EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE Schedule Guillaume Prévôt APC, Paris • Introduction • Procurement status • Main milestones
Introduction • The schedule(EUSO-SCH-INST-005-APC_V1.0)has been made frommid 2012 to March 2014 with: • 3 weeks of margins • 7 weeks of holydays / year. Schedule
Procurement status • - Lenses:willbemanufactuedfromDecember the 10th.The 3 lenseswillbefinishedJune, the 10th. • Deliveryat IRAP of the 3 lensesaftermeasurements in US: July, the 27th • - Mechanical structure: will be received by IRAP June, the 10th. • - EEE: every electronics components are supplied or foreseen to be. No long-span delivery identified. • PDM: • -EC_ASIC board: EC_ASIC board FM will be produced April, the 2ndby LAL. • -HVPS boards: HVPS boards FM will be delivered April, the 2nd at APC. • PDM board: PDM board FM will be delivered March, the 12ndat APC. • DP: • -All the subsystems will be produced and tested April, the 2nd. Schedule
Main milestones Main milestones: - CRE AIT EC Unit May, the 29th - CRE AIT PDM July, the 3rd - CRE AIT DP June, the 25th - CRE AIT PDM + DP communication September, the 13rd - CRE AIT Instrument (after a rehaearsal of a campaign), ready to fly November, the 19th - Delivery at Timins, Canada (after 30 days shipment) February, the 18th - Ready to fly March, the 6th Schedule