12th March 2014 Conference The Hatton London, UK. CBTC from the start: 28 years of SkyTrain in Vancouver. Ian R Graham Manager (retiring) Operations Planning Expo/Millennium Lines BC Rapid Transit Company, Burnaby, Canada. 12th March 2014 Conference The Hatton London, UK.

Download Presentation

CBTC from the start: 28 years of SkyTrain in Vancouver

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 12th March 2014 ConferenceThe Hatton London, UK CBTC from the start:28 years of SkyTrain in Vancouver Ian R Graham Manager (retiring) Operations Planning Expo/Millennium Lines BC Rapid Transit Company, Burnaby, Canada

  2. 12th March 2014 ConferenceThe Hatton London, UK CBTC:More than a signalling system Ian R Graham Manager (retiring) Operations Planning Expo/Millennium Lines BC Rapid Transit Company, Burnaby, Canada

  3. Vancouver in context • >3 decades of history and development since 1980 – a different starting point now. • Green field – a clean start. • No regional interoperability issues. • Proprietary technology, but generally applicable experience.

  4. Vancouver, Canada • Canada’s 3rd largest city • metro area 2.5 million in 2013 • 3 million by 2027? • was 1.5 million in 1980 (SkyTrain decision)

  5. Technology • Urban Transportation Development Corporation (UTDC), now part of Bombardier • small lightweight cars • steerable trucks • linear induction motors (LIM) • SelTrac S40 inductive loop ATC system (Thales) • full operational dependence on primary system – no axle counters or other “backup” systems. • ongoing evolution of functionality around the original system principles

  6. Expo/Millennium Lines • 1986: 21 km / 15 stns / 114 cars / 20M pass/year • now: 49 km / 33 stns / 258 cars / 80M pass/year • 2016: plus 11 km / 6 stns / 28 cars • future: discussions of extensions; $$$?

  7. Canada Line:same but different • opened in 2009 • separate line (non-interoperable), but integral part of the transit system • P3 project with 30 year concession • 19 km / 16 stns / 40 cars (larger) / 40M pass/year • Rotem cars, with AC rotary motors • Seltrac ATC, similar to Expo/Millennium • generally similar operational approach

  8. 5 km 5 mi Millennium Line(2002) Evergreen Line(2016) Broadway-UBC(future) Expo Line(1986-1994) Canada Line(2009 - separate P3 operation) Surrey extension(future)

  9. The commitment to automate • Automation experience in the 1970’s • High dependence on signalling in “manual” systems • An attendant to watch a machine drive itself? • Eliminating the cab – no turning back

  10. Unattended Train Operation (UTO) • SkyTrain is: • not only automated • not only driverless • it operates trains primarily in unattended mode • Unchaining the driver from the cab makes a fundamental customer servicedifference. • The SkyTrain system is not unstaffed; • not about eliminating staff or unions

  11. Operating staff levels • BCRTC total 600 staff for O&M • Operations staff on duty (per shift) for: • 33 stations, 49 km, 22-57 trains • Field: • 38 SkyTrain Attendants (STAs) • 4 Field Supervisors • 1 Duty Manager • Control: • 7 Control Operators (ATC, power, alarms, communications) • 1 Duty Manager

  12. Original issues and concerns • No driver to view the track ahead • full track segregation • intrusion detection system (no platform screen doors) • No on-board personnel • passenger security features (intercom, alarm, PA) • door safety (positive interlocking; “pushback” feature) • system reliability and redundancy • Unattended stations • design, CCTV, communications; passenger self-service • => organizational confidence / public acceptance

  13. CBTC/UTO achievements (1) • throughput • 108 sec. sustained AM/PM 3-hour peaks • 96 sec. average, inner 6 stations, 2-hour AM peak • 95 sec. target future headway • 80 sec. “recovery” headway at terminus => 75 sec. potential • increased service frequency • same operating cost with shorter trains at higher frequency =>less waiting time for passenger • travel time (average in-service speed) • optimized and consistent speed control =>shorter travel time • headway consistency • all “drivers” are the same => variation and bunching are reduced

  14. CBTC/UTO achievements (2) • delay recovery • no recovery (rest) time required for drivers at end stations; insertion of spare trains in front of delayed train • schedule adjustments • additions or reductions based on demand • special events • additional trains without extra drivers (some extra staff may still be needed to manage crowds and supplement fare collection) • alternative service (planned / unplanned) • preplanned for maintenance, or unplanned for emergencies

  15. CBTC/UTO achievements (3) • safety • automated train control minimizes routine human error, although giving up opportunity for human discretion • fleet productivity • higher average speed and reduced end-station turnaround means fewer vehicles, and smaller yard, to serve the same ridership • yard flexibility and productivity • automation of storage lanes and some maintenance tracks allow trains to be launched, returned, and inspected, with minimal driving

  16. CBTC/UTO achievements (4) • fault response • SkyTrain Attendants (STAs) can deal with many train faults while the train is still in service, minimizing delay or disruption • passenger emergency • STAs can respond to passenger emergencies • customer assistance • STAs available to assist customers with directions, information, fare payment, etc.

  17. Ongoing and future challenges • Proprietary technology • Technology obsolescence and upgrades • Maintenance and upgrades of aging system • Growth – getting better to stay the same • “More than a signalling system” -- CBTC is not a “get and forget” system

  18. Conclusions A rapid transit system is always a “work in progress”. CBTC, and the related commitment to UTO, has provided Vancouver with a successful, well-used, efficient rapid transit system, and provided a relevant reference point to other cities around the world.