Status of FMD

Status of FMD. Comprehensive Review CERN, 23 March 2004 Jens Jørgen Gaardhøje Niels Bohr Institute. Integration and mechanical issues Sensors Preamp-shaper chips Hybrids Read-out strategy FMD-TDR. Forward detector overview. Beam and FMD support cone RB26 side.

taini
Download Presentation

Status of FMD

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status of FMD Comprehensive Review CERN, 23 March 2004 Jens Jørgen Gaardhøje Niels Bohr Institute • Integration and mechanical issues • Sensors • Preamp-shaper chips • Hybrids • Read-out strategy • FMD-TDR Jens Jørgen Gaardhøje, NBI

  2. Forward detector overview Jens Jørgen Gaardhøje, NBI

  3. Beam and FMD support coneRB26 side Jens Jørgen Gaardhøje, NBI

  4. Finite element calculations of beam pipe support stresses Prototype beam-pipe support structure (crucial for LHC) in construction at NBI 33 m Displacements Less than 50 mum Jens Jørgen Gaardhøje, NBI

  5. Installation Sequence 2 1 4 3 Jens Jørgen Gaardhøje, NBI

  6. FMD sensors 512 strips 256 strips Inner module Final negotiations with (Micron/Hamamatsu) ongoing. Outer module Jens Jørgen Gaardhøje, NBI

  7. Custom preamp-shaper chip VA1_ALICE 50 m input pitch Jens Jørgen Gaardhøje, NBI

  8. VA1_ALICE noise simulations Jens Jørgen Gaardhøje, NBI

  9. Hybrids Inner module VA1_ALICE (128 channels) pitch adapter (ceramics) bonding (CERN) Sensor - Custom production of adapted VA1 - Hybrid design settled with IDEAS. Connectors for power, control, read-out, bias Jens Jørgen Gaardhøje, NBI

  10. Radiation environment Doses and Fluences in Central ALICE (10 years running): FMD: 4.2 cm | | 28 cm Belle measurements SSD2 TPC(in) Doses in FMD: =0.31 Mrd Jens Jørgen Gaardhøje, NBI

  11. FMD Read-Out and Control Electronics IN COUNTING ROOM ON DETECTOR NEAR PATCH PANEL FMD Module Front-end bus  1 m Analog serial link (10 MHz)  0.5 m FMD Digitizer RCU ALTRO (16 ch) Data Proc. and Memory  16 Bus controller ( conf. & R/O) DDL ALTRO (16 ch) DAQ int. (DDL-SIU) BOARD ALTRO (16 ch) DCS BOARD controller DCS int. (Ethernet) CTRL Local Monitor and Control TTC-RX TTC optical Link (Clock, L1 and L2 ) Read-out CTRL Trigger int. (TTC-rx) VA Control Network (I2C-serial link) VA read-out control Trigger L0 1 ring: 10/20 modules 2 Digitizers 1 RCU per ring system Full FMD: 70 modules 10 Digitizers 3 RCU’s BSN, 17 Feb 2004 New read-out strategy Jens Jørgen Gaardhøje, NBI

  12. New RCU location DAQ RCU FMDD Jens Jørgen Gaardhøje, NBI

  13. Error estimates per run Estimates of SEU High Energetic Hadron Flux (@ TPCin): 250 – 550 hadrons / sec • cm2 Error rate per run (4 hours) per device FEC 3•10-4 RCU 1.5•10-2 DCS 3•10-2 Jens Jørgen Gaardhøje, NBI

  14. FMD and TDR milestonesDetailed schedule for 2004 Jens Jørgen Gaardhøje, NBI

  15. Overall schedule2004-2006 Jens Jørgen Gaardhøje, NBI