An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CONVENTIONAL FACILITES MANAGEMENT

  2. Conventional Facilities Management • Staffing • Field Support: 7 UTR full time; 1 UTR part time • Office Support: 6 (including APD) full time; 3 part time • CM/GC and Trades: 18 Turner/HMM; 130-140 trades • Changes in Last 6 months • UTR staff reduced by one (tunnel inspector) • A/E coordinator on-site support reduced to part-time • Roll-off Plan developed

  3. Conventional Facilities Management • Change Order Request Technical Review Process • Potential Change Order (PCO) initiated by Turner with rough order-of-magnitude (ROM) estimate. • Trade contractor submits cost estimate for change. • Contract Administrator distributes to Conventional Facilities (CF) for evaluation of technical merit. • CF returns recommendation to Procurement for negotiation. • Contract Administrator finalizes negotiations and requests authorization (Requisition) from Project Office. • CF processes Baseline Change Request (BCR) and Requisition. • Contract Administrator issues Contract Modification.

  4. Conventional Facilities Management • In-house Estimating Service • Support provided by Jacobs Facilities • Dennis Day – on site • Supports Technical Evaluation Process. • Provides check estimates for Change Orders. • Provides estimating services for non-Turner. construction contracts.

  5. Conventional Facilities Management • Coordination with Procurement • Weekly Procurement Status to review: • Critical Procurement List • Advance Procurement Plan • Site Office approval process • Status of Change Orders/Field Change Orders • Status of Turner contract (invoicing, payments, etc) • Status of Jacobs Facilities contract (changes, modifications, payments, etc.)

  6. Conventional Facilities Management • Coordination with Procurement (continued) • Status of Change Order Requests / Field Change Orders • Review list of active CORS/FCO against PCO list. • Preliminary evaluation of merit of new PCO items. • Status of Technical evaluation of merit. • Prioritize pending actions. • As required • Daily interaction with technical evaluations, negotiation progress, other support from CF.

  7. Conventional Facilities Management • Non-Turner Construction Managed by CF • Electrical Substation – Awarded to Dynelectric • Contract value: $1.8M • Duration: 20 weeks • NTP: July 07 • Switchgear provided as GFE • BTH West Upgrades • Budget: $470K • Duration: 12 weeks • NTP: pending

  8. Conventional Facilities Management • Non-Turner Construction Managed by CF • Gas Line – PGE (pending DOE approval) • Contract Value: $33K • Duration: 10 weeks • NTP: pending • Gas Line – Meter to Central Utility Plant (CUP) • Contract Value: $80K • Duration: 8 weeks • NTP: pending

  9. Conventional Facilities Management • Non-Turner Construction Managed by CF • Bldg 028 & bldg 751 into LCLS Offices • Budget: $5M • Duration: 14 months • Both projects have design delay starts due to FY 08 budget constraints • No impact to CD 4 (July 2010) • FEH Hutches • Budget: $2.5M • Duration: 9 months

  10. Conventional Facilities Management • Jacobs Facilities • A/E Support • A/E Coordinator reduced to part-time • On-site estimator (full-time thru Dec 07) • Review of Submittals and RFI • Prepare Change Order documents • Structural Observations

  11. Conventional Facilities Management • 10CFR851 Worker Safety & Health Program • Contract change effective April 2007 • Additional ES&H requirements • Trade contractor to provide medical services • Burdensome of smaller contractors • Permissible Exposure Limits more restrictive • Possible increase in cost of construction • LCLS original flow-downs to TCCo already included the majority the requirements of 10CFR851

  12. Conventional Facilities Management end of presentation