Project To Speed Safety/Damage Assessments Thru Interoperable Mobile Field Inspection Technology

Project To Speed Safety/Damage Assessments Thru Interoperable Mobile Field Inspection Technology. Final Report on Outcome & Recommendations from Pilot & Golden Guardian Demonstrations Robert Wible, Project Director, “The L.A.Basin Project” December 19, 2008, CA OES, Mather, CA. The Problem.

sandra_john
Download Presentation

Project To Speed Safety/Damage Assessments Thru Interoperable Mobile Field Inspection Technology

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project To Speed Safety/Damage Assessments Thru Interoperable Mobile Field Inspection Technology Final Report on Outcome & Recommendations from Pilot & Golden Guardian Demonstrations Robert Wible, Project Director, “The L.A.Basin Project” December 19, 2008, CA OES, Mather, CA

  2. The Problem In the aftermath of a disaster what can be done to speed: - Conducting of safety/damage Inspections? - Getting inspection results Into central database to understand magnitude? - Completion & submission of ATC forms to get victims & Federal disaster assistance funds?

  3. Lessons from Katrina: Mobile inspection technology can significantly speed conducting & compiling safety/damage assessments & immediately enter results onto forms to speed claims / recovery - 120,000 homes in 6 weeks!

  4. The Question: • Can we build on Katrina Lesson in California but radically speed up process by expanding number of inspectors available & enabling them to bring and use their own diverse hardware /software forming an interoperable regional, and then a state-wide network?

  5. Origin & Purpose of Project • Briefings, spring 2006 State of CA OHS, City of L.A. & L.A. Basin Chapter of ICC by Robert Wible in wake of experience with Katrina & PNWER “Blue Cascades III Exercise” • Design project to ascertain feasibility & conduct proof of concept demonstrations that diverse hardware & software can be linked & used to create regional/statewide network of inspectors to rapidly conduct, transmit to central database safety/damage assessments in aftermath of major disaster

  6. “The L.A. Basin Project” • In 2007 - CA OHS support, CA OES grant from U.S. DHS to: • Work in L.A. Basin to “Demonstrate Regional Interoperability of Mobile Safety/Damage Assessment & Inspection Technologies to prove the concept that CA & local governments can build first a regional and then a national network of safety/damage assessment inspectors to speed disaster reporting & recovery”

  7. Project Participants • Project Team: Robert Wible, RW Associates, Paul Watkins, Chair ITIA Committee, Neville Pereira – Chair L.A. Basin Chapter ICC Admin. Committee (Glendale) & David Schnitger, Vice Chair (Los Angeles), Alliance I.T. Industry Advisory Committee • C A OES Project Oversight: Michael Sabbaghian & Jim Barnes • Initiated May, 2008

  8. “L. A Basin Project” Scope of Work • Proposed Four Phases – U.S. DHS Grant funded Phase I & Phase II ($125,000) • Phase I - Design & conduct feasibility study – include survey all L.A. Basin jurisdictions regarding mobile technology • Phase II – Design conduct Pilot Demonstration & design, conduct Expanded Demonstration during Golden Guardian - Report lessons & recommendations towards building a Regional (Phase III) & Statewide (Phase IV) Networks

  9. Phase I - Feasibility Study • May – June, 2008: - Design & conduct survey of 84 jurisdictions in L.A. Basin region - Identify jurisdictions with appropriate technology (84 / 13) - Research/report feasibility of interoperability of linking that diverse hardware/software - Identify 4 to participate in Pilot demonstration

  10. IVR and MOBILE INTERNET or VPN JURI DATA STAGED and INSPECTION DATA DEVICES with PROPAGATED DATA PAPER-BASED FORMS FEMA FORMS Phase II – Demonstrations & Report Lessons & Recommendations for Networks • Pilot Demonstration: - Design methodology to use / link diverse hardware & software & get it to compile data & send to central point

  11. Phase II - Pilot Demonstration • August 27, 2008: • Jurisdictions of: Gardena, Glendale, San Dimas & Santa Clarita 8 different devices 3 different software systems & all: pulled down addresses, conducted inspections, uploaded to central data point & downloaded inspection results onto ATC – 20 forms

  12. Pilot Lessons & Recommendations • Interoperability worked • Uniform Address issue • Need redundancy • Expand Demo during Golden Guardian but put under stress • Need & interest for developing network & expand outreach to interest other states in developing similar networks

  13. Phase II – Expanded Demonstration During Golden Guardian • Revised Methodology - Expand number of jurisdictions but also: - Test under realistic disaster conditions - “Grab and go” - Use more IVR - Use paper inspection forms – scan to upload - Central data point in GG SOC Sacramento - Mockup actual building – LAUSD Middle School #3 S. Shatto Place, L.A.

  14. November 14 – Golden Guardian Expanded Demonstration • Seven Jurisdictions Participated: Gardena, Glendale, San Dimas, Santa Clarita, Monrovia, City of L.A. & Riverside Co. - Eight diverse hardware/software systems - Three smartphones & IVR inspections- all from marked up Middle School # 3 - Tested under both simulated (GG) & actual disaster conditions (fires)

  15. Lessons Learned • Simulated & actual damage conditions were successful test of technologies • Paper-based & IVR inspections strengthen future system • Inspection of mocked up school beneficial • Need to simplify all aspects of technology

  16. Recommendations from Golden Guardian Demo to CA OES / OHS • Regional Network can be readily built using mobile technology, IVR & paper • Keep system simple • Conduct more mock-ups in future exercises • Work on issue of address uniformity • Work on interoperability standard to go into future procurements of IT • Build Regional & then Statewide Network • Share outcome from Phase II with other states

  17. Recommendations to Others: • To CA Local Jurisdictions - Test mobile technology in future drills - Train more staff in safety/damage assessments - Working with state to build network • To Vendors - Work with state on interoperability standard & network • To U.S. DHS - Assist CA building network in Phase III & IV - Consider national uniform address system

  18. The Question – Can CA Build Interoperable Network of Safety/Damage Assessment Inspections & Speed Process ? • A resounding YES, and soon and open to all jurisdictions whether they have mobile inspection technology or use paper-based inspections • Phase III – S. California Regional Network by end 2009 • Phase IV – Statewide Network 2011

  19. Questions ? • Contact: • Project Director Robert Wible at: rcwible@comcast.net or 703-568-2323 • Project Technical Coordinator Paul Watkins at: paulcwatkins@gmail.com 704-309-3479