This update provides information on the Georgia Chapter Air Permitting Program, including permit application timeliness, expedited permits, PSD resources, meteorological data, surface roughness update, background concentrations, permit modeling guidance, GHG permitting, Boiler MACT and GACT, wood pellet emission factors, and EPD switching email systems.

ricardob
Download Presentation

AWMA – Georgia Chapter Air Permitting Update April 16, 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AWMA – Georgia ChapterAir Permitting UpdateApril 16, 2013 Eric Cornwell Stationary Source Permitting Program

  2. SSPP Structure • 4 Units - 28 permit engineers, 2 admin • Chem Unit – Glass, engineered wood • NOx Unit – Landfills, engines • VOC Unit – Wood pellets, lumber kilns • Min Unit – Military, rendering, asphalt

  3. Permit Application Timeliness: • Pending Application Count (April 2013): • 202 permit applications • 12 (non TV-renewal) apps older than six months • 500 permit apps processed in past 12 months • Processing time • Title V significant modifications……161 days • 502(b)10…………………………….…...66 days • Synthetic Minor…………………..……62 days

  4. Expedited Permits • In response to Senate Bill 427  O.C.G.A 2-2-2(c)(1)(A). • Implemented no later than July 1, 2013 • Two stakeholder meetings (Oct and Dec) • http://www.georgiaair.org/airpermit/html/sspp/expeditedssppmeeting.htm

  5. Expedited Permits, Cont. • No rulemaking – Director to implement procedures. • Fee-based and optional for applicants • Reviews done by EPD – no third party review • TV-I, TV-R, MAWO not eligible

  6. PSD Resources • PSD Guidance for Industry – now available • Pre-processed met data – now available • Background ambient concentrations – now available • Statewide NAAQS and PSD Increment inventory (aka Off-site Emissions inventory) • Not yet…EPD intends to do this if funding is available

  7. PSD Guidance for Industry • Provides up-front expectations for a complete PSD application • BACT, Modeling, Submittals • Emphasizes early resolution of issues. • http://www.georgiaair.org/airpermit/html/sspp/psd_guidance_document.htm

  8. Meteorological Data • GA EPD has developed 5-years of meteorological data for each ASOS surface and upper air pairing • Pairing based on distance, climatological zone, and data completeness criteria • Last updated on April 4, 2013 • All data sets are available on-line • http://www.georgiaair.org/airpermit/html/sspp/modeling/aermetdata.htm

  9. Surface/Upper Station Pairings

  10. Surface Roughness Update • Previously, EPD provided data sets with three different surface roughness values (0.05, 0.5, 1.0) and the applicant ran AERSURFACE at the project site to find the most representative value. • Now, meteorological data is processed using the surface roughness at the airport • 12 different sectors • Applicant will provide a justification for representativeness in modeling protocol

  11. Background Concentrations • GA EPD has develop background concentrations for each county based on the 2009-2011 design values • PM10, PM2.5, SO2, NO2, CO, Pb • Will update to 2010-2012 design values by the end of April • All data sets are available on-line • http://www.georgiaair.org/airpermit/html/sspp/modeling.htm

  12. Permit Modeling Guidance • Guideline for Modeling PM10 Ambient Concentration in Areas Impacted by Quarry Operation Producing Crushed Stone - August 7, 2012 • http://www.georgiaair.org/airpermit/downloads/sspp/modeling/quarryguideline_august2012.pdf

  13. GHG Permitting • July 20, 2014 – Biomass deferral set to end. • GHG-major sources with non-PSD permits must “begin actual construction” prior to this date; otherwise permit invalid. • US EPA has recently proposed revised “Global Warming Potential (GWP) for Part 98. 78 FR 19809, Table 2

  14. Boiler MACT and GACT • Final standards published in FR Feb 2013 • SSPP slowly rolling details into permits • Adding to already pending applications • Companies can request revisions • Conditions as specific as practical • No mass “open for cause”

  15. Wood Pellet Emission Factors • Process – Log chipper, dryer (usually direct-contact), hammermill, pelletizer, and pellet cooler. • Downstream testing showed VOC previously unaccounted for. • Plants over ~120,000 tpy production may be PSD major without downstream controls. • Manny Patel developed default wood pellet emission factors from AP-42 and testing

  16. EPD switching email systems • Novell to Outlook • Air Branch transition this week • Email addys to remain the same • First.last@dnr.state.ga.us • First.last@gaepd.org • First.last@gadnr.org • 10 Megabyte attachment limit