An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Community of Evaluators Conclave ProgressEvaluation for Development - 2013

  2. Content - Progress • Programme drafted. • Invitation sent; follow-up being done. • Concept notes have been received. • Virtual conferencing for M Q Patton

  3. Content – Challenges • Bringing in more members to review the draft notes • What is the EvalPartners Agenda for their meeting! • Panel confirmations!

  4. Content – Work to be done • Follow-up on Concept notes – 30th Nov • Review of Concept Notes – 15th Dec • Programme finalised – 15th Dec • Facilitators and Co-Facilitators list ready – 15th Dec • Schedule printed and circulated – 15th Dec • Interactive schedule available on site – 20th Dec • Concept note and biographies of facilitators - published onsite – 20th Dec • CoE meeting agenda finalised and circulated – 15th Dec

  5. EM & Logistics - Progress • Venue arranged. • Event Management contracted to IDOBRO. • Vendors identification in process. • Collaterals finalised and work begun. • Comparative activity chart agreed. • YES – Logistics partner identified in Nepal. • Broad workplan developed in conjunction with CoE Nepal. • Logistics information being collected. • Coordination support from CoE Nepal finalised. • Task Team meetings being conducted.

  6. EM & Logistics – Challenges • Larger Task Team for some of the tasks - during the conclave • Quick clarity on venue, quality of vendors, products and hotels • Clarity and agreement in roles and responsibilities

  7. EM & Logistics – Work to be done(1) • Vendors finalised – 30th Nov • Design for venue and collaterals finalised – 15th Dec • Collaterals & promotional - agreed, designed – 15th Dec • Travel & visa for invitees, members – 30th Dec • Registration – Details prepared, completed – 30th Jan • Inauguration and closing arrangements made – 30thJan

  8. EM & Logistics – Work to be done(2) • Technical arrangements – Audio, visuals, Net – 30th Jan • To include live streaming/ live blogging/ tweeting • Anchors for various sessions – finalised – 15th Dec • Rapporteurs finalised – 30th Jan • Evaluation of the conclave designed – 30thJan • Accommodation for participants – 30th Dec

  9. EM & Logistics – Work to be done(3) • Media partner identified and journalists invited – 30th Dec • Local volunteers identified and engaged – 30th Dec • Sight seeing arrangements made – 30th Jan • Food and beverages coordinated. • Teaching and learning aids arranged – 30thJan

  10. EM & Logistics – Work to be done(4) • Pick-up and drop facility, accommodation for non-invitees and other travel arrangements made – 30th Jan • Finance – Estimate made, procedure laid down, money arranged, payments made – 30thJan • Separate venue for CoE meeting – 30th Jan • Conclave report finalised – 30th Mar

  11. Media - Progress • Himal South Asia identified as possible media partner • Media outlets defined and contacted • Accounts created in for Facebook, LinkedIn, Twitter • Press release drafted • Task Team meetings being held.

  12. Media – Challenges • Ensure that conclave is covered and published • Main message needs to be brought into focus • Identify media outlets in Sri Lanka

  13. Media – Work to be done • Media partner finalised and role agreed-15th Dec • Press release - pre and post event prepared – 15th Dec • Accredited journalists invited-15th Dec • Media outlets contacted-30th Nov • Press release sent to the media outlets-15th Dec • Social media resource hired to create an online presence and buzz-15th Dec • Daily press release drafted and circulated • Live tweeting and blogging • Journalists given access to keynote speakers, workshop leaders for conclave coverage

  14. Resource Mobilisation - Progress • Rockefeller Foundation • USD 50,000 grant; 20 – 25 participants; • Expected by January 2013 • Discussion with PACT; • Paper work to be clarified by Dennis • CLEAR • Scope of work submitted; • Expected by January 2013; • USD 40,000 from IDRC; • INR 22,00,000 from Conclave – I; • Cost for Coordination support from CoE Nepal – added.

  15. Resource Mobilisation - Challenges • Conclave cost is high • Sponsorship for panelists • Resource generation through registration -200 participants

  16. Res. Mob. – Work to be done • Paper formalities completed and fund received from RF and CLEAR – 15th Jan • Resources generated through registration of participants - 200 participants – 15th Jan • Surplus from first conclave to be redirected – 7th Jan

  17. Marketing - Progress • Offline • Regional events - 8 events planned • Media identified • Conclave advertised twice in List Serves and also sent to Evaluation Association • Financial support provided • Task Team meeting conducted.

