Project Subcommittee. Subcommittee Purpose/Goals: Develop a master inventory of flood-related projects in the Chehalis Basin Seven sets of discussions: September 9 October 4 October 20 (Flood Authority Workshop) November 22 January 13 February 3 (Conference Call) March 1. Project Matrix.
E N D
Project Subcommittee • Subcommittee Purpose/Goals: • Develop a master inventory of flood-related projects in the Chehalis Basin • Seven sets of discussions: • September 9 • October 4 • October 20 (Flood Authority Workshop) • November 22 • January 13 • February 3 (Conference Call) • March 1
Project Matrix • Flood related projects from 15 different flood planning documents. • Chehalis Flood Authority Project List May 2011 • New Projects Proposed by Flood Authority Jurisdictions (11/22/2010) • Confederated Tribes of the Chehalis Reservation CFHMP (3/17/2009) • Chehalis River Basin Draft Comprehensive Flood Management Plan (June 2010) • Centralia Comprehensive Flood Management and Natural Hazards Mitigation (4/2011) • Thurston County Annual Progress Report – Implementing Flood Hazard Mitigation Initiatives in the Natural Hazards Mitigation Plan (8/11/2011) • City of Aberdeen Public Works Master Project List (January 2011) • ACOE Mitigation Projects in the Chehalis Basin • Grays Harbor County Draft Hazard Mitigation Plan 2001 • City of Chehalis Email from Bob Nacht 10/10/2011 • Lewis County Comprehensive Flood Hazard Management Plan • Grays Harbor County Draft Hazard Mitigation Plan 2011 • Description of Potential Enhancement Projects in Upper Chehalis Watershed • Chehalis Basin Watershed Management Plan • Chehalis Basin Partnership – Multi-Purpose Water Storage Assessment
Proposed Goal of Project Matrix • “The purpose of this matrix of projects is to reflect the Chehalis River Basin Flood Authority’s priorities to provide flood relief and protection in the basin.”
Project Matrix • Projects sorted into nine different sections • Floodplain Protection (includes retention, and levees/dikes • Reduction of Damage to Existing Structures • Bank Stabilization • Conveyance Capacity • Planning/Implementing and Data Collection • Education and Public Information • Emergency Response and Preparedness • Potential Flood Projects with Ecological Opportunities (includes correcting barrier culverts) • Programmatic Solutions-i.e. regulation changes, tax breaks
Project Matrix • Projects may be grouped under a sub heading (“Retention Projects” or “Levees and Dikes” under Floodplain Protection) • In these cases, the project heading is numbered following the project numbering sequence. • Projects under the heading are numbered in Roman Numerals • Matrix of projects is not prioritized • Meant to serve as a baseline of projects for potential future funding • Served as source material for 2012 legislative jobs package
Projects to be Removed Matrix • Matrix of projects that are proposed to be removed from the Projects Matrix • Repetitive • Completed • Currently funded and on-going • Source of project unknown • No longer a priority
Request to the Flood Authority • Provide recommendations on: • 1. Proposed Goal • 2. Overall Approach • 3. Do you have any additional projects for the Project Matrix? • 4. Do you have any additional sources that should be reviewed for additional projects?