New Build prospects in the UK International Nuclear Forum

New Build prospects in the UK International Nuclear Forum Bulgarian Nuclear Energy – National, Regional and World Safety 28-30 th May 2008 Bulgarian Atomic Forum BULATOM andy.jackson@amec.com. Who will finance new build in the UK ?. Not the Government, the Nuclear White Paper stated;

vienna
Download Presentation

New Build prospects in the UK International Nuclear Forum

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. New Build prospects in the UK International Nuclear Forum Bulgarian Nuclear Energy – National, Regional and World Safety 28-30th May 2008 Bulgarian Atomic Forum BULATOM andy.jackson@amec.com

  2. Who will finance new build in the UK ? • Not the Government, the Nuclear White Paper stated; • it is in the public interest that new nuclear power stations should have a role to play in this country’s future energy mix alongside other low carbon sources • that it would be in the public interest to allow energy companies the option of investing in new nuclear power stations • that the Government should take active steps to open up the way to the construction of new nuclear power stations

  3. Who will finance new build in the UK ? • The Utilities and generators will finance and lead new build, perhaps in consortium, interested parties include • EDF • British Energy • RWE • EoN • Centrica • Other UK and overseas utility parties are expressing interest also • Energy companies will also meet the full costs of decommissioning and their full share of waste management costs

  4. Who will back the process? • Government will facilitate; • Engagement with Public and Stakeholders • Planning reform for major electricity generating stations • Undertake a strategic siting & environmental assessments • Run a process of justification (involving ionising radiation) • Generic Design Assessment of the reactor designs • Energy Bill clauses (duty to create WM&D funds) • Push for strengthening of EU Emissions Trading Scheme • Managing Radioactive Waste safety

  5. What technology will be adopted in the UK ? • Only standard and proven nuclear technology will be adopted, as reviewed under the generic design assessment process • Westinghouse (AP1000) [under construction in China & US announced 1st Contract] • AREVA (EPR) [under construction in Finland and France] • GE Hitachi (ESBWR) • AECL (ACR 1000) focusing on Canadian Market

  6. What technology will be adopted in the UK ? • Only standard and proven conventional turbine generator technology will be adopted, typically as supplied by • ALSTOM Power • SIEMENS • Mitsubishi • GE Hitachi

  7. When is UK new build likely to start/finish? • Generation output from the first unit of UK new build expected by 2020, (EDF suggest 2018) other units to follow thereafter, typical early timescale is • Site review and selection between 2008 and 2010 • Early contracts between 2009 and 2011 • Early civil works start between 2010 and 2012 • First concrete between 2012 and 2015 • First generation possible 2018 and 2020

  8. Apr-08 Apr-09 Oct-09 Now When is the GDA due to complete? HSE Jul-2011 Step 1: Design & safety case preparation Step 4: Detailed Design Assessment (Evidence) Step 2: Fundamental Safety (Claims) Review Step 3: Overall Design Safety Review (Arguments) Decision Consultation Fundamental Review Detailed Review Initiation Dec-2010 Environment Agency Source BERR Energy Bill Feb 2008 Consultation on Funded Decommissioning Programme Guidance for New Nuclear Power Stations

  9. Possible timing of new nuclear power plants

  10. Where is UK new build likely to be? • Not in Scotland (SNP threatened to block their development) but within England and Wales where preference is for sites and local community support with experience of nuclear power and process operation • British Energy sites • NDA sites (18 off) • Government may sell its stake in British Energy

  11. What is the impact on UK plc? • Strong UK involvement in large scale new build programme • Owners groups will require experienced UK staff with regulatory and power plant experience. • Possible programme of multiple build will require flexible resources • UK programme, project and construction management companies will be employed • Heavy on site and some off shore civil works • UK supply chain will be used • Additional trained UK resources will support existing UK resource

  12. What will be the process in the short term? • Owner groups will be formed • Contracting strategy will be confirmed (EPC turnkey vs incentive style arrangement) • Preferred sites and reactor designs will be selected • Justification/Strategic Siting Assessment process will start • First orders placed • Early site works will be started

  13. White Paper Forward by the Prime Minister “More than ever before, nuclear power can and will make a real contribution to meeting our commitments to limit damaging climate change” Gordon Brown January 2008 This view is fully supported by the BNES/INucE, the NIA, AMEC and the UK utilities and supply chain. It is no longer if we choose nuclear power as part of our energy mix. It is how and when and where.