An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Control System of production furnace for SPES project Results and progress status march 2010 March 2010 Target Group

  2. Power Supplies LambdaGenesys 3.3kW • Upgrade software Prototype.CFP.v.9 to Prototype.CFP.v.10 It has been updated the Prototype_CFP_1_ctrl_valve.v.9 software to release 10 (Prototype_CFP_1_ctrl_valve.v.10). This new release allows to work with or without thermocouple (older release prevents this choice,so the absence of thermocouple causes the program stopping). The choice to disable or to enable thermocouple is done by means of DIP switch N°1 on the front of the cFP-2120 (shown in figure). SWITCH1 ON  no therm.  LEDA ON SWITCH1 OFF  with therm.  LEDA OFF March 2010 Target Group

  3. Power Supplies LambdaGenesys 3.3kW • Upgrade software Prototype.CFP.v.10 to Prototype.CFP.v.11 It has been updated the Prototype_CFP_1_ctrl_valve.v.10 release to release 11 (Prototype_CFP_1_ctrl_valve.v.11). This new revision replaces the drivers for ESS Power Supply with the drivers for Genesys Power Supply. Figure shows the genesys drivers in the state 1001 of FSM (state for CHECK SYSYTEM COMMUNICATION ) March 2010 Target Group

  4. Power Supplies LambdaGenesys 3.3kW As shown during december meeting, in addition to parameter configuration of Power supply, it is necessary to provide the correct settings for the communication channel. March 2010 Target Group

  5. Power Supplies LambdaGenesys 3.3kW Work in progress I’m developing the revision 12 of the software. This release replaces the Eurotherm serial RS232 drivers with the drivers for new controllers RS485. Future steps - Test and verification of the final software. - Power supply and eurotherm regulators assembling in the furnace and relevant wiring - Last test in site March 2010 Target Group