Reducing Trash in Stormwater

Reducing Trash in Stormwater. John Fusco Senior Engineer EOA, Inc. May 23, 2013. Trash Capture. Trash Load Reduction Requirements 40 % by July 1, 2014 70 % by July 1, 2017 “No Impact” by July 1, 2022 MRP Minimum Full Capture Requirements

richj
Download Presentation

Reducing Trash in Stormwater

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Reducing Trash in Stormwater John Fusco Senior Engineer EOA, Inc. May 23, 2013

  2. Trash Capture • Trash Load Reduction Requirements • 40 % by July 1, 2014 • 70 % by July 1, 2017 • “No Impact” by July 1, 2022 • MRP Minimum Full Capture Requirements • Must treat an area equivalent to > 30% of Retail/Wholesale/Commercial Land Use • Devices must be installed by July 1, 2014 • San Francisco Estuary Partnership Grant • Bay-area Trash Demonstration Project • Funded by the Clean Water StateRevolving Fund and the American Recovery and Reinvestment Act of 2009 • $4.27 M

  3. Trash Capture Devices • General Description • Small Full Capture • Large Full-Capture • Partial Capture • Small Full-Capture and Partial Capture (Combo)

  4. Full-capture Devices • Full-capture Standard • Traps all particles retained by a 5 mm (0.2 inch) mesh screen and has a design treatment capacity of not less than the peak flow resulting from a one-year, one-hour storm in the sub-drainage area • “Recognized” by SF Bay Regional Water Quality Control Board as part of SFEP/ARRA trash demonstration project • ~30 recognized full-capture devices

  5. Small Full-capture Devices • Any full-capture device installed within a catch basin • Requires more frequent maintenance than large full-capture devices • ~20 recognized small full-capture devices

  6. Large Full-capture Devices • Any full-capture device installed in-line or end-of-pipe • Recent installations within the fore bay of a stormwater pump station • ~10 recognized large full-capture devices

  7. Partial Capture Devices • A trash capture device not meeting the full-capture treatment standard • Usually used in combination with small full-capture devices • Automatic Retractable Screen • Clean Screen

  8. Installed Trash Capture Devices