SC Link Point 1 and Point 5J.P. Corso EN-MEF-INTY. Muttoni EN-MEF-INT 1st HiLumi LHC/LARP Collaboration meeting
Overview • Geographical location • Equipment at point 1 • Equipment at point 5 1st HiLumi LHC/LARP Collaboration meeting
Geographical location Point 5 LHC Point 1 1st HiLumi LHC/LARP Collaboration meeting
Point 1 1st HiLumi LHC/LARP Collaboration meeting
Point 1 Top viewShafts 1st HiLumi LHC/LARP Collaboration meeting
Point 1 Top view Buildings 1st HiLumi LHC/LARP Collaboration meeting
Point 1 Top View Underground 1st HiLumi LHC/LARP Collaboration meeting
Geographical location UJ14 LHC Insertions Upgrade Working Group (LIUWG) 20-03-2008
Equipment in place IP1 Q3 DFBX Warm D1 UJ13 1st HiLumi LHC/LARP Collaboration meeting
Point 1 Left Machine Equipment IP1 IP1 UJ14 DFBX Q3 UJ13 Warm D1 1st HiLumi LHC/LARP Collaboration meeting
Equipment in place UJ14 IP1 UJ14 New SC link should be installed to connect underground equipment machine and surface electrical equipment. Q2 RB14 1st HiLumi LHC/LARP Collaboration meeting
Equipment in place UJ14 All the equipment should be installed in a new surface building. IP1 UJ14 LHC Insertions Upgrade Working Group (LIUWG) 20-03-2008
Geographical location UL14 LHC Insertions Upgrade Working Group (LIUWG) 20-03-2008
By pass building UL14 SC link pass in this gallery. UL14 1st Floor UL14 Ground Floor 1st HiLumi LHC/LARP Collaboration meeting
Geographical location US15/PM15 LHC Insertions Upgrade Working Group (LIUWG) 20-03-2008
Shaft PM15 (Height ~ 85 meter) The two SC link pass in the shaft. One from right side One from left side. 1st HiLumi LHC/LARP Collaboration meeting
Building SD1 A way should be found for the two SC link. PM15 1st HiLumi LHC/LARP Collaboration meeting
Building SD1 1st HiLumi LHC/LARP Collaboration meeting
New building SD1 All the equipment moved from UJ14 and UJ16 should be installed in this new surface building. 1st HiLumi LHC/LARP Collaboration meeting
Point 5 1st HiLumi LHC/LARP Collaboration meeting
Point 5 Top viewShafts 1st HiLumi LHC/LARP Collaboration meeting
Point 5 Top view Buildings 1st HiLumi LHC/LARP Collaboration meeting
Point 5 Top View Underground 1st HiLumi LHC/LARP Collaboration meeting
Geographical location RZ54 1st HiLumi LHC/LARP Collaboration meeting
Point 5 Left Machine Equipment RZ54 Q3 DFBX IP5 IP5 Warm D1 1st HiLumi LHC/LARP Collaboration meeting
Equipment in place RZ54-USC55 New shaft for SC Link Height ~85 meter LHC Insertions Upgrade Working Group (LIUWG) 20-03-2008
Equipment in place RZ54-USC55 Some equipment should be installed in a new surface building. See next slide. LHC Insertions Upgrade Working Group (LIUWG) 20-03-2008
Point 5 New surface building Left side 1st HiLumi LHC/LARP Collaboration meeting
Geographical location UJ56 1st HiLumi LHC/LARP Collaboration meeting
Point 5 Right Machine Equipment IP5 DFBX Q3 UJ56 Warm D1 IP5 UJ57 1st HiLumi LHC/LARP Collaboration meeting
Equipment in place UJ56 Way for SC Link from surface to underground should be studied. Some equipment should be installed in a new surface building. No space found yet. LHC Insertions Upgrade Working Group (LIUWG) 20-03-2008
Point 5 New surface building* Right side * A place must be found 1st HiLumi LHC/LARP Collaboration meeting
Thanks for your attentionQuestions? 1st HiLumi LHC/LARP Collaboration meeting