IBL CO 2 cooling planning 03 July 2013

bverlaat@nikhef.nl. IBL CO 2 cooling planning 03 July 2013. Jan Godlewski, Bart Verlaat, Lukasz Zwalinski. IBL CO 2 cooling sub units. Several sub projects all with their own planning Fluid systems: CO2 circulation plants (2x) CO2 accumulator Unit (1x) R404a chiller units (2x)

shilah
Download Presentation

IBL CO 2 cooling planning 03 July 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. bverlaat@nikhef.nl IBL CO2 cooling planning03 July 2013 Jan Godlewski, Bart Verlaat, LukaszZwalinski

  2. IBL CO2 cooling sub units • Several sub projects all with their own planning • Fluid systems: • CO2 circulation plants (2x) • CO2 accumulator Unit (1x) • R404a chiller units (2x) • Vacuum transfer line (97m) • Junction box (1x) • Manifold box (2x) • Flex lines (14x) • Support systems • Vacuum system • Electronics • CO2 control cabinets (2x) • Maintenance control cabinet (1x inside accu unit) • Chiller control (2x, inside chiller units) • Vacuum control cabinet (1x) Inside USX Inside USA

  3. Assembly and commission approach • Cooling system commissioning will be done via the junction box dummy load. • Target for hardware installation =>September - December 2013. • 1st circulation before xmas (cooling the xmas Champaign bottle!) • Commissioning campaign January- April 2014 • IBL cooling connection after IBL installation • Cold tests with IBL from June to September Manifold box Flex lines Junction box 3kW dummy heater Pump Transfer line Cooling plant (2x CO2 + 1x accu + 2x chiller)

  4. Current focus • Current focus is on the hardware needed for junction box commissioning. • Fluid systems: • CO2 circulation plants (2x) • CO2 accumulator Unit (1x) • R404a chiller units (2x) • Vacuum transfer line (97m) • Junction box (1x) • Manifold box (2x) • Flex lines (14x) • Support systems • Vacuum system • Electronics • CO2 control cabinets (2x) • Maintenance control cabinet (1x inside accu unit) • Chiller control (2x, inside chiller units) • Vacuum control cabinet (1x) • Commissioning is a length process: • Tuning of PID parameters • Make it work in full phase space of temperature and heat load • Test procedures like start-up, switch over, standby, back-out. Needed for junction box commissioning Needed after IBL installation

  5. Road to CO2 circulation • Rough schedule of units (Everything will be directly installed in the pit): • CO2 plants: Nikhef delivery begin of September. • Activities: Cabling and IO checks • Possibility of local CO2 circulation using fill bottle as accumulator and small chiller as condenser • Accumulator unit end of September: • Activities: Cabling and IO checks • CO2 filling for specific accu tests • Chiller units delivery half October • Activities: Cabling and I\O checks • Direct connection to CO2 plant, circulation for test possible • Transfer line installation: 4 weeks in October • Installation of Junction box in October • Inter connection of units with orbital welding in November • 1st circulation of Junction box in December. • See detailed planning in Excel file in this meetings indico.

  6. Road to IBL cooling • Commissioning via junction box and dummy load (January to April 2014). • Test all procedures • Tune parameters • Long duration testing • During junction box commissioning focus on other hardware like • Vacuum system • Flex line integration • Manifolds • IBL installation in March 2014 • IBL to cooling connection in April-May 2014 • Flex lines will be installed after the IBL is in. • IBL with cooling commissioning: June to September 2014 • Beam pipe back-out October 2014. • When still alive IBL with cooling is ready for physics! • See detailed planning in Excel file in this meetings indico.