580 likes | 746 Views
2. 3. American Bar AssociationForum on the Construction Industry. . Welcome
E N D
1. 1
2. 2
3. 3
4. 4
5. 5 Withstanding the Tremors:
6. 6 “Structuring the Contractual Relationships Among the Design/Build Team Members” Bennett D. Greenberg, Esq., DBIA
Seyfarth Shaw LLP
Robyn L. Miller, Esq.
DMJM H&N, Inc.
7. 7 NEW REALITIES IN DESIGN/BUILD CONTRACTING
Design /Builder’s perspective
Designer’s perspective
8. 8 MANAGING CLIENT EXPECTATIONS Design/Builder’s relationship with Owner
Designer’s relationship with Design/Builder
9. 9 MANAGING THE DESIGN/BUILDER AND DESIGNER RELATIONSHIP Selection of Partners – Understanding and Appreciation of Different Cultures
Tools for Identifying and Allocating Risks
D/B Owner Agreement
Risk Matrices
Teaming Agreements
10. 10 DESIGN/BUILD BRIDGING Definition
When used
Pitfalls
Best practices
11. 11 ESTABLISHING PRICE AND CONTROLLING PROJECT COST GMP v. Lump sum
Use of contingencies
Design/Builder and Designer’s role in pricing and cost control
12. 12 ROLES & RESPONSIBILITIES Pre-award
Proposal responsibilities
Design responsibilities
Sharing of information &
coordination of Design/Build
proposal or bid
13. 13 Post-Award
Design Development coordination
Standard of care
Performance specifications
ROLES & RESPONSIBILITIES
14. 14
15. 15 Housekeeping Notes:
1) Topic is too broad to cover comprehensively in 45 minutes. If this subject is of interest to you, the paper goes into far greater depth. and this is a case where the Book may be better than the Movie.
2)Some of the slides have been modified , eliminated or reordered, so don’t be concerned if there is not a direct match between this presentation and the printed slides.
Intro:
I approach this topic in my role as project counsel or management consultant, reponsible for developing the project delivery approach, preparing front-end contracts, and developing the risk management and insurance program
Housekeeping Notes:
1) Topic is too broad to cover comprehensively in 45 minutes. If this subject is of interest to you, the paper goes into far greater depth. and this is a case where the Book may be better than the Movie.
2)Some of the slides have been modified , eliminated or reordered, so don’t be concerned if there is not a direct match between this presentation and the printed slides.
Intro:
I approach this topic in my role as project counsel or management consultant, reponsible for developing the project delivery approach, preparing front-end contracts, and developing the risk management and insurance program
16. 16 DEVELOPMENT OF RISK MANAGEMENT AND INSURANCE STRATEGY Process commences during project delivery selection
Performed in conjunction with qualified insurance broker
Strategy based on analysis of threshold issues
Housekeeping Notes:
This is more than a 45 minute topic. Material in paper that I won’t touch on here.
Some change and rearrangement in the slides.. But content is all there somewhere.
When we serve as Project Counsel or consultant, we begin structuring the risk management and insurance program in conjunction with selection of the project delivery system
We retain qualified broker
Create strategy based on threshold issuesHousekeeping Notes:
This is more than a 45 minute topic. Material in paper that I won’t touch on here.
Some change and rearrangement in the slides.. But content is all there somewhere.
When we serve as Project Counsel or consultant, we begin structuring the risk management and insurance program in conjunction with selection of the project delivery system
We retain qualified broker
Create strategy based on threshold issues
17. 17 TYPICAL THRESHOLD INQUIRIES Project Size
Jurisdictional Legal Constraints
Owner's Risk Profile
Project Risk Requirements (lenders, rating agencies, public stakeholders, etc.)
Design/Build Methodology
Structure of Design/Build Entity
Pre-existing Practice Policies
Availability and Cost of Insurance Products in the Marketplace
18. 18 THE PROJECT RISK MATRIX Identify risk factors
Assign contractual, insurance, process and other remedies for each risk
Dress rehearse before project commencement
19. Matrix is useful:
Comprehensive Checklist
To dress rehearse the job
To “sell” the project to stakeholders, lenders and rating agenciesMatrix is useful:
Comprehensive Checklist
To dress rehearse the job
To “sell” the project to stakeholders, lenders and rating agencies
21. 21 STRUCTURING THE DESIGN/BUILD INSURANCE PROGRAM
22. 22 TRADITIONAL INSURANCE FORMAT Owner
Builder’s Risk
Loss or damage to building during construction
Environmental Coverage
Contractors
Insurance
Worker’s Comp.-- Work related injuries
General Liability -- 3d party personal injury / property damage
Automobile
Misc.
Bonds
Bid --Secures bid
Payment-- Secures lower tier payments
Performance-- Secures Contractor performance
23. 23 Contractors
Insurance
Worker’s Comp.-- Work related injuries
General Liability -- 3d party personal injury / property damage
Automobile
Misc.
