ELI begins construction - the next phase of implementation. Vlastimil Růžička, ELI Beamlines Managing Director Prague, May 24, 2013. Recent progress in ELI Beamlines. Establishment of ELI-DC (April 2013) Contract for building general contractor signed (May 2013)
E N D
ELI begins construction - the next phase of implementation Vlastimil Růžička, ELI Beamlines Managing Director Prague, May 24, 2013
Recent progress in ELI Beamlines Establishment of ELI-DC (April 2013) Contract for building general contractor signed (May 2013) Contract for delivery of PW class laser close to being concluded (probably June 2013)
Establishment of ELI-DC Signature of notarial deed, Brussels, April 11, 2013 Fourth from the left: Robert-Jan Smits, Director-General of DG Research and Innovation Institute of Physics joins theAssociation after itbeing established legally by royal decree (expected May/June 2013)
General contract signed Construction pit May-17, 2013 (phase 1, site preparation, contractor: Strabag) Size: 120 x 60 m Depth: 9 m • General contractor: consortium Metrostav, OHL ŽS, VCES • Laser hall (3 stories bldg., 1 underground), admin.bldg., multifunctional bldg. • To be finished May 2015, total cost 1,4 bil. CZK (VAT excl.)
Procurement of PW class laser Cutting edge 2-PW class 10 Hz repetition rate laser Based on DPSSL technology World leading parameters in output power and repetition rate „Workhorse“ of the ELI Beamlines facility Supplier: Lawrence Livermore National Laboratory, California, USA Participation of Czech scientists in the development team Contract to be signed June 2013