1 / 22

B. Jeanneret, CTC, 24th August 2010 With material thanks to

Drive Beam Linac , Surface lines & building DB+MB, 500 GeV Bypass for the DB, Power for the DB. B. Jeanneret, CTC, 24th August 2010 With material thanks to G. McMonagle , E.Jensen , R. Wegner , A. Aksoy , D. Siemaszko & D. Nisbet , J. Osborne, N. Baddams

shiri
Download Presentation

B. Jeanneret, CTC, 24th August 2010 With material thanks to

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Drive BeamLinac, Surface lines & building DB+MB,500 GeVBypass for the DB,Power for the DB B. Jeanneret, CTC, 24th August 2010 Withmaterialthanks to G. McMonagle ,E.Jensen, R. Wegner, A. Aksoy, D. Siemaszko & D. Nisbet, J. Osborne, N. Baddams L. Rinolfi, D.Schulte

  2. DB Linacs

  3. DB Linacparameters

  4. Cell structureR. Wegner, E. Jensen, A, Aksoy, D. Schulte • RF active section : 20 cells × 0.1m = 2m • Coupler, interconnect : 0.5 m • Quad, MBCO, BPM : 0.6 m • TOTAL : 3.1 m • May needadjustement ( Vacuum equip. for pressure p ~ 5 10-11 Torr, … ) 15 MW klystrons Acc. V/module 3.2 MV 819 cells / linac Total length 2540 m Plug-power for RF (2 linacs): 290 MW ( 0.115 MW/m) 3100 Linac 1

  5. Magnets – quadrupoles • N=819 Q, spaced by 3.1m for eachLinac (total Linaclength 2540m) • R = 3.7 10-2Ω, Imax = I0 = 414 A, pmax = 6.3 kW • Gradient must follow the beamenergyincrease • I(n) = nI0/N • Power schemesimilar to DECEL_Q advisable • Total power : P = Npmax/3 = 4 MW I(n) I0 = 414 A 1 (s=0) N=819 (s=2540m)

  6. Power & Cooling • Total plug power for RF : Ptot = 290 MW • 140 MW to beam150 MW to heat • Total power for magnets (Quad + Sol): 9 MW to heat • Total installed power : • Pinstalled = (1+ ε) × ( 290 + 9 ) • withε the 18kV conversion yield (seewith Daniel/Cesary) • Add for light, cranes, safetysystems, … • Total cooling power (tunnel & surf. Blg) : • Pcool = (1+ ε) × ( 150 + 9 )

  7. DB Linac, tunnel • Total lengthnow : 2540 m • conflictwith EHN1 •  move towards top of the drawing, seebelow Water cooling pipes, Cabletrays Loads 1200 3000 1000 1000 800 6000

  8. 2m DB Linac building Top view (half) 3.1m Width: 23.5m Height: 9m ? Length : 2540 m 0.75m 3m 5m 3m Klystrons are transported along the central path. A technical area without RF must beforeseenat crane extremities End view (half) 11.75m 3.5m ? 3m 1.5m 2.5m 4m 2m

  9. Top View of DB Linac xx • A small building isneeded for 18kV station ~ everyyy = 40 m ? • Size : xx by xx , xx = ? • Installed power 4.6 MW/40m xx Awaiting data From RF and EL • Still to beworked-out • withCesary ~yy 23500

  10. Top view of DB Linac buildings 2140 m 23 m 30 m Fixed point (beforedelayloops) 420 m Underground & surface (slide 6 & 7) Underground, Same section as in slide 6 (CDR, to berevised for TDR)

  11. Surface layout

  12. Site implementation DB Linac (undergroud and surface) - Long segment : 2140 m - Short segment : 420 m Widthnow 23m But annexblgs for 18kV missing  Use 30m as average

  13. 500 GeVdelayedtransfer for the drive beam B.Jeanneret , July 2010

  14. Input data • Time delaybetween e+ & e- DB train : • The two sets of 5 trains each 240 ns are produced one after the otherwith a single Linac • Δt = 5 × 24 × 240 ns = 28800 ns Δ = 8640 m • The trains must besynchronouswhen passing along the end of the Main Linac

  15. Option I : Coming back to surface Case 1 G D C I H F TA • Case 1 : • e+ trains come first and go through : AFGHI-TA-IHGFBCD • e- trains go through : AFGHI • Case 2 : • e- trains come first and go through : ABCD-TA-DCBFGHI • e+ trains go through : ABCD r x From CR2 B A Blue : additionalbeam line Red : additional tunnel D,I : end of ML Case 2 G D C I H F x TA r From CR2 B A • AG = 770 • GH = 1449 • HI = CD = 25 (500GeV) • AC = 2117 • AB = 2r = 524 • TA = 146 • With y = AG+GH+AC+2*HI • x = (Δ + 2r – y –TA)/2 • x(case1) = x(case2) = 2316 m See ~/clic/CDR/500gev/bypath.sce

  16. Option II : Use a by-patharound IP-- Preferred case -- • D,I : end of ML (500 GeV) • e+ in D & e-in I : synchronous • Δdb = 8640 • ID = 2×1870 , TA = 146 • δbp = 14 • x = (Δdb - δbp - ID –TA)/2 = 2361 m • x / Lsector = 2361/877 = 2.70 sectors IP I D C x TA From CR2 A see :/Users/Bernard/clic/CDR/500gev/bypath_ugnd.sce

  17. Impact for hardware / underground by-path • x / Lsector = 2361/877 = 2.7 sectors • one extra DB line to behoused in the main tunnel • Civ. Eng. : • 374 m of tunnel to beadded for by-path • 1 additionnalturn-around , of type ‘DB’ • Additionalbeamlines: • 3740 m ( DI ) of type ‘DB-LTL’ • 1 dedicatedturn-around , of type ‘DB’ • Beamlines not needed : • Surface loop & descent down (2460 m) • Advantage : disconnectedfrom surface changes for Main Beam Alexey, Michele

  18. Experimental area and by-path

  19. Power for the DB

  20. All power data in MW

  21. Summary for drive beam powerEnd-Linac Enter Decelerator

More Related