SE 12 th Street. Roadway Improvements. February 8, 2005. N. PROJECT LOCATION. E. UNIVERSITY AVENUE. 26. 331. SE 12 th STREET. SE 1 st AVENUE. SE 11 th STREET. SE 2 nd AVENUE. PROJECT PURPOSE. Widen roadway and improve condition of pavement
E N D
SE 12th Street Roadway Improvements February 8, 2005
N PROJECT LOCATION E. UNIVERSITY AVENUE 26 331 SE 12th STREET SE 1st AVENUE SE 11th STREET SE 2nd AVENUE
PROJECT PURPOSE • Widen roadway and improve condition of pavement • Improve pedestrian access, movement and safety • Address residential flooding problems • Improve water quality of Rosewood Branch
DESIGN ELEMENTS • Reconstruction/widening of SE 12th Street • Addition of curb & gutter and storm drain system • Sidewalk and ADA-compliant ramps • Paved driveway entrances • Parking reconfiguration in commercial area • Construction of stormwater pond • Rosewood Branch stream bank stabilization
N PROPOSED IMPROVEMENTS E. UNIVERSITY AVENUE 26 • Roadway widened from 20’ to 24’ • Curb & gutter and storm drain system • Paved driveway entrances at all existing • locations • 6’ sidewalk along west side of • roadway for entire street length • 8’ sidewalk and parallel parking along east • side of street in front of commercial area • Utility relocations • Stormwater management (SWM) pond • south of SE 2nd Avenue for water quality • Grade and stabilize stream banks south of • SE 2nd Avenue 8’ SIDEWALK PARKING SE 1st AVENUE SE 12th STREET 6’ SIDEWALK SE 2nd AVENUE STREAM WORK SWM POND
ROADWAY TYPICAL SECTION Existing Roadway Proposed Typical Section
SE 12th STREET - Looking Towards SE 2ND Avenue Existing Conditions Artist’s Rendering
SE 2nd AVENUE AT SE 12TH STREET (Looking East) Existing Conditions Artist’s Rendering
SE 12th STREET AT SE 2nd AVENUE (Looking North) Existing Conditions Artist’s Rendering
SE 12th STREET - Looking At East University Avenue Existing Conditions Artist’s Rendering
ROSEWOOD BRANCH STREAM WORK • New endwall • Stabilize stream banks • Lay back slopes • Revegetation • Erosion Protection • Reforestation
CONSTRUCTION GOALS • Minimize disruptions to residents and businesses • Keep all impacts within City right-of-way • Grading for sidewalk • Driveway entrance tie-ins • Maintain one lane of traffic at all times during construction • Road to be closed to through traffic • Access for local residents only • Maintain access to all residential/commercial driveways/entrances • Complete construction as quickly as possible
PROJECT SCHEDULE We Are Here