An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. UPDATE at SBU (Feb 24, 2009) • 1st Water Target SuperP0Dule (DaveF, Kevin, Scott) • last week spent setting up hoses, pipes, water tank. • Problem with unfiltered SBU was solved with additional filters. • water filling started on Friday to ½ full, recommenced Monday, but stopped due • to funny crackling sounds. DaveW recommends more bracing before continuing • water level sensors will have to be removed before shipping and reinstalled in • Japan (may cause some interference with cabling) • needs to start cabling as soon as water test finishes • 2nd Water target SuperP0Dule • 11 of 13 P0Dules now mounted, should finish by later today or tomorrow • labeling can start • next water fill test in Mar 9(?), waiting for parts • 1st & 2nd ecal SuperP0Dules • Dima has tested at TFB’s and started some LI tests • plan to attach temp monitors (not all parts here? UW to ship this week?) • utility rails need to be lowered into final position (need to have temp monitors) • ears/bookends need to be attached • hoses to be attached and vac. Loop test (few parts to be ordered)

  2. UPDATE at SBU (Feb 24, 2009) continued • Shipping date now finalized to April 15 (?) • drop dead week, March 30 • crating people move SuperP0Dules to basement on April 6 • crated superP0Dule fly out of NY week of April 15 • Remaining time for SBU assembly and check is **5 weeks** including this week • two ECAL SuperP0Dules to be completed • temp monitors, move utility rails to final position • 1st water target SuperP0Dule • modify braces and finish water filling test (this week) • start cabling top and sides, temp monitors • TFB testing? • 2nd water target SuperP0Dule • finish assembly tomorrow • start labeling • insert pipes and sensors (Mar 9 by UW people?) • start cabling sides and top, temp monitors • TFB testing? •  guessimate of about 4 weeks of solid shift work needed to complete above • Assuming no parts delays and no impact of new tasks on shifters • Other parts; (Dave&Clark) lifting fixtures, covers, corner brace for shipping, etc.

  3. Water level sensors and water pipes to Be inserted into the bags in the SP0Dule Scott inserting pipes into Water tank Kevin and DaveF attaching hoses to each pipe

  4. Dave Forbush attaching sensor leads Detail of elbow connections in Water bag frames Trung, Chris, & Ian setting up braces before filling bags

  5. Readout, being checkec before filling water bags. Scott, Dima, DaveF Kevin, and Bent. Note P0Dule on right being prepared for mounting on 2nd water target SuperP0Dule