1 / 13

GEO 600 detector status report (S4)

GEO 600 detector status report (S4). K.A. Strain for the GEO 600 team. LSC Meeting LLO, March 2005 LIGO-G050094-00-Z. GEO600 optical layout (S4). 600m. Attenuated to 5W. interferometer with dual recycling. mode cleaners. 12W laser. ~1% Transmission. detector. Site (S4).

shiloh
Download Presentation

GEO 600 detector status report (S4)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GEO600 detector status report (S4) K.A. Strain for the GEO600 team LSC Meeting LLO, March 2005 LIGO-G050094-00-Z

  2. GEO600 optical layout (S4) 600m Attenuated to 5W interferometer with dual recycling mode cleaners 12W laser ~1% Transmission detector

  3. Site (S4) • Container-city grows

  4. Progress (post S3 to preS4) • Improvements to michelson and signal recycling loops • less noise at low frequency through gain redistribution etc. • general reduction of RFI by improved signal handling • Substantial reduction of collimated-backscatter from several optics • most importantly those handling the “arm pick-off” beam used to obtain SR control signals (components repositioned or removed) • now normally no scattering problem • Modest increase in injected and circulating power (using almost half of the power from the 12W laser now) • 1 kHz performance limited by mixture of shot and dark noise

  5. Progress (S3 to S4) • Noise projection work • all major linear contributions now tracked (control noise, amplitude noise, oscillator phase noise …) • some of the couplings tracked continuously to allow investigation of potential vetos • Calibration • full on-line calibration of the two instrumental output quadratures (“HP”, “HQ”) • remember detuned SR gives nearly SSB at response peak so nearly equal signal in P,Q. “HP” has more information <1 KHz, HQ > 1kHz • combination of HP and HQ signals to get h(t) • optimal signal recovery, some SNR increase

  6. Progress (S3 to S4) • Computer / data exchange infrastructure • additional supervisory control computers • general upgrade of supervisory control computers to increase reliability, now very few problems • extension of on-site storage and various minor enhancements and upgrades of data handling computer infrastructure • rapid generation and publication of calibrated frames • many on-line monitors provided • summary reports generated

  7. Sensitivity – Pre S4 example line: 150 Hz 200 Hz 250 Hz pump 820 Hz 32 violin modes +harmonics 4kHz RFI peak preliminary calibration

  8. Continuous calibration • continuous injection of calibration lines • fitting of parameters (optical gain) to measured line amplitudes • sophisticated control model used to aid good fit • inverse filters calculated and applied to error point signals to produce HP and HQ • random error due to parameter miss-estimation is kept small • main uncertainty is systematic (overall gain) due to difficulty of establishing electrostatic drive response • long term plan to use separate calibration “actuator” • on-line calibration and good reliability allowed unattended frequent overnight runs

  9. optical On-line optical TF measurements P and Q CAL actuator

  10. Combining HP and HQ - example result • Resulting HQ’ contains almost no signal compared to HP’ -> h(t) • Noise cancels in some frequency regions, is uncorrelated in others

  11. 10 -21 10 -22 10 -23 10 1 2 3 10 10 10 Noise Projections - example Proj Det+shot -17 10 Proj FP-MCE-HV Proj FP-MCEI-MCNI Proj FP-MSR Proj MIC_VIS -18 10 Proj MID_VIS Proj Uncorr. Sum HP -19 10 -20 ASD [h/rt(Hz)] Frequency [Hz]

  12. S4 • Pre S4: one fault developed <24 hours before S4 - fixed just in time • Early S4: intermittent fault in suspended EO modulator • reduced data quality for some times (part of some nights) about 10 bad periods of a few hours • problem identified and fixed • may (dis)qualify affected data where appropriate • duty cycle • many long lock stretches (up to >105s) • over 35 100% 8-hour shifts so far • only 2 shifts < 90% • two shifts (16hr /day) with experts on call (automated SMS calling 24/7)

  13. Some next steps • Post S4 checks and calibrations • actuator calibration • checking vetos arising from noise projection work • Review of S4 after ~1 month • Exchange of T~1% MPR for one with T~1000 ppm • some changes to the control systems • will make acquisition more complex • increased thermal effect in BS may increase contrast defect, but we have modulation index capability to spare • currently contrast defect is ~10-6 • probably do not require OMC • Noise reduction and tuning to lower frequency to improve overlap with L1/H1/H2

More Related