CMS gas systems meeting. Outline Introduction Review achievements during 2013 Review usage of CMS gas M&O 2013 Review of 2013 upgrade projects Agree/Review activities and schedule for 2014. Outline. PH-DT-DI Gas Service Team. Gas Service Team mandate:
E N D
CMS gas systems meeting Outline Introduction Review achievements during 2013 Review usage of CMS gas M&O 2013 Review of 2013 upgrade projects Agree/Review activities and schedule for 2014 Outline R. Guida CERN/PH-DT-DI
PH-DT-DI Gas Service Team • Gas Service Team mandate: • M&O and upgrades of the gas systems for all the LHC experiments: • preventive and corrective maintenance on 30 gas systems • on-call service all along the year (24/24 7/7) – phone 162516 • Construction of gas systems for other experiments at CERN (CLOUD, NA62, LINAC4, …) • General support for test beam and equipment belonging to external users. ALICE Albin Wasem Introduction – Working team FSU team Jonathan Dumollard AbdelmajidLaassiri Benjamin P. Marichy HerveMartinati Ace Ordanov (User) Cedric Landraud (also CMS-CO2) Guillaume Lacroix (also CERN Expo) ATLAS Frederic Merlet (0.25) Louis-P. De Menezes (0.5) Coordination R. Guida CMS-TOTEM Andrea D’Auria (0.5) LHCb Patrick Carrie (0.5) Steven Pavis (0.25) R. Guida CERN/PH-DT-DI
PH-DT-DI Gas Service Team First contact person for all issues related to CMS gas systems during working hours is in charge of: -standard operation -standard maintenance/small modifications -daily check of all systems CMS-TOTEM Andrea D’Auria 16-0021 CMS experiment and Gas Service Team If Andrea is in holiday or busy: -during working hours call directly Roberto (16-2146) -outside working hours call directly on-call service (16-2516) Outside working hours call directly on-call service (16-2516) R. Guida CERN/PH-DT-DI
Gas Service working team • In order to cope with LS1 a significant reinforcement of the team during 2013 was needed: • two new users with high experience in the workshop (mechanics and gas systems) • many students for short and well defined projects • Details: • CERN FTE (and students > 1 year): • 6.3 FTE: +1.3 wrt 2012 • Ernesto: TTS 50% for gas project • “FSU” (FSU + technical users): • 5.5 FTE: +1.5 wrt 2012 • Ace: user on ATLAS budget • Andrei: user on ALICE budget • Trainees (student < 1 year) • 1.9 FTE: +1.8 wrt 2012 • 4 trainees (3 from Poland, 1 from Canada) • 2 summer students • 2 children of staff members Working team R. Guida CERN/PH-DT-DI
PH-DT-DI Gas Service Team • 2013 activities can be divided into three main sectors: • Standard maintenance of gas systems for the LHC experiments • LS1 consolidation program for the LHC experiments • Not LHC experiments/support to users • Standard maintenance andLS1 consolidation programconstitute the main field of activity • Not LHC experiments and support to users represent about 20% of the activities LS1 – 2013: Overview R. Guida CERN/PH-DT-DI
Review usage of CMS gas M&O 2013 • CMS contribution to M&O budget for gas systems: 157 kCHF On-call service: purifiers RPC, CSC IR RPC SGX5 Supply R134a CSC broken bubbler Distribution RPC, CSC, … Primary Gas Supply monitoring alarm SX5 and 904 mixers CMS gas M&O 2013: on-call R. Guida CERN/PH-DT-DI
Review usage of CMS gas M&O 2013 On-call service summary On average only 1.5 h/year/system of downtime (power-cuts and outside events excluded) Intervention triggered by: CMS gas M&O 2013: on-call • Intervention are: • Equally distributed between experiments • Decreasing with time R. Guida CERN/PH-DT-DI
Review usage of CMS gas M&O 2013 CMS gas M&O 2013: material R. Guida CERN/PH-DT-DI
Review usage of CMS gas M&O 2013 CMS gas M&O 2013: material R. Guida CERN/PH-DT-DI
Review usage of CMS gas M&O 2013 CMS gas M&O 2013: material for gas workshop R. Guida CERN/PH-DT-DI
Review usage of CMS gas M&O 2013 CMS gas M&O 2013: FSU resources R. Guida CERN/PH-DT-DI
Review usage of CMS gas M&O 2013 Summary: CMS gas M&O 2013: summary about 13 kCHF overspending R. Guida CERN/PH-DT-DI
Review of 2013 upgrade projects Summary: Upgrade projects 2013: summary • Others related to CMS: • CMS-TIF lab186: • Mixer and distribution for GEM detector • Flushing distribution for CO2 cooling plant • CMS-TIF CO2 cooling plant construction in gas workshop. R. Guida CERN/PH-DT-DI
LS1 – 2013 R. Guida CERN/PH-DT-DI
More details available on the excel table in agenda LS1 – 2014 schedule R. Guida CERN/PH-DT-DI
Software upgrade Main responsible: Steven Pavis • EN-ICE ispreparing the migration to a new software version (CPC6 & more). • The migration requires to (~) completely rewrite the code (PLC+PVSS): • Preparation phase needed to definestrategy and milestons • Define modules, test logic, … • Validation of one/twogassystemscoveringalmost all functionalities • Deployment on one experiment (all detectors) • Deployment on all the experiments • A completecommissioningwillberequired (same as itwasdoneat the first start-up of the gassystems) • About one-twoweek of stop/instability for each detector (CSC, DT, RPC, T1, T2, ID flushing, …) • Activitiyscheduledfrombeg. March to June 2014 Software upgrade R. Guida CERN/PH-DT-DI
Software upgrade Software upgrade Main responsible: Steven Pavis R. Guida CERN/PH-DT-DI