Bonds
Bid --Secures bid
Payment-- Secures lower tier payments
Performance-- Secures Contractor performance
Owner
Builder’s Risk
Loss or damage to building during construction
Environmental Coverage
Wrap-up- (Worker’s Comp, GL, Excess)
WRAP-UP INSURANCE FORMAT
24. 24 TYPICAL DESIGN/BUILD SETTING Contractor-led design/build
Design/builder provides indemnities, guarantees and warranties for construction and design
Design/builder passes design obligations to architect/engineer subcontractor
Design/builder relies on architect/engineer’s professional liability practice policy to cover negligent errors and omissions
25. 25 TYPICAL DESIGN/BUILD SETTING---QUESTIONS??? Is this insurance structure adequate?
In particular, what policies respond to design risk?
Builder’s Risk?
Commercial General Liability?
Professional Practice Policy?
How can this structure be improved?
26. 26 BUILDER'S RISK INSURANCE Some basics:
Covers direct physical loss to the structure, as well as building materials, whether incorporated into the structure, stored on-site or in transit.
Covers “all risks” except those specifically excluded
“Delay in completion” endorsement
Does not insure loss due to errors or omissions in design, BUT….
27. 27 BUILDER'S RISK INSURANCE "Ensuing Loss" from defective design or workmanship
28. 28 BUILDER'S RISK INSURANCE Facts:
Prior to substantial completion, roof system subjected to significant water infiltration during a "horizontal wind-driven rain."
Insulation below roof was soaked and had to be replaced, and other structures below the roof were damaged.
Failure due to design error and deficient workmanship.
Result:
Policy did not pay " cost of making good design error," i.e., replacing the defective roof,
Policy did pay ensuing loss, such as replacement of the insulation and all other damaged work.
29. 29 BUILDER'S RISK INSURANCE Importance of “Ensuing Loss” coverage for design risk
Policy is primary
Supports contractual waiver of subrogation
30. 30 COMMERCIAL GENERAL LIABILITY (CGL) Some Basics:
Covers bodily injury and property loss exposure
Operates on "occurrence basis"
May include “completed operations” coverage
Carried by contractors and architect /engineer
31. 31 CGL AND DESIGN RISK Standard policy doesn’t exclude design
But…design normally excluded by endorsement
For years, most common endorsement was ISO Form CG 22 43:
This insurance does not apply to "bodily injury", "property damage", "personal injury", or "advertising injury", arising out of the rendering of or failure to render any professional services by you or any engineer, architect or surveyor who was either employed by you or performing work on your behalf in such capacity. Professional services include: (1) the preparing, approving, or failing to prepare or approve maps, shop drawings, opinions, reports, surveys, field orders, change orders or drawings and specifications; and (2) Supervisory, inspection, architectural or engineering activities.
Not thought to preclude “incidental design”
32. 32 CONTINUUM OF CONTRACTOR DESIGN ACTIVITIES
33. 33 CGL AND DESIGN RISK Harbor Ins. Co. v. Omni Construction Co.
Facts:
Property damage to adjacent property during excavation
Caused by subs error in design of sheeting and shoring system
Omni paid repair cost and sought recovery
Carrier denied coverage due to “professional service” exclusion in CG 22 43.
Rulings:
District Court:
Exclusion does not apply to engineering within “normal means and methods”
Court of Appeals:
Reversed … All professional services excluded…even those within means and methods!
34. 34 CGL AND DESIGN RISK Response to Harbor v. Omni
CG 22 43 only to be used for A/E CGL policies
Two new endorsements issued:
ISO CG 22 79 –
Preserves coverage for design incidental to “means and methods”
ISO CG 22 80 -
Preserves coverage for all engineering, architectural, surveying service for project being built
Almost has broad as unendorsed policy
Is this sufficient for Design/Builder?
35. 35 CGL AND DESIGN RISK Limitations of all CGL Policies
Only covers third-party claims for "bodily injury" and "property damage“
No coverage for:
Increased costs to complete the work
Cost of repairing work rendered deficient by negligent design
Economic loss, including the owner's consequential damages (such as loss of profits), resulting from negligent design
36. 36 PROFESSIONAL LIABILITY (PL) INSURANCE Some Basics:
Provides indemnity and defense to the architect/engineer for claims by the owner, design/builder or third parties for damages caused by negligent errors or omissions in the performance of the insured's professional services
Operates on “claims made” basis
Covers economic loss
37. 37 LIMITATIONS OF PL PRACTICE POLICY Aggregate Limits
Inadequate Limits
Potential for Cancellation or Non-renewal
No Direct Access to Policy for Design/Builder (or Owner)
Deductible Responsibility
Application to Design/Build Warranties
38. 38 DESIGN/BUILD PROFESSIONAL LIABILITY ISSUES Warranties and Guarantees
PL coverage only responds to “breach of contract” or warranty claims to the extent the A/E would otherwise be liable for failure to meet the standard of care (i.e. negligence)
Design obligations contained in integrated design/build warranties that are not tied to standard of care are not insurable and generally not bondable
39. 39 CAVEAT ON NEW AIA DESIGN/BUILD WARRANTY Former AIA design/build warranty
“Construction will be free from faults and defects.” § 3.29 AIA Document A191-1996 (Part 2) § 3.29
No reference to Design responsibility
New AIA design/build warranty
“The Design-Builder warrants to the Owner that…, that the Work will be free from defects….” AIA Document A401 Exhibit A (2004) § A.3.5.1
“The term 'Work' means the design, construction and services required by the Design-Build Documents" AIA Document A401 Exhibit A (2004) § A.1.1.6
Clear reference to Design responsibility
40. 40 DESIGN/BUILD PROFESSIONAL LIABILITY ISSUES Warranties and Guarantees
Integrated design/build warranties are not insurable or bondable
Solutions:
Differentiated warranty
Create contingency for uninsurable “Gap” “Design/Builder warrants and guarantees that all materials and equipment incorporated into the Project under this Agreement shall be of first quality and new unless otherwise specified, and that all construction work will be free from faults or defects in materials or workmanship, and in strict accordance with requirements of the Contract Documents; provided, however, that all design services shall be performed in accordance with the standard of care set forth in Paragraph ___ of this Agreement.”
