Hans Verheij Owner. Justin Schmidt University of Wisconsin – Madison Construction. Nathan Johnson Georgia Tech Architect. John Swallow University of Manchester Engineer. Noor Atari Stanford Engineer. Megan Folkmann Stanford Engineer. Site Location.
E N D
Hans Verheij Owner Justin Schmidt University of Wisconsin – Madison Construction Nathan Johnson Georgia Tech Architect John Swallow University of Manchester Engineer Noor Atari Stanford Engineer Megan Folkmann Stanford Engineer
Site Location University of New Mexico -Educational Building -Urban Environment -Environmentally Sensitive Cactus Grove -Sustainable Design -Existing Footprint Existing Footprint - The ‘L’ Shape
Key Challenges Floor Height -Atrium • Site Constraints • -Cacti, size Structural System -Materials • MEP System • -Lack of technical knowledge
Site Diagram Circulation Cores Building Footprint Internal Atrium Entrance Paths A Building as an Open Mind
First Floor First Floor Auditorium Bathrooms Large Classrooms Glass Curtain Wall
Second Floor Communal Student Offices Computer Labs Small Classrooms Glass Curtain Wall Bathrooms
Third Floor Faculty Offices Seminar / Meeting Room Admin. / Secretary Faculty Lounge Bathrooms
Basement Plan Storage Mechanical room Elevator Room Computer Machine Room
Section 1 2nd Floor Plan 1st 3rd 2nd
Section 2 2nd Floor Plan 3rd 1st 2nd
Renderings View From Cornell Drive Interior Views
Renderings View From Cactus Grove
Structural Modeling SAP MRF - 27’ Bay SAP MRF - 18’ Bay
Queen Post Truss Queen Post
Albuquerque Geology • GIVEN INFORMATION: • Compact sandy, silty material • Allowable bearing • pressure ~ 4KSF • Upper layers are • predominantly of a • sedimentary material
Foundation Load TOTAL FACTORED LOADINGS: Concrete 3334 K Steel 406 K Cladding 1044 K Live Load 1566 K TOTAL LOADING: 6350 k
Foundation Load Information Theoretical area of foundation required: 6350 K / 4 KSF = 1587 square feet Based on an assumed 5’ wide strip/pad foundation, actual area of foundation provided = 3305 square feet Provided area of foundation is acceptable
Atrium Glass Wall GSW Headquarters, Berlin
Glass Wall Details 18” GSW Headquarters, Berlin
Adobe Panels Single 6’ Panel Detail Section
Adobe Panel Fixing Prefabricated beams used to hang the Adobe panels
Equipment Selection • Rough Terrain Crane • 83 ft boom • Outriggers fully extended at furthest pick • Geothermal Boring Rig • Extend to 300’
Budget Final Budget $7,062,194 Back to Present Value at 3% Inflation Invested with 5% Rate of Return
Estimate Total Cost: $8,294,824
Estimate Night Sky System, 2.4% Plumbing, 1.6% Underground HVAC, 3.4% Geothermal, 6% Radiant Ceiling Panels, 5.6% Conventional HVAC, 1.4% Total Mechanical Cost: $1,693,025
Life-Cycle Costing Modeled using eQUEST Energy Simulation Tool Basic Gas Costs $13,310/year Basic Electrical Costs $42,633/year
Justification • Innovative Design • Comfortable User Space • Complements Surroundings • Life-cycle Payback • Government Funding • Conservatively Estimated
Scheduling Begin Site Mobilization: September 30th, 2015
Schedule Highlights Install Main Mechanical Equip: December 15, 2015 Install Elevator: February 23, 2016 Early Move-In: May 3rd, 2016 Project Completion: September 22, 2016
Spring - When can we meet? Solution: Shorter frequent meetings M – Administrative W – Problem solving F – Accessible hours
Process Improvements Wednesday/Friday meetings Use classroom time for problem solving Mentor meetings Fishbowl Utilize mentors Create a detailed schedule and stick with it Calendars and agendas galore Increase in daily interaction on ThinkTank and email Work together on tasks