  18. Marketing – Challenges • Resource mobilisation - through registration of paid participants in all countries • To be taken up by members • Graduated incentive system for conclave participation for CoE members.

  19. Marketing - Milestones • Regional Event conducted – 30th Dec • Perspective participants for the conclave and members for CoE identified • Online and offline marketing strategies documented and pursued – 15th Dec • Short audio/ video prepared for marketing conclave offline – 15th Dec • Graduated incentive system for members for participation in the event – 15th Dec • Conclave - I participants contacted for participating in the second conclave – 30th Nov

  20. Phase - II

  21. Actions Planned(1) • New Knowledge • Publishing articles through existing journals • Documentation of innovation • Establish website as an interactive platform • Supporting evaluation panel • Capacity Building • Organising evaluation conclave • Supporting regional events • Moderated discussion groups • Networking with other institutions/ groups

  22. Actions Planned(2) • Network and Advocacy • Increasing membership • Online networking and communication • Building connections with other evaluation societies • Liaison with the government • Professionalisation of Evaluation • Code of Conduct • Quality standards • Ethical guidelines • Protocol for engaging with members, government and other evaluation associations

  23. Actions Planned(3) • Institutionalisation • Registration of CoE • Selection of Governing body • Chairperson • Vice-Chairperson • Secretary General • Selection of General Body • Resource Mobilisation • Approach other associations and donors • Identify large funding opportunities, submit proposals • Membership fee collection

  24. Phase II – Progress(1) • New Knowledge • Edited volume compiled; expected to be published soon • New CoE website in place • Note on documentation of innovation – drafted and shared • Note on online journal drafted • Capacity building • Conclave preparation - in progress • New conclave website • Regional events - planned and being organised

  25. Phase II – Progress (2) • Network and advocacy • EvalPartners has members from CoE • CLEAR – Collaboration initiated • SLEvA – Continuing from Phase- I • Networking with MES, AEA, IOCE, AfREA – initiated • Outreach improved through Newsletter • New members registered • Professionalisation of Evaluation • Desk research completed • Institutionalisation • To be under Section – 25 Companies Act, India • MOA, AOA Drafted • Registration attempted

  26. Phase II – Challenges • Increasing membership base • Institutionalisation • Sharing of responsibilities by all members • Business planning • Resource mobilisation • Sustainability

  27. Phase II – Work to be done(1) • New Knowledge • Edited volume published – 15th Feb • CoE site established as an interactive platform – 30th Dec • Searchable database for members • Discussion board • Online journal • Innovations in evaluation documented – Oct 13 • Moderated discussion group – Mar 2013

  28. Phase II – Work to be done(2) • Capacity Building • Evaluation Conclave completed successfully – 7th Mar • Regional events conducted successfully – 30th Dec • Scope of work agreed with CLEAR and EvalPartners and partnership formalised – 30th Dec • Knowledge products developed – Jun 2013 • Focussed CB event and mentoring support offered – Jul 2013

  29. Phase II – Milestone(3) • Networking and Advocacy • How to support country specific CoE - Scope of work finalised – 30th Dec • Membership – 30th Jan • Responsibility and Incentives systems for members developed, agreed and circulated • Membership drive conducted and members increased to 100 • Strategy for Liaison with government – Drafted 15th Dec

  30. Phase II – Milestone(4) • Professionalisation of Evaluation • First draft of standards, ethics and protocols prepared – 30th Jan • Institutionalisation – 15th Feb • MoA and AoA reviewed, revised and redrafted • Application for name submitted • Application for registration submitted • Board and Executive Committee selected

  31. Phase II – Milestone(5) • Resource Mobilisation • Proposal submitted to EC – Not successful • Governance • SAT formulated and regular meeting facilitated • Members • Solomon Chelladurai • Shubh Kumar-Range • Mallika Samaranayake • Gana Pati Ojha

  32. Phase II – Milestone(6) • Project management support • Face to Face meeting in New Delhi on 1st and 2nd February 2012; • Skype meetings on 25th February, 14 April, 28th April and 30th May; • Face to Face meeting in Kathmandu, Nepal from 18th to 19th June 2012; • COE Visit to Nepal for identification of venue for the conclave; • Meeting with CLEAR South Asia in Delhi; • Meeting with EvalPartners in Delhi; • Face to Face meeting in Dhaka; • Meeting with PACT/RF • Six monthly financial and technical report submitted to IDRC