laterals, ½ Mineral Point backbone • Site surveys • Permit status • City of Madison Board of Public Works (4 permits) • WisDOT Rails & Harbors permit (bike path) • Construction activity notes • Most work done by 9/30/11 (if not sooner) • I-94 to Portage/Thierer conduit available Fall 2012 • Regent St conduit available July 2011 • Conduit installs/fiber pulls

  4. Phase 2 fiber construction bid results • 2/28/11 RFB issued to qualified vendor list • 3/8/11 RFB questions received (2 Q’s) • 3/9/11 questions responded to • 3/24/11 Five RFB responses received • Result – (again) Intercon Construction won all 4 segments • AT&T Madison area fiber contractor • Reputable and local • Bid unit costs slightly better than phase 1 • UW only awarded 3 of 4 segments (Monona Dr not awarded; S. Fair Oaks issue)

  5. Phase 2 fiber construction bid results

  6. Phase 2 construction schedule • What is MUFN phase 2 again? • Univ. Ave backbone + laterals, Northport Dr backbone + laterals, Mineral Point Rd ½ backbone + all laterals • Site surveys • Permit status • City of Madison Board of Public Works (6/8/11) • WisDOT High Point Rd crossing • City of Middleton (to be scheduled yet)

  7. Phase 2 construction schedule • Construction activity notes • Most work done by 12/1/11 • ~12 week delay on fiber due to earthquake/tsunami (impacting foreign fiber mfgs so US plants at full demand) • S. Pleasant View Rd conduit (Fall 2011) • S. Point Rd conduit (Fall 2011) • Sherman/Northport conduit (Fall 2011) • Monona Dr (Winnequah to Cottage Grove Rd) conduit available (Fall 2012) • Univ. Ave conduit (Whitney Way to Allen Blvd (Fall 2012) • 2016 High Point Rd bridge (working around this)

  8. Phase 3 construction schedule • What is MUFN phase 3 again? • Monona Drive + Broadway + Agriculture Dr area backbone + laterals • WisDOT negotiation for I-90 fiber pair (Femrite to Cottage Grove Rd) • Waiting for final pricing • Looking to capitalize 20yr IRU costs with NTIA funds

  9. Phase 3 construction schedule • Construction activity notes • Anticipated start 4/15/12 with likely end date 12/1/2012 • Monona Drive conduit completed by 11/2012 • S. Fair Oaks & Atwood Ave intersection conduit (9/2012) • Aerial fiber Nichols/Pflaum to Winnequah • May start portions sooner (Fall 2011) & provide partial service if WisDOT agreement reached and NTIA approves IRU funding

  10. MUFN: Cash Match Distribution UW initially “fronts” cash; partners repay amount over 10 years (starting Spring 2011) 10yr payments now start Fall 2011

  11. MUFN: Project Plan Milestones • 6 (backbone & lateral) “service areas” & 2 rings • Light WisDOT (NE side) metro ring – was 5/2010 (NOW 12/2011) • S. Park Street (17 laterals only) – was 9/2010 (NOW 9/11) • East Washington (22 laterals + 2.5mi BB) – was 12/2010 (NOW 9/11) • Mineral Point (23 laterals +2.5mi BB) – 12/2010 (NOW 12/2011) • Northport (7 laterals + 3.5mi BB) – was 9/2011 (NOW 12/2011) • Monona Drive (15 laterals + 2.25mi BB) – was 9/2011 (NOW 12/2012) • University Avenue (14 laterals + 1.5mi BB) – 12/2011 • Light Monona Dr. (SE side) metro ring – was 12/2011 (NOW 12/2012) • 2/3 project MUST be done within 2yrs (1/31/2012) & completed within 3yrs (by 1/31/2013)

  12. Construction Process Notes • Stakeholder obtain/notify building owner(s) • Network design planning • Requirements for internal/external connections • Redundancy & capacity requirements • Use fiber to replace circuits or change network topology • Layer 1, layer 2 and/or layer 3 solutions

  13. NTIA Feedback • Sub-recipient agreement with City of Madison • Agreement completed 6/30/11 • Executed by 8/1/11 • Conduit/fiber appraisal • Market rate for 25.75mi of conduit & 5.75mi of 96ct FOC • In-kind match with non-federal funds (FHA)

  14. MUFN Phase 4 • What is MUFN phase 4? • POTENTIAL construction beyond our initial grant proposal with “excess” funds • MUST pass through NTIA (service/census block) and EA screens again • Anticipated start 4/15/2012 and likely end 12/2012 • NEED PRIORITIZED LIST OF SITES BY 6/3/11 • NEED 1 CONSORTIUM MEMBER REPRESENTATIVE BY 6/3/11 FOR APPROVALS OF NEW LOCATION (MAJORITY VOTE)

  15. MUFN Phase 4 • POTENTIAL UNRANKED criteria to select new locations to serve • Priority based on pro-rate share of $530k cash match • Proximity to existing MUFN locations (<$ additions) • Clustering of sites (>>> bang for $$$) • Location within MUFN service areas included in grant application • “Need” (# of people served & broadband connection upgrade benefit) • Consideration for consortium members who dropped sites or had partial work done on grant sites • What do you think about this criteria and proposed selection process???

  16. MUFN: Silly name – SERIOUS Fiber Comments Or Thoughts? mufn@lists.wisc.edupatrick.christian@doit.wisc.eduhjmills@cio.wisc.edu nazario@doit.wisc.edu