1 / 32

Experience from Co-curing

Experience from Co-curing. Tom Johnson, Eric Anderssen , Mario Cepeda , Gil Gilchreise , Carl Haber Lawrence Berkeley National Lab 11-Nov-2010 AUW. Outline. Introduction Build process Cable metrology Stave metrology Plans and Ideas. Introduction.

vilmos
Download Presentation

Experience from Co-curing

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Experience from Co-curing Tom Johnson, Eric Anderssen, Mario Cepeda, Gil Gilchreise, Carl Haber Lawrence Berkeley National Lab 11-Nov-2010 AUW

  2. Outline • Introduction • Build process • Cable metrology • Stave metrology • Plans and Ideas

  3. Introduction • Early tests with lamination of bus cables to stave cores were successful but difficult • Concern with QC on a large number of parts and loss of expensive components • Have studied co-cure of bus cables to facings followed by core lamination • Shape metrology and bus cable metrology • Have used these in subsequent electrical studies as well

  4. Composites Facility

  5. Configuration • Lay up is 90-0-90, better for thermal conductivity across the module and reduced local curvature • Overall twist can be handled with fixtures

  6. Cable Inspection • Inspect Cable for Damage prior to curing. • Broken traces • Wrinkles • Laminated dirt • Discoloration

  7. Clean Top Surface and Apply 1 mil Flashbreaker Tape

  8. Surface Prep of Backside Prior to Bonding - Use ScotchBrite pad to Abrade Backside of Cable. - Clean with Alcohol

  9. -Part is layed up on a glass plate covered with A4000 release plastic. -0 deg ply on bottom and 90 deg ply on top. -The white is the paper backing of the prepreg. -Once layed out they are taped together to hold in place and covered with another layer of A4000. (4,5) -Plys are then compacted under vacuum to stick the plys together. (6) 1 2 3 4 5 6

  10. - After compaction, flip part so the 90’s are down against the glass. - Remove the paper backing from the 0 ply. (1) - Stack the next 90 deg ply the same as the previous 90 ply. (2) - Tape together, A4000 release plastic and compact (3,4) 1 2 3 4

  11. - After compaction remove the exposed paper backing. • Apply a single layer of pealply to this side. Pealply gives the surface • the desired texture and absorbs extra resin

  12. - Flip part again so the pealply is now against the glass and remove the paper backing. (1) • Position cable and apply it to the stack. (2) • Add a small piece of pealply to the remaining exposed carbon on the end. (3) • Cover stack with A4000 release sheet. (4) • Compact. (5) 1 2 3 4 5

  13. - After compaction, Flip the entire stack so the cable is now against the flat glass surface. (1) • Cover with a fresh piece of A4000 making sure to have no wrinkles. (2) • Add layer of breather (no wrinkles) and put under final vacuum bag for cooking. (3) 2 1 3

  14. Stave Assembly • Stave assembly proceeds similar to the usual case • Special 1.5 meter vacuum fixture was prepared to hold co-cure facing/cable flat for lamination to core

  15. -The honeycomb needs to have one side ground/sanded flat prior to bonding on the first co-cure cable. Can be ground on a surface grinder using thick “Airtech” double sided tape. Or as we did if a grinder is not available at the time. Flat Mic6 plate and two spacer blocks. Sandpaper is applied to one side of the mic6 . Then honeycomb is sanded flat

  16. Each piece of honeycomb (HC) is dipped into a thin pool of epoxy and let sit for 30 seconds to allow the epoxy to wick onto the HC. Its then positioned onto the co-cure cable that is securely held down flat by the vacuum chuck. An aluminum plate with a silicon sheet is placed on top the HC and left overnight to cure. You can see the aluminum plate w/silicon and epoxy pool in the next slides.

  17. Red Silicon and aluminum plate. Left to cure overnight.

  18. This first side with bonded HC is held flat by vacuum. Second side HC (exposed) is then surface ground or sanded.

  19. Completed Honeycomb side . Epoxy Pool for dipping Honeycomb. The entire stave will be set into the pool for 30 sec then placed on top the 2nd co-cure facesheet that will be held flat by the vacuum chuck

  20. Align top co-cure to bottom co-cure. Place aluminum plate with silicon sheet on top. Add additional weight as needed. Red silicon can be seen under the alum plate.

  21. After minimum of 24 hour cure can be remover from fixture. Hysol EA 9396 epoxy has 80% cure at room temp in 24 hours. 100% cure room temp 72 hours.

  22. Post Processing • Completed stave is cleaned with an atmospheric plasma system • Cleanliness can be checked with a water droplet system • Good wire bonding performance observed along the entire length Full stave with 24 BCC boards mounted and bonded, EOS card bonded at the left

  23. Cable Cleaning • Find that wire bonding ease and reliability improves with plasma cleaning • Have procured and installed a plasma cleaning and scanning system • Plasma generator from SurfX • Custom large area scanner

  24. Droplet System

  25. Metrology • Optical metrology (OGP) was performed on free cables, cable+facing co-cure, and completed stave • Metric was module-to-module feature, nominally 98 mm • Touch-probe metrology was performed on the completed stave to measure full profile

  26. Optical Metrology of Cable and Stave full stave

  27. Data on Full Length Parts

  28. Findings • Free bus cables (or co-cure to facing) are consistently short by ~100 mm per segment • Cummulative error is ~ 1 mm • If true we would need to adjust in artwork • On complete stave some of this error is recovered, particularly near the ends.

  29. Stave Metrology Flatness • Thickness measured with calipers • Flatness measured on a CMM with a touch probe scan. • Stave supported flat (maximal sag orientation) at the Airy points • Consistent built-in bowing measured from both sides: 735 microns

  30. Thickness 6.188 6.195 6.159 6.173 6.191 6.204 6.251 6.230 6.236 • Well correlated side-to-side: 10-20 mm • Systematic ally thicker at far end: 50-60 mm • Maximum deviation point-to-point = 102 mm • Potentially better if HC had been ground rather than sanded 6.200 6.183 6.162 6.154 6.200 6.183 6.256 6.212 6.200 mm

  31. CMM Scan Data

  32. Discussion • What drives this bow? • Is it related to the cable differential linear measurements on the stave? • How much CTE difference would drive this? • Does it matter? – barrel mounts would compensate • In the future could co-cure both cables and facings on the same sheet and at the same time • Ensure identical stack and thermal profile

More Related