INFN Perugia INFN Firenze CERN. M.Lenti. Separate pions from muons <1% level between 15 and 35 GeV /c Track time at 100 ps level Partecipate in the L0 trigger. Mirrors. RICH. 17 m. Beam Pipe. Neon as Cherenkov radiator mosaic of mirrors (17 m focal length )
E N D
INFN Perugia INFN Firenze CERN M.Lenti • Separate pionsfrommuons <1% levelbetween 15 and 35 GeV/c • Tracktime at 100 ps level • Partecipate in the L0 trigger Mirrors RICH 17 m Beam Pipe • Neon asCherenkovradiator • mosaicofmirrors (17 m focallength) • twospotswith PM (1000 PM per spot) • beam pipe passingthrough PM lodging disk
NIM A593 (2008) 314-318 NIM A621 (2010) 205-211 RICH prototyperesults 15 GeV/c 35 GeV/c msuppression: 0.7% ( 15<p<35 GeV/c) M.Lenti
Milestones: • Design formirrorsupport: 30.06.2011 • Vessel installationready: 30.04.2012 • Mirror and PM installation complete: 2.12.2012
Vessel (CERN): vacuumproof ! Gas system simplified: makevacuum, theninject pure Neon M.Lenti
Vessel tender notsubmittedyet (CERN responsibility) M.Lenti
Photomultipliers • 1944 PM available (quality test ongoing) • 2000 HV divider in preparation (custom made) PM mechanics in fabrication FE electronics in preparation M.Lenti
RICH PMs PM Timeresolutionmeasurementsmade in Perugia M.Lenti
PM HV dividers SOLDERED HV+ (GND) TOP AND BOTTOM SMD COMPONENTS COAX SHIELD AND HV+ SOLDERED TOGETHER SIG OUT COAX SOLDERED HV- CONNECTION M.Lenti
HV Filterboard BRACKET TO FIX BOARD TO THE 9U EMPTY CHASSIS SHV CONNECTOR FROM CAEN HV-PS 32 CH HV TO PMT SPACERS SUPPORT FOR SECURITY COVER M.Lenti
Electronicschain VME RICH FE 32 CH BOARD PRE_NINO NINO_CHIP TELL 62 BIPOLAR HV CABLE VHDCI CONN GAIN DIFF PMT RG174 MADISON UNIVERSAL TM CABLE FOR 130 OHM DIFFERENTIAL FOR LVDS SIGNAL 50 OHM TERMINATOR PCB MICROSTRIP 50-52 OHM DIFFERENTIAL FOR NINO CHIP MATCHING PCB MICROSTRIP 130 OHM DIFFERENTIAL FOR CABLE MATCHING M.Lenti
FE board 340 mm MAX. 220 mm MIN. 120 mm DC/DC CONVERTER 3.3 TO 2.5V 8CH NINO CHIP J1 VME CONNECTOR 8CH NINO CHIP 32 LEMO COAX SIGNAL FROM PMT 360 mm 32 CH VHDCI CONNECTOR TO TELL62 32 CHANNEL FRONT-END AREA G 8CH NINO CHIP 4CH MULTIPLICITY TO TELL62 I2C 8CH NINO CHIP CAN BUS CONNECTORS CAN M.Lenti CUSTOMIZABLE FRONT END (“FE”)AREA “DAQ” AREA
DAQ • TEL62 boardequippedwith 4 HPTDC: 512 ch • 4 TEL62 forall PM (2000 ch) • 1 TEL62 for “multiplicity” trigger (250 ch) • Perugia groupworks on the TEL62 fimware and trigger • SeeM.Sozzi report fordetails M.Lenti
Mirrors • Allmirrorsready (18 hex + 2 semi-hex), now at CERN • Quality test made in Italy in may 2011 • Coatingtobedone at CERN • Mirrorsupport system with a “dummy” mirror: • hung at the center • alignedwithmicrometricpiezo.motors V.Carassitiwillengeneerize the mirrorsupport system In the fall 2011 M.Lenti
Lab’s OpticalMeasurementsLab 12.4.2011 DummyMirror in CleanRoom 12.4.2011 M.Lenti
Hex10 Hex10 in Box3 (28.04.2011) Hex10 in box (29.04.2011) Hex10 in OpticsLab (29.04.2011) M.Lenti
Hex10 Horiz. Sigma Vert. Sigma DistLaser-Mirror: 33.875 m DistMirror-Diode: 33.985 m Minimum: +0.6 cm R = (33.875+33.985+0.006)/2 = 33.933 m F = R/2 = 16.967 m σX(min) = 0.20 mm σy(min) = 0.13 mm √(σX*σY)(min) = 0.12 mm Fx-Fy: +4.2 cm Horiz.*Vert. Sigma(2) M.Lenti
