60 likes | 142 Views
HiRadMat : report from WG2 – WANF dismantling . Agenda. WANF cleaning T1 removal Access and Ventilation hardware Integration : naming convention Short Term Planning : co-activities in January 2010 Long Term Planning . WANF cleaning .
E N D
HiRadMat: report from WG2 – WANF dismantling Agenda S. Evrard • WANF cleaning • T1 removal • Access and Ventilation hardware • Integration : naming convention • Short Term Planning : co-activities in January 2010 • Long Term Planning
WANF cleaning S. Evrard • Technical specification worked out with RP : WANF cleaning • PE launched (S. Sonnerat, purchase officer) • 4 companies enquired (all contacted): • Cerap(F, MrX. Labat) • Salvarem(F, MrB. Agret) • Techman(F, MrO. Rotelle) • Technubel(B, MrK. Lenie) • Deadline offers return: Tues. 15.12 • Work foreseen in week 4 (18 22 January)
T1 removal S. Evrard MCA + 6 TAX blocks Procedure prepared by EN/HE Forklift shielding study in progress Forklift preparation in Weeks 2 Work foreseen in week 3 (11 15 January)
ACCESS S. Evrard
Integration issues S. Evrard Kick-off meeting done Naming convention
Co-activities in January 2010 EN-HE EN-CV Contractor EN-HE GS-ASE, IT-CS EN-HE EN-HE: T1 : MCA + Tax blocks EN-HE: furet removal EN-HE: Electrical cabinet refurbish.