Superconducting Cavities for Super-KEKB

Superconducting Cavities for Super-KEKB. S. Mitsunobu. Summary of KEKB SCC Operation. Max. Current 1 270m A Max. Power for Beam      380k W HOM Power 1 4k W Operation Voltage  1.4-2.0 MV Average Trip rate is once per month for good vacuum condition. KEKB SC  Super-KEKB SC.

Download Presentation

Superconducting Cavities for Super-KEKB

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Superconducting Cavities for Super-KEKB S. Mitsunobu

  2. Summary of KEKB SCC Operation • Max. Current1270mA • Max. Power for Beam      380kW • HOM Power14kW • Operation Voltage  1.4-2.0 MV • Average Trip rate is once per month for good vacuum condition. .

  3. KEKB SC  Super-KEKB SC • Cavity Field 1.4-2.0MV OK • Input Coupler 380kw 460kW OK(500kW) • Input Coupler Qext 7x104  5x104 • HOM Power 10 kW  60kW (test 43 kW) • Large Gate Valve D=220mm to be solved • Add 4 Cavities • Larger Sigma z should be studied

  4. Dedicated 1 MW klystron system for coupler test bench Testing high power coupler, at D10 area new 1MW klystron power supply and klystron system have been constructed. One of limitation of high power operation for KEKB coupler is heating at capacitor for bias voltage. An air duct is added near this capacitor to increase cooling power. Couplers could operate more than 500 kW.

  5. Cap of Doorknob Air Duct

  6. HOM Damper • Cooling limit (4.0m/sec ) 60kW • Inner Surface Temperature Limit 200 ℃ • KEKB 80kw with 4A at 3mm BL(2.5pC) • D=220 mm Beam Pipe 56 kW(4A,3mm) • KWKB could be operate (4A, 4MM, 1.8pC) P=k(σz)・I**2/frev/Nb

  7. A SBP HOM damper have been tested up to 18 kW and 25 kW for LBP HOM damper.

  8. Acoustic monitor attached

  9. Artificial acoustic signal breaking pencil lead of 0.5mm

  10. Crab cavity • Crab cavities will be install in KEKB ring next winter shutdown. • New crab cavity design for SKEKB have been proposed by Akai.

  11. New crab cavity (Coaxial type) • (Left) The cross-shaped waveguide dampers and coaxial dampers are attached at the squashed-cell. • (Right) Cross section of the coaxial damper at the cut plane of Y-Y’. Proposed by Akai

  12. Summary • KEKB SC will be used with small modification for Super-KEKB. • Coupler already tested more than 500kW(800kW in short time),beam test will be done. • HOM damper is most important issue for Super-KEKB SC. (43kW reached) • Crab cavities going to be test soon.