An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TDC2/TCC2 Réunion de chantier 3 08.11.2013 In sharepoint: https://espace.cern.ch/sba-workspace/tcc2wg/LS1%20worksite%20meeting/

  2. Agenda • TCSC • Fuite vide • Statut démontage • Cellule stockage TCSC au B.955 • Echange QNL de TT20 • Proposition blindage plomb • Préparation retrait splitter • Planning

  3. Fuite vide Fuite non détectée, retour à d bonnes conditions de vide

  4. Cellule blindage TCSC

  5. Aimants QNL a remplacer dans le TT20 PPG.21161 porte interzone à franchir maintenir ouverte durant l’opération Roulage coté Jura dans le TT20 Aimant QNL a remplacer Réinstallation de l’aimant neuf dans la foulée. Temps total de l’opération: 2-3jours Planification: Apres le retrait du TCSC (environ fin novembre) Transfert coté Jura à coté Salève. Chambre à vide à démonter.

  6. Proposition blindage plomb (F. Loprete, EN-STI)

  7. Proposition blindage plomb (F. Loprete, EN-STI)

  8. Préparation retrait splitters • Impacts • Retrait TCSC :  37401 • Retrait 5 aimants (3 splitter et 2 MDLV) : 37405 • Vacuum : 37404 SVP rajouter les intervenants ! • EDH transport et stockage QNL, splitters et MDLV • VIC (pour tous les aimants le jeudi 14 AM) • Impact

  9. Planning (proposition)