1 / 31

Use of Gas Mixing Equations and Simulation Approaches in Design of Mine Inertisation Systems

Use of Gas Mixing Equations and Simulation Approaches in Design of Mine Inertisation Systems. HW Wu and ADS Gillies 13th United States/North American Mine Ventilation Symposium, 13-16 June 2010 . 1. Objective of the study.

quilla
Download Presentation

Use of Gas Mixing Equations and Simulation Approaches in Design of Mine Inertisation Systems

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Use of Gas Mixing Equations and Simulation Approaches in Design of Mine Inertisation Systems HW Wu and ADS Gillies 13th United States/North American Mine Ventilation Symposium, 13-16 June 2010 1

  2. Objective of the study • To examine gas mixing and dilution approaches to give a better understanding of how acceptable levels of mine atmosphere contaminants can be evaluated. • As an example the interaction between gases from inertisation systems and the underground mine atmosphere can be evaluated to assist in design of the mine inertisation system. • Inertisation approaches include use of engine exhausts, nitrogen, carbon dioxide, and diesel fired boiler units.

  3. Introduction • New approaches allowing improvement in understanding use of inertisation techniques have been examined. • Case studies used to examine available calculation or computer simulation approaches for predicting induced inertisation gas interaction with the mine ventilation system. • Comparisons are made of the use of different approaches to estimate the time required to inert a sealed underground atmosphere situation.

  4. Approaches Adopted • Two direct calculation approaches are • the application of “commonly accepted rules of thumb” for fluid dilution or flushing of a mined space with a minimum diluting gas requirement of for instance of three times the void volume, and • the direct utilization of gas mixing and dilution equations (Hartman, et al 1997). • The use of advanced fire simulation network software, Ventgraph.

  5. Inertisation System - GAG-3A jet engine exhaust unit (GorniczyAgregatGasniczy)

  6. Inertisation System - Liquefied nitrogen

  7. Inertisation System - Liquefied nitrogen

  8. Inertisation System - Tomlinson Boiler

  9. Inertisation System - Membrane Floxal units

  10. GAG Docking Point

  11. Case Study I: Nitrogen inertisation • To provide an estimation of the time required to inert a single entry development in an underground coal mines using a membrane nitrogen gas unit. • Parameters of the single entry roadway are: • Total length of sealed zone 280m with brattice sail partition, • Dimension of the single entry roadway 2.6m by 5.3m., and • Gas make CH4 is 14 m3/hour; CO2 is 7.2 m3/hour. • Parameters of the inertisation system proposed • A nitrogen gas inert unit with inert line into the sealed zone and an inert capacity of 1,100 m3/hour or 0.316 m3/s. • Inert gas output oxygen level of 0.01 percent.

  12. Layout of the seal and inertisation arrangements

  13. Dilution or flushing rule of thumb Time determined from inert gas flow rate and mined void volume Where Y is volume of working space in m3,  is time in seconds, Q is inertisation unit output, m3/s C is a constant set at for instance 3.

  14. Gas mixing and dilution Equation Where Y, Q and  are as defined previously Qg is the gas inflow, m3/s x is conc. of contaminant in the mixture, x0 is conc. of contaminant in the space initially, B is conc. of contaminant in normal intake air

  15. Times required with various constant values used – Rule of Thumb

  16. Times required to achieve various oxygen levels - Gas Equation

  17. Correlation between constant vales, C and the resulting oxygen levels for dilution or flushing rule of thumb

  18. Times required to achieve various oxygen levels – Rule of Thumb

  19. Snapshot from Ventgraph simulation after 10.2 hours with oxygen level at about 1.1% percent

  20. Predicted Gas Concentration in the Purge Pipe over time from Ventgraph simulation outputs

  21. Case Study I Summary • Based on the simple gas dilution or flushing rule of thumb with three times volume, it will take the membrane nitrogen inerting system about 10.5 hours to inert (O2 ~1.1%) the sealed area. • When applying the gas mixing and dilution equation, it would take the membrane nitrogen inertisation system about 10.7 hours to achieve an oxygen level of 1.0 percent. • From Ventgraph simulation it will take 10.2 hours for the membrane nitrogen inerting system to reduce the oxygen level in the sealed area down to 1.1 percent with the assumptions of leakages (every 50m) from the wide side of the heading to the narrow side behind the brattice.

  22. Case Study II: Diesel Fired Boiler • to provide an estimation of the time required to inert a sealed coal Mains development in case of emergency using a diesel fired boiler inertisation unit. • Parameters of the sealed Mains roadways are: • 66 roadways with a total length of 2,273m. • Dimension of the roadway 2.7m by 5.0m. • Parameters of the inertisation system proposed • Three inertisation boreholes, one 0.76m and two 0.56m in diameter are located at 4 ct between B and C Headings. • The boreholes are 54 m in length with a surface steel manifold structure to connect the boreholes to the inertisation unit.

  23. Layout of the Mains development area and inert boreholes arrangements

  24. Times required to achieve various oxygen levels – Rule of Thumb

  25. Times required to achieve various oxygen levels - Gas Equation

  26. Snapshots from Ventgraph simulation after 50.5 hours with oxygen level at about 3.0 percent with Portal seals, R=1,000 Ns2/m8

  27. Predicted oxygen levels over time from Ventgraph outputs (Portal seals, R=1,000 Ns2/m8)

  28. Times required to achieve various oxygen levels – Ventgraph

  29. Case Study II Summary • Based on the simple gas dilution or flushing rule of thumb with three times volume, it will take the diesel boiler inerting system about 50.1 hours to fully inert the sealed Mains area. • When applying the gas mixing and dilution equation, it would take the diesel boiler inertisation system about 49.0 hours to achieve an oxygen level of 3.0 percent. • From Ventgraph simulation it will take between 42.6 to 53.5 hours for the diesel boiler inerting system to reduce the oxygen level in the sealed Mains area down to 3.0 percent with assumptions of resistance values for the portal seals ranging from 100 to 10,000 Ns2/m8.

  30. Conclusions • Case studies have been developed to examine usage of induced inertisation tools available to the Australian coal mining industry. • Comparisons made of estimations of the time required to inert include • the application of “commonly accepted rules of thumb” for fluid dilution or flushing with minimum three times quantity of inert gas requirements, • the utilization of gas mixing and dilution equations, and • the use of advanced fire simulation network software for and modelling of the mine ventilation system.

  31. Conclusions Cont. • These approaches all give reasonable estimation of the times required to inert a sealed area. • However use of rule of thumb or the gas equation calculations does not taken into consideration leakages in mine ventilation systems and assumes prefect gas mixing. • Use of the Ventgraph fire simulation program is able to take these into account but needs careful modelling to reflect the behavior of the mine ventilation network under consideration. • The direct calculations are simpler and more approximate but do not require the effort to set up the more complicated fire simulation model.

More Related