A. Cassese M.Lenti
MirrorSupport The Mirrorissupportedthroughone hole in the back where a dowel isinserted. The Mirrorisfalling: the dowelis touching the mirrornot in the barycenter Actuatingribbonworksagainst g and gives verticalaxisalignment A secondactuatingribbon at 90 deggives the horizontalaxisalignment Piezomotors are usedto pull the ribbons System heavilytested in Lab in Firenze M.Lenti
MirrorSupportPanel Goal: engeneer project by the end of 2011, then go for tender (INFN responsibility) M.Lenti
Milestones RICH 2012 • Installazione dei PM e dell'elettronica di FE 31.08.2012 • Installazione degli specchi 31.08.2012 M.Lenti
RICH Schedule V8.4 (baseline) Assumes Rich vessel in time for TR today Very short time window To get ready for the TR Temp. installation… M.Lenti
RICH Schedule V8.42 (back-up) Non-conform with baseline planning today TR Outside beam periods M.Lenti In this scenario the RICH could only be used if there is a window to prolong the TR in 2013 !
Conclusions • Lotof progress on manyitemsof RICH • Vessel production (CERN responsibility) delayed • Mirrorsupport system tobefinalized • The RICH is on the criticalpathforseptember 2012 technicalrun M.Lenti
Richieste Firenze 2012 INTERNO Totale: 10.00 1. Riunioni con gli altri gruppi italiani di NA62 e riunioni del gruppo RICH 10.00 ESTERO Totale: 64.00 1. meeting di analisi e collaborazione al CERN: 8 MU 32.00 2. Installazione al CERN del rivelatore RICH: 4 MU 16.00 3. Technicalrun di NA62: 4 MU 16.00 CONSUMO Totale: 153.00 1. Electronic Pool del CERN: noleggio moduli di elettronica 20.00 2. Common Fund della collaborazione NA62 100.00 3. Metabolismo 10.00 4. Installazione al CERN del rivelatore RICH 20.00 5. Noleggio auto al CERN per l'installazione ed il technicalrun 3.00 APPARATI Totale: 25.00 1. Installazione e test dell'elettronica di front-end del rivelatore RICH (CORE 2012) 25.00 Totale NA62 Firenze 252.00 M.Lenti
Richieste Perugia 2012 INTERNO Totale: 18.00 1. Riunioni e attività in Italia per RICH e TDAQ (Firenze, Pisa, Frascati) 12.00 2. Riunioni in Italia 6.00 ESTERO Totale: 76.00 1. Installazione rivelatori (RICH, TDAQ): 4 m.u. 16.00 2. Commissioningrun: : 6 m.u. (previsione durata run: 6 settimane) 24.00 3. Riunioni di analisi e di collaborazione (7 riunioni) al CERN o presso altre istituzioni estere, riunioni e "workinggroup" sul rivelatore e per la preparazione del commissioningrun (9 m.u.) 36.00 CONSUMO Totale: 32.50 1. Installazione rivelatori al CERN 10.00 2. Metabolismo ricerca 10.00 3. Attività TDAQ (1 PC x sviluppo firmware L0: 2k€; 2 schede di rete 10Gbit: 1k€; TDAQ spare: 1 Tel62: 3.5k€; 2 TDCB nuova produzione con cavi: 3k€; consumo di laboratorio per riutilizzo elettronica esistente di NA62 per lettura CHOD di NA48 nel commissioningrun 2012: 3k€) 12.50 TRASPORTI Totale: 1.00 1. Trasporto materiale ordinato 1.00 LICENZE-SW Totale: 2.00 1. Licenze Software Altera (convenzione Università) 2.00 APPARATI Totale: 25.00 1. Completamento HV RICH (residuo CORE) 25.00 SPSERVIZI Totale: 6.00 1. Spese consumo per servizi 6.00 Totale NA62 Perugia 160.50 M.Lenti