An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Hardware Procurement Status and Plans Andrew Sansum e-Science Centre, CCLRC-RAL Tier1 Board May 2004

  2. Equipment Purchased • All Kit ordered from Compusys • CPU Cluster: • Dual 2.66GHz Xeon CPUs • 224 Nodes (2GB RAM) • 32 Nodes (4GB RAM) • Disk • 20 Servers • Each with 16 SATA drive Infortrend RAID arrays • 3.5TB per ARRAY • Delivery: • Should have arrived by now • Lost in Atlantic no delivery before 1st week in June • 3 week delay in deployment • Early production phase should be 6 weeks after deployment Tier1 Group

  3. Tender Process • Obtain requirements from experiments • Review tender options (Autumn) select GCAT • Government procurement catalogue • Companies have already completed pre-tender • Informal hardware review – test Opterons etc etc. • Contacts with suppliers • Initiate Tender (early February) • Prepare tender documents • Identify suppliers and obtain primary supplier details • Tenders out door • Tender closed – (Mid March ) • Evaluation (Me + HAG) • Order out door end of March Tier1 Group

  4. GCAT Good or Bad? • Good • Very fast – less than 8 weeks to order • Our usual suppliers can bid • More chance we get what we want • MUCH, MUCH less work • Reduces risk: • No duffers • Less risk that process breaks (go back to GO do not collect …) • BAD • 3-5% overhead for Tier 2 companies (cheaper than EU route for Tier 1s), but not obvious how this reflects into price. • Complicates contractual • Less competition • Less chance of finding new companies • Nagging suspicion that it is all TOO easy and we have missed some snag! Tier1 Group

  5. Next Procurement • Must do better – devolve more work – start sooner • Need to: • look at new storage architectures (iSCSI?) • Spend on network? • Buy tapes (outside this tender) • Buy H/A servers? • Aim for delivery by December of main volume • Must decide very rapidly if GCAT or EU route • EU procurement probably needs 7 months from EU Journal entry • Must start now • Staff committed on installation • GCAT much faster – but take more time than last time. Need to think about it but probably 4 months. Probably can start in August. Tier1 Group