1 / 25

LTU/Undulator Commissioning Plans Heinz-Dieter Nuhn, SLAC / LCLS June 16, 2008

LTU/Undulator Commissioning Plans Heinz-Dieter Nuhn, SLAC / LCLS June 16, 2008. Overview Pre-Beam Checkouts LTU to Dump Commissioning (No Undulator Segments) Undulator Segments Commissioning Characterization of Spontaneous Synchrotron Radiation Characterization of SASE.

udell
Download Presentation

LTU/Undulator Commissioning Plans Heinz-Dieter Nuhn, SLAC / LCLS June 16, 2008

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LTU/Undulator Commissioning PlansHeinz-Dieter Nuhn, SLAC / LCLSJune 16, 2008 • Overview • Pre-Beam Checkouts • LTU to Dump Commissioning (No Undulator Segments) • Undulator Segments Commissioning • Characterization of Spontaneous Synchrotron Radiation • Characterization of SASE 1

  2. Related Presentations • Paul Emma, Commissioning Results and Plans • H. Tompkins, FEE/FEL Commissioning Overview • Richard Bionta, FEE Diagnostics and Commissioning 2

  3. J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A A M 2008 2009 2010 Down PPS LCLS Installation and Commissioning Time-Line First Light in FEE First Light in FEH PPS Cert. LTU/Dump LTU/Und/Dump Install Undulator Seg. Install X-Rays in NEH CD-4 (7/31/2010) FEE/NEH Install FEH Hutch BO FEH Install PEP-II run ends now LTU/Und Comm. Linac/BC2 Commissioning Re-commission Inj/BC2 to SL2 NEH Operations/ Commissioning FEE Comm. May 2, 2008 3

  4. 2008 2009 Beam-Based Commissioning A B C A: LTU – Dump B: Undulator Segments C: Spontaneous X-Rays D: SASE e--Beam D X-Ray 4

  5. LTU/Undulator e--Beam Commissioning Blocks • Installation and Conventional Alignment (=>Nov 08) • All beamline components except Undulator Segments • Pre-Beam Checkouts (Checklists will be prepared) (Oct-Dec 08) • LTU Section • Magnet Polarities / Motion (OTR, Collimators, Wire-scanners) / etc. • Undulator Section • Magnet Polarities / Motion (Girder, BFW, Slide) / ADS Calibration / etc. • Pre-Undulator Commissioning with Beam (Jan 09 – Mar 09) • LTU Section • Undulator Section (w/o Undulator Segments) • Motion Control / Beam Containment / Beam-Based Alignment / etc. • Beam Dump Section • Installation of Undulator Segments (Mar 09) • Undulator Commissioning with Beam (Mar 09 – Apr 09) • Beam Based Alignment / Undulator Slide Functions / Beam Stability A B 5

  6. LTU-to-Dump Pre-Beam Checkouts (Oct-Dec 08) • Undulator Hall HVAC System checkout (before Girder installation) • ADS (WPM & HLS) Control System checkout • ADS commissioning • EPICS Control System Checkout • Network Configuration of IOC's • Timing System • Communication with ADS Checkout • Verification of individual Device Operation • Magnet Power Supplies and Interlocks • Magnet Polarity Checkout • Dipoles • Quadrupoles • Correctors (where power supplies available) • BPM Cable Checkout • Motion Checkouts • Movable Collimator motion • Wire Scanner motion & calibration • Beam Finder Wire In/Out motion (BFW01 – BFW33) • Girder Motion Control checkout (33 Girders using external pos. sensors) • CAM Mover motion checkout • Transverse slide motion checkout • Compound motion checkout (Smooth beamline motion, System re-pointing) 6

  7. LTU Commissioning with Beam (Jan-Mar 09) A • Perform radiation surveys in BTH/FEE, etc with beam in the dump (Stan Mao, et al.) • Checkout BPMs (timing, scale, sign errors, etc.) • Test MPS (toroid collimators, BPMs, loss monitors, magnets, trip the beam, etc?) • Checkout optics using beam oscillation data (does a betatron oscillation fit the model well everywhere? – backwards quads?) • Test/checkout BYKIK and its abort dump and logic (MPS). • Test/checkout new OTR screens/cameras (OTR30, OTR33, and OTRDMP). • Test/checkout new wire scanners (WS31, 32, 33, 34). • Test/checkout new adjustable collimators (CEDL1, CEDL3, CX31, CY32, CX35, CY36) • Commission new energy and launch feedback loops. • Characterize beam, etc. 7

  8. Undulator Beamline Commissioning to Main Dump with Beam but without Undulator Segments (Jan-Mar 08) A • Commission Radiation Monitors • Get Beam through Undulator vacuum pipe with minimum losses. • Checkout BPMs (timing, scale, sign errors, etc.) • Commission Girder Motion with Beam • Verify and calibrate steering effect of quadrupole motion • Calibrate motion parameters (gain, pivot points etc.) • Check BPM offset tracking • Commission RF Cavity BPMs • Check charge dependent response over entire charge range • Use Girder Motion to calibrate position vs. readings • Check and correct optics matching over entire operational energy range • Commission Beam Based Alignment (BBA) • Develop saved configurations for three different energies. • Commission BBA GUIs and BBA procedure. • Commission Beam Finder Wires • Calibrate PMT signals. • Commission BFW GUIs (Alignment and scanning capabilities) • Commission ADS-based girder position stabilization feedback systems. • Commission Tune-Up Dump in preparation for commissioning with Undulator Segments 8

  9. Install Undulator Segments (Mar 09) • Mount Undulator Segments onto girdersSegments will be stored in Undulator Hall before installation • System is designed to be Self-Aligning • Re-check slide motion clearance • Expect to install 3 Segments / day 9