41. 41 ALTERNATE APPROACHES TO INSURING DESIGN RISK
42. 42 Four Alternates to Standard Professional Liability Practice Policy Project Specific Excess
Project Professional Liability Policy
Contractor Professional Liability Policy
Owner’s Professional Protective Indemnity
43. 43 PROJECT SPECIFIC EXCESSDescription Preserves coverage for specific project
Sits “on top” of practice policy and “drops down” if practice policy is exhausted
44. 44 PROJECT SPECIFIC EXCESSLimitations Only covers practice policy holder
Subject to annual placement or renewal
“Follows form” of practice policy
45. 45 PROJECT PROFESSIONAL POLICYDescription Single policy covering all professionals (including Owner’s consultants)
Replaces practice policies
Dedicated project limits
Covers project duration plus 3 to 5 years
Not subject to cancellation
“No fault” among multiple insureds with possible responsibility
46. 46 PROJECT PROFESSIONAL POLICYMarket Experience
47. 47 PROJECT PROFESSIONAL POLICYLimitations for Design/Build
48. 48 CONTRACTOR’S PROFESSIONAL LIABILITY (CPL) Description Professional coverage for design/builder
Vicarious claims due to sub’s performance
Direct claims due to design/builder’s performance
Broad definition of professional services
Waiver of subrogation may be supported
May be excess over A/E policy (must coordinate)
Coverage trigger doesn’t mention negligence
49. 49 Contractor’s ProfessionalLiabilityCoverage Trigger The Company will pay on behalf of the Insured, Loss that the insured is legally obligated to pay as a result of Claims first made against the insured and reported to the Company in writing during the Policy Period for Breach of Professional Duty:
1. by the Insured; or
2. for which the insured is legally liable as a result of the performance of others . . . .
Breach of Professional Duty means an error or omission or other act that causes liability in the performance or non-performance of Professional Services rendered to others by the Insured or others for whom the insured is legally liable.
Contractor's Professional and Pollution Liability, Form 77396 (12/00), Cl1257, American International Specialty Lines Insurance Company.
50. 50 OWNER’S ISSUES WITH LISTED ALTERNATIVES Insufficient limits
Inadequate coverage
Subject to exhaustion of limits
Risk of cancellation or non-renewal
No direct coverage as insured
Extremely expensive
Insufficient limits for catastrophic losses
No direct coverage as insured
51. 51 OWNERS PROTECTIVE PROFESSIONAL INDEMNITY (OPPI) Description Owner is named insured
Design professionals required to maintain practice policies with “Minimum Insurance Requirements”
OPPI is excess of practice policies, drops down to SIR if practice policy exhausted
No right of subrogation if Minimum Insurance Requirements are maintained
52. 52 BUSCH STADIUM OPPI
53. 53 BONDING THE DESIGN/ BUILD PROJECT
54. 54 PERFORMANCE BOND FORMAT Protects Obligee from default of Principal
Surety performs or pays up to penal limit
Surety has subrogation and indemnification rights against Principal
55. 55 UNDERWRITING CONCERNS
Design Risk
Sureties balk at taking insurable risk
Sureties refuse design risk; integrated design & construction warranties
Solution:
Bifurcate warranty and bonding responsibility in Contract
Limit design liability in performance bond form
56. 56 AGC APPROACH TO DESIGN/BUILD BONDING Warranty is for construction only
Bonding requirement:
57. 57 AGC APPROACHTwo Design/Build Bond Forms AGC Document No. 470 AGC Document No. 471
58. 58 UNDERWRITING CONCERNSComposition of Design Build Entity
“Bondability” Factors
Financial strength
Design/build experience
Internal organization
Specific team work history
Track record of success
Contractor-led
Integrated design/builder
Designer-led?
Limited liability company?
Project specific joint venture?
59. 59