Lake Worth Capital Improvements Implementation Plan Update. Paul Bounds, Regulatory and Environmental Coordinator August 2011. Gas Lease Funding. Current Lake Worth Gas Lease Fund balance is $23,354,423 Lake Worth CIIP - $23,319,212 Completed Projects - $3,592,572
E N D
Lake Worth Capital Improvements Implementation Plan Update Paul Bounds, Regulatory and Environmental Coordinator August 2011
Gas Lease Funding • Current Lake Worth Gas Lease Fund balance is $23,354,423 • Lake Worth CIIP - $23,319,212 • Completed Projects - $3,592,572 • In Progress - $3,546,640 • Budgeted – $16,180,000
Completed Projects • Phase I Dredging Design $1,519,299 • Northside III 16” Water Main 913,405 • Arrow S Boat Ramp 300,000 • Gas Drilling BMP Study 24,871 • Stump and Hazard Removal 307,207 • Casino Beach Boat Ramp 527,790 • TOTAL $3,592,572
In Progress • Phase I Nature Trail Design $900,000 • Phase II Dredging Design 600,000 • Woodvale Water and Sewer 2,046,640 • TOTAL $3,546,640
Budgeted Projects • Phase I Dredging 15,000,000 • Green Printing Study 280,000 • Mobile LiDAR Study 100,000 • Casino Beach/ Watercress Water/Sewer Design 800,000 • TOTAL $16,180,000
Lake Worth Dredging Schedule • Receive proposals for disposal July 15 • Submit Letter of Permission Application to COE August 5 • Advertize for Bids September 1 • Award Bid November 15 • Notice to Proceed December 1