LHC IRQ Cryostat Interim Design ReviewMarch 13, 2000T. Page - Fermilab
Topics • MCBX Corrector Mounting • Q2A / Q2B Weld Test • Interconnect Design T. Page
MCBX Corrector Mounting • Cantilever corrector off of Q2B end plate. • Four (4) mounting bolts. • 20 mm spacer between end plate and corrector for flow. T. Page
MCBX Corrector MountingANSYS Analysis • Determine the deflection due to it’s own weight. • Modeled just the 15mm thick outer aluminum cylinder. • Simulated weight = 1105 lbs. (500 kg). • Gravity load. • Fixed the end plate around the perimeter. • Specifications from IR Quad Alignment Table: • Corrector Displacement 500 m [.0197 in] • Corrector Roll 5 mrad T. Page
MCBX Corrector MountingANSYS Results - Deflection (inches) T. Page
MCBX Corrector MountingANSYS Results - Stress in Cylinder (psi) T. Page
MCBX Corrector MountingStatus • Initial design complete for MCBX to Q2B mounting. • Mounting ring design discussed with CERN and efforts are underway to integrate the ring into the MCBX design. • Same concept is proposed for mounting correctors to Q1 and Q3. • Q1 Lead End • Q3 Lead End • Q3 Non-Lead End • Awaiting more information on the KEK end plate design. Possible incompatibility with floating end plate design. T. Page
Q2A / Q2B Weld Test • Magnet Q2 consists of two cold masses that will be joined together to form one magnet. • Cold mass alignment issues • Magnetic Performance • Beam tube insertion • The “Weld Test” is an experiment to test the welded connection between cold masses Q2A and Q2B. T. Page
Q2A / Q2B Weld Test T. Page
Q2A / Q2B Weld TestProcedure • Clamp cold masses in place. • Shoot position of cold masses. • Weld together with interconnect skin. • Unclamp cold masses. • Shoot position. • Interested in final position relative to initial position. • Use bullet strain gauges to detect the deformation of the end plate. T. Page
Q2A / Q2B Weld TestFixture T. Page
Q2A / Q2B Weld TestFixture T. Page
Q2A / Q2B Weld TestStatus • Alignment targets are being fabricated. • Cold masses are being prepared for the test. • Weld fixture is in the process of being mounted to the assembly table. • Test is scheduled for April. T. Page
Interconnect Design • Three (3) Interconnects in the triplet. • Q1 to Q2 • Q2 to Q3 • Q3 to DFBX • Interconnect Kits • Interconnect Joints T. Page
Interconnect Design T. Page
Interconnect Design T. Page
Interconnect DesignKit • Not shown: • Absorber • Heat shields • MLI (insulation) • Outer vacuum bellows • Weld rings T. Page
Interconnect DesignClamped Joint T. Page
Interconnect DesignWelded Joint T. Page
Interconnect DesignStatus • All bellows are complete and drawings are being reviewed. • Outer vacuum bellows needs to be designed. • Interconnect shields need to be designed. T. Page