Industrial Training at. Negombo Court Complex Site . W. J. M. K. PERERA (RU/E/2007/119) Department of Civil and Environmental Engineering. Presentation Outline. Introduction to Training Organization Detail information on the Project Training Experiences Problem encountered ………. ………..

rad
Download Presentation

W. J. M. K. PERERA (RU/E/2007/119) Department of Civil and Environmental Engineering

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Industrial Training at Negombo Court Complex Site W. J. M. K. PERERA (RU/E/2007/119) Department of Civil and Environmental Engineering

  2. Presentation Outline • Introduction to Training Organization • Detail information on the Project • Training Experiences • Problem encountered • ………. • ……….. • ……….

  3. Training Placement - CECB • Central Engineering Consultancy Bureau (CECB) is the largest engineering consultancy organization in Sri Lanka. • CECB offer multi-disciplinary expertise such as Building constructions, Roads, Highways, Bridges and Irrigational works. • Nearly 600 of engineers, architects and geologists are employed under CECB. • They are doing multi billion rupee projects which makes them large profit margins.

  4. Proposed Court Complex Negombo Court Complex Site • Client: Ministry of Justice & Law Reforms. • Contractor: State Engineering Corporation (SEC) • Consultant: Central Engineering Consultancy Bureau ( CECB ). • Contract period: 546 days • Funding: Government of Sri Lanka • Value : Rs. 631 millions

  5. PROJECT DETAILS PHASE 3 PHASE 2 PHASE 1

  6. Setting Out of Staircase Flight and Landing Going (280mm) Thickness of the Flight Rise (165 mm) Staircase Beam Staircase Flight

  7. Preparation of Stair-case Doing Setting Out of Staircase Flight Formwork of Staircase Flight

  8. Soil Compaction • Soil was filled layer by layer and water was sprinkled to bring the moisture content of the soil to the optimum moisture content. • Soil was compacted using Vibratory Roller. • Sand Cone test was done to determine to dry unit weight of the soil Performed Sand cone Test

  9. Termite Treatment • This is done as a protection against termite attack. • Drill holes at 2 to 3 feet intervals along the perimeter of the building. Inject the termiticide. • Then termiticide spray directly to the soil. Spraying termiticide Inject termiticide

  10. Plumbing Work Water Supply Line • 20mm, 25mm, 32mm, 40mm PVC pipes are used. • Pipe lines are checked by applying pressure of 8 bars. Sewer Line • Sewer lines are laid 1:80 slope. • All sewer lines are connected to manhole. Applying Pressure for Supply lines

  11. PROBLEMS & SOLUTIONS ON CONCRETE STRUCTURES Hydration temperature increment in mass concrete structures THERMOCOUPLE WITH DATA LOGGER THERMOCOUPLE LOCATIONS

  12. ADD FLY ASH SOLUTION

  13. Concrete Defects AFTER BEFORE SOLUTION BARA MORTAR

  14. SAFETY MANAGEMENT • Provide Safety Equipments (helmets, safety shoes,boots,googles, gloves and safety belts) • Safety Instruction Boards • Located Medical Centre at the Site • Special Traffic Controlling Section • Charge Fairs from employees for Misbehaviors

  15. Training Experience as a whole • Not only improved the technical knowledge as I discussed. • Obtained a vast knowledge on dealing with all sorts of people • Learned both contractor and consultant point of view when constructing a new building. • Made new friends with industry engineers and other workers. • Say any other activities involved during training period…

  16. Thank you