140 likes | 344 Views
INDEPENDENT COST ESTIMATES AND COST REVIEWS. Michael Peek, PE CCE CFM Office of Engineering and Construction Management. Click to LOOK INSIDE!. INDEPENDENT COST ESTIMATES AND COST REVIEWS. EINSTEIN’s Abbreviated Guide To. E = Mc 2 = TPC =. But what should it really cost?.
E N D
INDEPENDENT COST ESTIMATESANDCOST REVIEWS Michael Peek, PE CCE CFM Office of Engineering and Construction Management
Click to LOOK INSIDE! INDEPENDENT COST ESTIMATES AND COST REVIEWS EINSTEIN’s Abbreviated GuideTo E = Mc2 = TPC = • But what should it really cost? Michael Peek, PE CCE CFM
Why Independent Cost Estimatesand Cost Reviews? We cannot solve our problems with the same thinking we used when we created them. Albert Einstein • Support Secretarial/Acquisition Executive decision making • Logical “next step”… increase focus on front-end planning • Address External Stakeholder Concerns • Consistent with GAO Best Practices Guidelines (GAO-09-3SP) • Adopt Industry Standards • Requirements addressed in DOE O 413.3B • Statutory requirement … mandated in FY2012 Consolidated Appropriations Act (P.L. 112-74)
DOE O 413.3B Requirements • If you can't explain it simply, you don't understand it well enough. Albert Einstein • With the implementation of DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets, the Office of Engineering and Construction Management is required to conduct an Independent Cost Review (ICR) and/or develop an Independent Cost Estimate (ICE) to support the Secretarial Acquisition Executive’s (SAE)/Acquisition Executive’s (AE) decision at various Critical Decision (CD) milestones …
FY2012 Consolidated Appropriations Act Requirements (P.L. 112-74) A perfection of means, and confusion of aims, seems to be our main problem. Albert Einstein • Sec 308: None of the funds made available in this title may be used to approve critical decision-2 or critical decision-3 under Department of Energy Order 413.3B, or any successive departmental guidance, for construction projects where the total project cost exceeds $100,000,000, until a separate independent cost estimate has been developed for the project for that critical decision.
Best Practices The only source of knowledge is experience. Albert Einstein • GAO Cost Estimating and Assessment Guide: Best Practices for Developing and Managing Capital Program Costs, March 2009 (GAO-09-3SP) • Association for the Advancement of Cost Engineering International (AACEI) • Recommended Practices • Professional Practice Guides • Society of Cost Estimating and Analysis (SCEA) • Cost Estimating Body of Knowledge (CEBok) • DOE G 413.3-21 Cost Estimating Guide, May 2011
High Quality Cost Estimate Any intelligent fool can make things bigger and more complex... It takes a touch of genius - and a lot of courage to move in the opposite direction. Albert Einstein • Characteristics: • Comprehensive … addresses all known costs appropriate for the level of project definition • Well-documented ... basis of estimate allows for independent replication and updating • Accurate … is free from errors and omissions • Credible … is well structured and presented in an industry accepted format
Basis of Estimate • Everything should be made as simple as possible, but not simpler. Albert Einstein • A well prepared Basis of Estimate (BOE): • Documents overall project scope … • Facilitates review and validation of the cost estimate … • Alerts project team to potential cost risks and opportunities … • Record of key communications made during estimate preparation … • Establishes initial baseline for scope, quantities and cost for use in cost trending … • Source of support during dispute resolutions … • Provides historical relationships between estimates …
The Cost Estimate Everything that can be counted does not necessarily count; everything that counts cannot necessarily be counted. Albert Einstein • Identify/Focus on Cost Drivers • Cost drivers require a detailed independent estimate • Early technical, cost and schedule risk identification • Methodology • Bottom-up • Parametric Cost Models & Cost Estimating Relationships • Engineering judgment • Vendor quotes/vendor proposals • Updated throughout the project cycle … • Trend should cost versus will cost
Other Initiatives • I have no special talent. I am only passionately curious Albert Einstein • Historical Cost Data • Identify useful Cost Estimating Relationships … focusing on 10 selected projects • Percent of TPC devoted to specific project phases • Evaluation of Program Cost Estimates • Start-up & Commissioning CERs of special interest • WBS Best Practices Handbook • Product oriented… collaborate on standardization by project type… • Common element structure to capture cost data for common scope across projects …
Other Initiatives The only thing that interferes with my learning is my education. Albert Einstein • Evaluating existing data sources and estimating tools across DOE … • CEES @ Oak Ridge; ECAS @ EM CBC • PARS II & ACDB (ACEIT) @ OECM • Promote cost estimating consistency … • Common framework within each Program • Increased sharing of existing cost data • Address inflation indices … • Program Office/PMSO and EFCOG support critical for success …
Bottom Line Anyone who doesn't take truth seriously in small matters cannot be trusted in large ones either. Albert Einstein • A cost estimate is only as good as the project’s components … • Upfront planning - design maturity and technology readiness … • Risk identification and management … • Stable funding commitments … • Properly resourced staffing - numbers and skill sets … • Credible and consistent contract management and alignment … • Optimized oversight and reporting …
Take Aways Strive not to be a success, but rather to be of value. Albert Einstein • Independent Cost Estimates and Independent Cost Reviews should: • Enable Risk Informed Cost Effective Decisions • Support Mission, Program and Project Execution • Emphasis on Program and Project Accountability • Should Cost vs. Will Cost • Be based on industry accepted standards and processes
Questions? Unthinking respect for authority is the greatest enemy of the truth. Albert Einstein I OECM