Middle Santa Ana River Watershed Pathogen TMDL Task Force Consolidated Grant Project Update March 25, 2009. Monitoring Program. Monitoring Activities Cool season dry weather monitoring (2008-2009) completed week ending February 21st
E N D
Middle Santa Ana River Watershed Pathogen TMDL Task Force Consolidated Grant Project Update March 25, 2009
Monitoring Program Monitoring Activities Cool season dry weather monitoring (2008-2009) completed week ending February 21st Warm season dry weather monitoring (2009) scheduled to begin week ending May 16th Reports Final Data Analysis Report submitted to SAWPA for distribution Final Dry Season 2008 Report submitted to SAWPA for distribution Draft Cool Season 2008-2009 Report will be developed during April
E. coli Geometric Mean Concentrations Preliminary
BMP Pilot Study Update Wet weather sampling occurred on 02/16/09 Samples collected from all BMP pilot sites
BMP Pilot Study – Bioswale(Preliminary Data, E. coli & TSS, Wet Weather)
BMP Pilot Study – Extended Detention Basin (Preliminary Data, E. coli & TSS, Wet Weather)
BMP Pilot Study – Up-Flo Filter (Preliminary Data – E. coli & TSS, Wet Weather)
BMP Pilot Study – Perk Filter (Preliminary Data – E. coli & TSS, Wet Weather)
BMP Pilot Study – StormFilter (Preliminary Data – E. coli & TSS, Wet Weather)
Other Project Activities Grant Project Final Project Report (BMP pilot study results; BMP dry weather strategy; project summary) – on hold Public Awareness Plan - on hold Watershed-Wide Compliance Activities Draft cool season 2008-2009 report – mid-April Revisions to QAPP and Monitoring Plan?