140 likes | 153 Views
This update provides highlights of control performance in April, compares performance to previous years, discusses compliance activities with entities, Texas RE delegation agreement, NERC reliability standards, and ERCOT bylaws. It also includes the 2008 Texas RE budget summary and information on reliability compliance monitoring and enforcement.
E N D
Compliance Update June 2007
Control Performance Highlights • NERC CPS1 Performance • April Performance • April performance comparison • April 2007: 126.92 • April 2006: 143.31 • 12 month rolling average comparison • May 2006 April 2007: 138.23 • May 2005 April 2006: 129.90 • PRR 525 Performance • Scores for April indicate 32 QSEs passed / 2 non-wind-only QSEs failed the measure • Scores posted on the ERCOT Compliance Website • SCE Performance Scores
ERO / RE Activities • Entity Registration • Continues to be a work-in-progress • ERCOT Compliance Staff working with entities to resolve concerns • Any entity can challenge its listing and function with NERC • Appeals heard by the NERC Board Compliance Committee • Texas Regional Entity Delegation Agreement • ERCOT Board approved Texas RE Delegation Agreement on May 16th • Executed Texas RE Delegation Agreement re-filed at FERC on May 18th • FERC directives must be addressed and modifications filed within 180 days of the date of the order (mid-October) • NERC Reliability Standards • Mandatory compliance began on June 4th • Regional Entities to focus on most serious Reliability Standard violations until January 1, 2008 • ERCOT Bylaws • ERCOT Board approved changes to the ERCOT Bylaws incorporating the Texas RE on May 16th • ERCOT Membership vote in mid to late June
2008 Texas RE Budget Activities • First draft of Texas RE Budget and Business Plan submitted to NERC on May 11th • Special Texas RE Budget Meeting held on May 17th • Second draft of Texas RE Budget and final Business Plan submitted to NERC on June 1st • ERCOT Board approval to be requested on June 19th • Final draft of Texas RE Budget to be submitted to NERC by no later than July 12th • NERC Board approval anticipated on August 1st • NERC and Regional Entity budgets to be filed with FERC
2008 Texas RE Budget Summary • Adequate staffing needed to comply with FERC mandates and NERC requirements, including ERO Rules of Procedure • Process driven – very structured • Audits, investigations, and analyses • Tracking, reporting, and documentation • Increasing number of FERC approved reliability standards • Monetary penalties and non-monetary sanctions • Appeals of violations and penalties/sanctions • Must maintain clear independence from all owners, operators, and users of the bulk power system • Includes compliance monitoring of reliability-based ERCOT Protocols and Operating Guides as a separate and parallel process to the NERC Program
2008 Texas RE Budget Summary • 2008 proposed budget ~25% less than 2007 - $5,514,219 $4,144,849 • Additional staffing requested to keep pace with anticipated work load and regulatory requirements • Positions filled only when/if needed • Projected 2007 statutory spending ~$2.6M under budget • Original schedule was for mandatory standards compliance to begin January 1, 2007 – all positions were fully funded • Reduction in capital project expenditures • Unspent 2007 budget will be applied to the 2008 budget • Penalty money collected applied to subsequent years’ budget • ERCOT ISO applied to ERO Budget • All other Registered Entities’ applied to Texas RE Budget
Reliability Compliance Monitoring & Enforcement • ERCOT Protocols & Operating Guides • Texas RE – Monitors compliance and issues violation notices • PUCT – Compliance enforcement (issues penalties/sanctions) • NERC & Regional Reliability Standards • Texas RE – Monitors compliance and issues violation notices • Texas RE – Compliance enforcement (issues sanctions/penalties) • ERCOT ISO • 1 of 166 Registered Entities in ERCOT • 24/7 Reliability Coordinator Function – responsible for the real-time operating reliability of the ERCOT Region • Texas RE • Determines compliance and non-compliance • Reports non-compliance in a timely, meaningful manner • Does not monitor compliance in real-time • PUCT • Texas RE Hearing Body for appeals of NERC and Regional Reliability Standards violations and penalties/sanctions
NERC Standards Violation- Delegated Requirements No TRE issues violation notice & reports to PUCT Yes Protocol Violation? NERC Standards violation by the ERCOT ISO? No Issue Closed Yes TRE issues violation notice & penalty to the ERCOT ISO & reports to NERC No ERCOT ISO owes penalty Requirement Delegated? Issue Closed Yes No Protocol Violation? Issue Closed Yes TRE issues violation notice & reports to PUCT