ROUTAGE ECHELLES A CABLES DANS TDC2 SITUATION ACTUELLE
VUE SUR PASSERELLE, VERS TCC2, FIN SECTION 8mSITUATION ACTUELLE
VUE SUR PASSERELLE, VERS TCC2, DEBUT SECTION 6mSITUATION ACTUELLE
TDC2 : TRANSITION SECTION 8m VERS SECTION 6m SITUATION ACTUELLE TDC2 SECTION 8m 5 ECHELLES COTE JURA TDC2 SECTION 6m
A A TRANSITION SECTION 8m 6m SITUATION ACTUELLE
D D DEBUT SECTION 6m : SITUATION ACTUELLE
3 MSSB TCSC D D VOLUME ECHELLES SECTION 6m : PASSAGE ECHELLES DE LA PASSERELLE VERS MUR “JURA”
Proposition echellesau sol cote machine EN NUANCES DE VERTS : ECHELLES CONTROLE EN JAUNE : ECHELLE SERVICES GENERAUX EN ROUGE : ECHELLE PUISSANCE
A A Section de depart = section existante
B B • Degagementechelle SG vers cote saleve • Degagement OD 110 vers OD??? • OD??? Devient OD110 • Reste de la section inchange OD110 OD??? SG
C C • Degagement OD 118 vers cote Saleve OD118
D D MDLV.240104 ~28m • Mouvementexistant de OD110 versmurSaleve Section sur premiere partie TDC2 MDLV.240104 a peupres OD110
3 MSSB TCSC E E • Fin de la passerelle • Degagement OD 114 versmurSaleve MDLV.240104
3 MSSB TCSC F F • 2 echelles 600 surpasserelle 3 echelles 400 au sol
3 MSSB TCSC G G ECHELLES EXISTANTES MSSB MSSB MSSB
TCSC 3 MSSB H H
TCSC I I • 3 echelles AL 400 au sol configuration existante