  10. First Beam Through Undulator Segments (Mar 09) B • Conditions for First Beam: • All Undulator Magnets Rolled-Out • Single Shot Operation (low charge) • Send single electron bunch through undulator • Read and evaluate as much diagnostics as possible along undulator(such as BPMs, beam loss monitors, toroids) • Identify and remove sources of beam loss – if any • Iterate • Goal: Get beam through vacuum chamber with minimum losses. • Reminder: Main Constraint is to Protect Undulator from Radiation Damage 10

  11. First Undulator Segments Commissioning (Mar – Apr 09) • Undulator Segments still in Roll-Out position • Run BBA • Roll-In Individual Undulator Segments • Transport beam through individual Undulator SegmentsStart at slot #33 (last Undulator Segment) • Check and correct trajectory change. • Run BBA with Undulator Segments inserted. • Check Segment alignment with BFWs B 11

  12. Commissioning of X-Ray Diagnostics (May – Jun 09) • Direct Imager • Slit • Solid Attenuator • Gas Attenuator • Gas Detector • Beam-Based K Measurement Components Minimum Requirement X-Ray Diagnostics is located after last Undulator Segment in Front-End Enclosure (FEE) See presentations by Tompkins and Bionta 12

  13. X Ray Diagnostics (FEE) 5 mm diameter collimators Soft X-Ray Offset mirror system Gas Detector Hard x-ray Monochromator (K Spectrometer) Direct Imager Solid Attenuator NFOV Slit Hard X-Ray Offset mirror system Total Energy Thermal Detector e- WFOV Gas Detector Start of Experimental Hutches Muon Shield Gas Attenuator See presentations by Tompkins and Bionta 13

  14. Characterization of Spontaneous Radiation (May – Jun 09) • Initially at 1.5 Å to reduce damage issue • Start at low charge • Repetition rate of 10 Hz or lower will be sufficient • Start to characterize radiation at last undulator Measure: • total spontaneous energy / pulse • spontaneous beam direction • temporal variation in spontaneous beam parameters • spatial distribution around first spontaneous harmonic • spontaneous radiation spectrum • wavelength of first harmonic • first harmonic wavelength spread • Characterize radiation from each individual Undulator • Measure relative K of Undulator pair. C Limited capability using K Spectrometer 14

  15. Measure synchrotron radiation spectrum produced by two undulator segments, and scan K of one segment K’s are matched when spectrum has the steepest slope on high energy side of 1st harmonic peak. Match segments pair-wise until all segments are measured. K Measurement: 2-Segment Scheme C undulator segments (33 total) segments under test 15

  16. Angle-Integrated Spontaneous Spectrum for 2 Undulators with DK/K = -0.2 to +0.2% C Dj = 0 Simulations P. Emma Dx = 3 mm DK/K = +0.2% • 0.1% rms e- energy jitter • 0.003% rms e- energy meas. resolution • 2% rms charge jitter • 0.5% charge meas. res. • 0.5s rms angle jitter • 105 photons/pulse/0.01% • 100 photon noise • 100 beam pulses with natural energy jitter only DK/K = 0% ~106 photons/nC/0.01%BW DK/K = -0.2% 16

  17. Characterization of SASE (Jul – Aug 09) D • Initially at 15 Å to maximize SASE gain • Start with reduced number of undulatorsRedo BBA after change of undulator configuration • Verify that electron beam meets requirements • Find SASE signal using Direct Imager • Use Laser-Heater modulation to control gain(7 Hz Lock-In Detection) if necessary • Repetition rate of 30 Hz (to support Lock-In Detection) • Optimize gain (through electron beam quality and BBA) • Measure gain length etc… 17

  18. FEL Measurements D • Measurements along undulator • Intensity (LG, Saturation) • Measurements after undulator • Photon wavelength • Photon wavelength spread • Pulse intensity • Pulse duration • Pulse centroid and direction • Spatial distribution • Jitter Saturation Exponential Gain Regime Undulator Regime 1 % of X-Ray Pulse Electron BunchMicro-Bunching 18

  19. SASE Characterization with FEE Diagnostics D • X-ray beam diagnostics located in FEE, down stream of last Undulator Segment • Obtain necessary z-dependent information through SASE gain shut-off at selectable points along undulator line by • Introduction of trajectory distortion or • Roll-out of individual undulator segments 19

  20. Measurement of SASE Gain Length Using Rollout D Undulator Segments can be rolled-out by remote control. Roll-out will start at the last Segment. Rolled-out Segments will not effect radiation produced by earlier segments. 20

  21. Summary • Plans for LTU/Undulator commissioning have been worked out and include • Detailed pre-beam checkout • LTU-Main Dump commissioning without Undulator Segments installed. • Installation of Undulator Segments. • Undulator Segment Commissioning • Characterization of Spontaneous Radiation will be combined with commissioning of X-Ray diagnostics suite in FEE • Beam based K-measurement method included. • Characterization of SASE will start at 15 Å • Gain length measurements will use FEE x-ray diagnostics combined with z-dependent SASE gain cut-off A B C D 21

  22. End of Presentation 22

  23. Application Software Development • LTU Emittance Measurement (Loos – extension of existing GUI) • Undulator Steering and re-Pointing (Nuhn) • Beta-Matching into the Undulator – with variable mean beta (Loos) • Beam-Based Alignment of the FEL Undulator (Loos) • Beam-Finder Wire Application – Centering & Emittance (Loos/Nuhn) • K-Measurement Application (Welch/Nuhn) • There will probably be more … 23

  24. Undulator Segment and TLD Replacement Program 2009 2010 24

  25. Measurement of SASE Gain Length withTrajectory Distortion D GENESIS Simulations by Z. Huang Quadrupole Displacement at Selectable Point along Undulator 25

More Related