SLC PHASE 2 ST KENNETHS PRIMARY SCHOOL PARENT COUNCIL MEETING

respect. integrity. innovation. collaboration. excellence. SLC PHASE 2 ST KENNETHS PRIMARY SCHOOL PARENT COUNCIL MEETING . ALISDAIR ELLIOT – CONSTRUCTION MANAGER. 1. ST KENNETHS PRIMARY SCHOOL PARENT COUNCIL MEETING . 2.0 Project Overview & Images 3.0 BLL Project Team & Logistics

shasta
Download Presentation

SLC PHASE 2 ST KENNETHS PRIMARY SCHOOL PARENT COUNCIL MEETING

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. respect integrity innovation collaboration excellence SLC PHASE 2 ST KENNETHS PRIMARY SCHOOLPARENT COUNCIL MEETING ALISDAIR ELLIOT – CONSTRUCTION MANAGER 1

  2. ST KENNETHS PRIMARY SCHOOL PARENT COUNCIL MEETING 2.0 Project Overview & Images 3.0 BLL Project Team & Logistics 4.0 Current Progress & Phase 2 / 3 Transition 5.0 Q & A Close 1.0 Introduction and Agenda SECTION 1 2

  3. ST KENNETHSPRIMARY SCHOOL 2.0 The Project 2.1 Project Overview 2.2 Images SECTION 2 3

  4. ST KENNETHS PRIMARY SCHOOL2.1 Project Overview The project: This project is our fourth new-build primary school building to be constructed within Phase 2 Tranche 1 of the South Lanarkshire Primary Schools Modernisation Programme. The Client: South Lanarkshire Council The Contract: PPC 2000 (Partnering framework contract agreement) Overview: The project comprises the tandem build construction of a new two-storey 16 classroom primary school. In addition to the classrooms, the building comprises private and main stream nurseries, a double gym hall, general purpose room, library and IT Suite. The new building is located within the existing school campus, formerly the location of the existing sport pitch and car park. The works are being carried out in two phases to allow the existing school to operate whilst the new building is under construction. On completion of the new school building the users will decant from existing to new allowing progression into phase 2 where the scope is to remove asbestos from the existing school, demolish the building, complete the sports pitch and finish the hard and soft landscaping. Construction: The construction of the primary school is a steel frame structure with holorib decking topped with a concrete floor slab on pads/strip foundations. The building will have predominantly a facing brick outer leaf with areas of metal cladding and curtain walling on the elevations. The roof will be an aluminium standing seam roof throughout. Internally, underfloor heating has been incorporated throughout the building with fit out specification aligning with other projects in the programme. Externally, the scheme includes external hard and soft landscaping and lighting design scheme complete with a standard 60 x 40 metre sports pitch, car parking / pupil drop off with playground & soft play areas around the school/nursery. 4

  5. ST KENNETHS PRIMARY SCHOOL2.2 Images 5

  6. ST KENNETHS PRIMARY SCHOOL 3.0 PROJECT TEAM / SITE LOGISTICS 3.0 Project Team & Site Logistics 3.1 BLL Design Team 3.2 BLL Construction Team 3.3 Site Logistics SECTION 3 6

  7. Architect Structural Engineer Cost Consultant Services Engineer ST KENNETHS PRIMARY SCHOOL 3.1 BLL Design Team This is the design team engaged upon the St Kenneth’s Primary School Project 7

  8. GORDON ANDERSON Regional Director ED PARRY Commercial Director ANDY STRONACH Framework Manager TRACEY-LEIGH FINDLAY Framework Commercial Manager CORE TEAM BARRY O’HAGAN Framework Delivery Manager TOM CAIRNEY Framework Safety Manager EMMA ROBB Commercial Manager Alisdair Elliot Construction Site Manager DESIGN TEAM DELIVERY TEAM Michael McMullan Construction Manager (Part) OMAR AHMED WAZIR Planning Manager TBC Finishes Construction Manager (Part) ST KENNETHS PRIMARY SCHOOL3.2 BLL Construction Team 8

  9. ST KENNETHS PRIMARY SCHOOL 3.3 Site Logistics – Overall Phasing Diagram 9

  10. ST KENNETHS PRIMARY SCHOOL 3.3 Site Logistics – Phase 1 Logistics 10

  11. ST KENNETHS PRIMARY SCHOOL 3.3 Site Logistics – Phase 2 Logistics 11

  12. ST KENNETHS PRIMARY SCHOOL 3.3 Site Logistics – Phase 3 Logistics 12

  13. ST KENNETHS PRIMARY SCHOOL 3.0 PROJECT TEAM / SITE LOGISTICS 4.0 Programme 4.1 Current Progress 4.2 Phase 2 / 3 Transition SECTION 4 13

  14. ST KENNETHS PRIMARY SCHOOL4.1 Current Progress PROGRESS Bovis Lend Lease are currently reporting works on programme with all works due for completion 23/07/10 • Works on site at present comprise the following: • External Works • External Brickwork • Curtain Walling Windows and Doors • External Cladding 14

  15. ST KENNETHS PRIMARY SCHOOL4.1 Current Progress • Internal Works • Interior Fit Out (Joinerwork, floor finishes, suspended ceilings) • Mechanical & Electrical Installation • Architectural Metalwork • Decoration • Gym Fit Out 15

  16. ST KENNETHS PRIMARY SCHOOL4.2 Phase 2 / 3 Transition Bovis Lend Lease are scheduled to take possession of the Phase 3 site on the 30 July 2010 and commence preparation works for demolition of the existing school. Demolition of the existing school is scheduled to be completed during November 2010. Following which BLL will install synthetic sports pitch and carry out further hard and soft landscaping works BLL are scheduled to complete all Phase 3 works during January 2011 BLL are intending to use the existing delivery entrance of East Mains Road to service the Phase 3 works 16

  17. ST KENNETHS PRIMARY SCHOOL PARENT COUNCIL MEETING 5.0 Q & A Close SECTION 5 17