Activities TS week 13 Production for test area On-going design studies Activities TS week 19&25. Hi gh Rad iation to Mat erials WG3 – Experimental Area. Ans Pardons– EN/MEF. HiRadMat project Team Meeting 14/04/2011. HiRadMat. Installed week 13, total dose ~1mSv.
E N D
Activities TS week 13 • Production for test area • On-going design studies • Activities TS week 19&25 High Radiationto Materials WG3 – Experimental Area Ans Pardons– EN/MEF HiRadMat project Team Meeting 14/04/2011
HiRadMat • Installed week 13, total dose ~1mSv TS week 13: Construction Dump 4m downstream of T9 T9 Support TED Dump 4m Dump 4m Ans Pardons EN/MEF
HiRadMat TED support&dump installed, TED installed (and removed), new collimator installed, roof closed (±) Total dose preparation: ~0.9mSv, installation: ~0.2mSv TS week 13: Installation TED Ans Pardons EN/MEF
HiRadMat TED support&dump installed, TED installed (and removed), new collimator installed, roof closed (±) TS week 13: Installation TED Interference between crane lifting beam and new (downstream) roofblock Solution: use intermediate hooks (made for test tables) Short hook (for comparison) No interference Intermediate hook Ans Pardons EN/MEF
HiRadMat • Priority: base tables: • Reception aluminium support structure: week 15 assembly week 16 • Reception tables plates: week 17 add to support structure & paint week 17 • Reception additional small pieces (wedges, ...): week 18 final assembly of entire table week 18 &start of week 19 for installation week 19 • Intermediate crane hooks (also for closing T9 shielding) • Reception hooks: week 16 closing roof can in short access (assuming we can use “monte-charge”) • Structure for passage of cables to test stand • Study on-going, orders week 16, reception probably for week 19 Production for Test area & Muon Dump Ans Pardons EN/MEF
HiRadMat • Passage cables in TNC Material – slope – remote installation & dismounting Design studies Ans Pardons EN/MEF
HiRadMat • Remote dismounting base tables • Chariot for test tables Design studies Ans Pardons EN/MEF
HiRadMat (liste non-exhaustive, en ordre chronologique) • Installation ventilation autour de T9 (2 jours, PP) • Ouverture toit, installation TED, fermeture toit T9 (1 à 2 jours, YS, DG) prêt pour installation BPKG • Installation tables de base et alignement (2 jours, ML, DDP, KB) (plus test de manutention si temps disponible, autrement pendant prochain arrêt) prêt pour installation BLMs • Pose peigne et pose câbles d’expérience (à confirmer, GG) • Installation supports en zone de décroissance (ML, DDP) (plus test de manutention si temps disponible, autrement prochain arrêt) • Installation supports plaques marbres et blocs acier (si temps disponible, autrement pendant prochain arrêt) • Nettoyage, peinture Activities week 19 (pardon my French) Ans Pardons EN/MEF