420 likes | 559 Views
Activity report for year 2000 Manufacturing Unit Notebooks and Servers. JP CABRERA, MUNS Manager, 03/01/2001. MUNS Production Chart. Our Team Values. Polyvalence, Flexibility, Motivation, Involvement Autonomy, Professional integrity, Enthusiasm Presenteism, Punctuality
E N D
Activity report for year 2000 Manufacturing Unit Notebooks and Servers JP CABRERA, MUNS Manager, 03/01/2001
Our Team Values • Polyvalence, Flexibility, Motivation, Involvement • Autonomy, Professional integrity, Enthusiasm • Presenteism, Punctuality • Rigor, Method, Serious, Pro Activity • Dexterity, Rapidity, Agility, Reactivity • Competence, Knowledge, Confidence, Reliability • Communication, Respect for others, Welcome • Frankness, Team work, Competition • Innovation, Quality, Energy, Customer facing
Global process Engineering Purchasing Shipping Marketing Material Planning Quality Packing sales Order Admin Burn-in & Preload On Line Repair Production Planning Customers Brands NEC PBELL BULL US Assembly Maintenance Kitting Industrial Engineering Stockrooms Human Resources & Facilities Receiving
Production for Year 2K • 113511 notebooks • 20000 in December 2K (25000 in full year 1998) • average of 25 units per manufacturing order • 14282 servers • 15 models, racks and tower • 10 new product introductions • 2 units per manufacturing order (ATO) • 140000 accessories • for servers, notebooks and desktops • 10,5 M$ of stocks, 17500$ adjustment ie 0,0016%
Quality internal audit Y2K • Servers ( 30/03/2000) : Satisfaction : 95% • Remarks : • FA & security instruction not written : done • Notebooks (18/12/2000) : Satisfaction : 85% • Remarks and status : • procedure is not up to date : in progress • torque of screw drivers not calibrated : tool must be replaced, 19KF, Investment proposal to be done • ESD rules not respected : verify that everybody conforms the ESD rules • working instruction list not up to date : in progress
BUDGET Y2K : • Stockroom : • Actual (November) : 474729$ • Budget : 427719$ • Servers : • Actual : 402213$ • Budget : 641095$ • Notebooks : • Actual : 771892$ • Budget :611998$
Investments Y2K : • Stockroom : • Increase stockroom capacity in order to shorten the servers lead time : shelves + receiving • Amount = 48630$ • Notebooks : • Increase production capacity from 600/day to 900/day in order to achieve the target for end of the year : new layout + 6 trolleys for preload • Amount = 138000$
METHODS : • Quality measurement on the lines : • Acceptable Quality Level : cosmetics & docs • On Line Repair ratios • KAIZEN : the processes are always improved by the operators, in brainstorming meetings, controlled by leads or supervisors, • Progress group at receiving • Weekly meeting for OLR Quality improvement • Daily meeting for business & material management • New operators:2 days training + 3 (practice servers)
Capacity calculation : on Wednesday, 11:00 Capacity required by order admin Material availability Capacity calculation parameters = number of working hours or number of people Wednesday, 12:00 Mail : working hours & capacity for the following week
METHODS : 5S or Housekeeping • Quality can only grow in a clean workshop • Seiri = to throw away useless things • Seiton = everything at its place • Seiso = to clean • Seiketsu= to be methodical, organized • Shitsuke= to learn rigor
METHODS : New product Introduction Production: operator training, quality, routing times, efficiency, productivity, practice Purchasing Material planning Production planning MOs 1 unit for FA test Marketing Engineering Tests & support FA team : assembly method working instructions test process Products FCS dates roadmaps
Mission for the server production team • To produce servers • with Excellence in quality, • delivered in time to the customer, • and with respect of the budgeted costs. • This must be done with well trained people, in respect of the working conditions and environment, and continuously searching for improvement of the process.
Process for servers Packing 1 work station Shipping Burn-In 180 entry points Entry = 6 hours High = 12 hours Quality On Line Repair Nationalization kits Stockroom Assembly 10 work stations 45 mn (Average) Kitting Max Capacity : 300/day/3 shifts
Objectives and results for servers • Quality : • On Line repair, Objective : 6.7 % current : 6.8% • Non conform products • Process issues • assembly errors • DOA, Objective 1 % , current : 0.1% • Lead times : Objective : 4 days from order placed to FOB • current lead time : 10 days (average) • production cycle time : 3 days (average) • Costs : • productivity : Objective :4/day/operator, current 3,35
Production cycle for servers • J = order is placed in SOPSYS • J+1 = MO is planned at J+2 • J+2 = production, pretest, burn-in, • J+3 = delivery to shipping
Mission for the notebooks production team • To produce notebooks • with Excellence in quality, • delivered in time to the customer, • and with respect of the budgeted costs. • This must be done with well trained people, in respect of the working conditions and environment, and continuously searching for improvement of the process.
Process for notebooks Packing Shipping Pretest/Preload 192 entry points 3,5 hours Quality On Line Repair Nationalization kits Stockroom Assembly 12 work stations 10 mn (Average) Kitting Max Capacity : 900/day/3 shifts
Objectives and results for notebooks • Quality : • On Line repair, Objective : 2.7 % current : 2.7% • Non conform products • Process issues • assembly errors • DOA, Objective 2 % , current : 1% • Lead times : Objective : 3 days from order placed to FOB • current lead time : 10 days (average) • production cycle time : 3 days (average) • Costs : • productivity : Objective :4/day/operator, current 3
Production cycle for notebooks • J = order is placed in SOPSYS • J+1 = MO is planned at J+2 • J+2 = production, pretest, preload, • J+3 = delivery to shipping
Mission for the warehouse team • To receive and stock each component • with Excellence in inventory accuracy, • delivered in time to the productions or to the other warehouses, • and with respect of the budgeted costs. • This must be done with well trained people, in respect of the working conditions and environment, and continuously searching for improvement of the process.
Process for warehouse Prod. Planning Max Capacity : 900 notebooks or 50 MOs/day/3 shifts + 300 servers or 100 Mos/day/3 shifts + 50 Mos for accessories Office : following up of MOs Manufacturing Orders & picking lists Inventory Resupply Goods Docks Receiving Mass Stockroom Picking Stockroom Picking warehousemen Prekit preparation Protected Stockroom Production Shuttles
Inventory Adjustments Y2K 1999 2000 Transfer from St Sylvain
Weakness and axes of improvement • Global : • supply chain : forecasts accuracy, bids not taken in account, specific components with low volumes => suppliers not flexible • dependence of engineering on Boxborough • production planning : launch of production with components arriving the same day => shortages • too many temporary people => low skills level • Stockroom : • not enough space on the docks and shelves • no software for picking list nor MO grouping
Weakness and axes of improvement • Notebooks: • Quality management must be improved by 10 points • Floor and walls to be repaired • Servers : • Packing becomes very hard because of the weight of servers : a handling tool has to be developed, in progress • Not enough light on the line : budgeted, IP to be done • both Nb & Sv: • compressed air screw drivers : budgeted for 2001 • On Line working instructions : budgeted for 2001