1 / 16

MICE Updates

MICE Updates. Target. BM2. BM1. Decay Solenoid. MICE Hall Target Decay Solenoid Trackers Spectrometer Update Schedule. Terry Hart, NFMCC Friday Meeting, May 15, 2009. Details at www.mice.iit.edu/vc/vc118/vc118.html , www.mice.iit.edu/vc/vc119/vc119.html ,

watson
Download Presentation

MICE Updates

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MICE Updates Target BM2 BM1 Decay Solenoid • MICE Hall • Target • Decay Solenoid • Trackers • Spectrometer Update • Schedule Terry Hart, NFMCC Friday Meeting, May 15, 2009 Details at www.mice.iit.edu/vc/vc118/vc118.html, www.mice.iit.edu/vc/vc119/vc119.html, www.mice.iit.edu/vc/vc120/vc120.html TLH, NFMCC Friday Meeting

  2. MICE Beamline Target BM2 BM1 Decay Solenoid Target: Titanium paddle dipped into ISIS proton beam to produce pions Decay Solenoid: Focuses muon beam coming from pion decay TLH, NFMCC Friday Meeting

  3. TLH, NFMCC Friday Meeting

  4. TLH, NFMCC Friday Meeting

  5. TLH, NFMCC Friday Meeting

  6. Installation & Commissioning Schedule (Draft! To be discussed tomorrow [May 8]!) Early August (1 week): Assemble Target1: Core (stator), shaft, optics, bellows in clean area at RAL. Install in R78. Add optical, electrical, water connections. Run for ≤ 1 week (How many pulses??) Infrastructure planning – finalise tomorrow [May 8]. In parallel, assemble Target2. Install Target2 in R78. Run as demonstrator. Transfer Target1 to ISIS, install in August shutdown. Chris Booth University of Sheffield TLH, NFMCC Friday Meeting 6

  7. MICE Beamline Target BM2 BM1 Decay Solenoid Target: Titanium paddle dipped into ISIS proton beam to produce pions Decay Solenoid: Focuses muon beam coming from pion decay TLH, NFMCC Friday Meeting

  8. Decay Solenoid (DS) • Lack of multi-layer insulation (MLI) determined to be cause of quenches about 290 A (normal running at 890 A) • MLI added to exit end of DS. • Add MLI to entry end of DS during ISIS shutdown • Other tasks • Investigate quench detector issues • Attempt to fix transfer line leak TLH, NFMCC Friday Meeting

  9. Decay Solenoid Decay Solenoid – Powered up to 900 A, 24/04/09 • Between 21-23 April: • Quench Detector (QD) problem diagnosed to broken wire within QD chassis • 2A fuse associated with QD external relay chain blew and replaced with 5A fuse (need to restore original fuse tolerance) • Fri 24 April: • Decay Solenoid powered up in stages to 900 A • Then brought down to 870 A (5T B-field), where it remained for 1 hour • Powered down once more. • Further tests need to be carried out • Need to carry out soak tests at 870 A over a period of many days to demonstrate that solenoid can work in a stable manner • Tom Bradshaw putting together document to define standard operating conditions for decay solenoid. Many thanks to Matt Hills, Jim Rochford, Mike Courthold, Craig Macwaters, James Leaver, Willie Spensley, Linda Coney … TLH, NFMCC Friday Meeting

  10. Tracker 2 Readout • Tracker 2 readout boards tested and characterized at FNAL • Tracker 2 readout system shipped to RAL • Tracker 2 assembled at RAL • Power failure prevented tracker 2 cosmic ray tests (joining tracker 1) TLH, NFMCC Friday Meeting

  11. Trackers • 2 trackers currently in Lab 7 • Optimum bias voltages set for all 8 cassettes • Final LED data taking starts today TLH, NFMCC Friday Meeting

  12. Spectrometer Update • “Second magnet” to be shipped to FNAL for field mapping before “first magnet” • Field mapping progress • Developed by IIT student Ben Freemire with help from Yagmur Torun and Rajendra Raja • Software can plot field components at specified locations • User interface functionality determined and finished • Differences in field values of test magnet using Senis and NIKHEF probes TLH, NFMCC Friday Meeting

  13. Field Plots from Senis and NIKHEF Probes • Top: NIKHEF • Asymmetric along y-z • Max. field different than for Senis • Not flat at min., max fields • Explanation • Magnet bumped? • Manipulator skewing positions? • Bottom: Senis • Field shape and values good • Remap magnet TLH, NFMCC Friday Meeting

  14. Summary [from May 7 videoconference] • Second magnet assembly including all fixes and modifications has been completed • Second magnet had been cooled to 5K (cold mass) and transfer of LHe was under way • An internal leak developed between the cryostat and the insulating vacuum (1 week ago) • Leak is likely in either the cryostat fill or vent lines • Magnet has been warmed up and leak checking is under way • LN cooldown system developed at FNAL has been installed • Temperature logging system developed at LBNL is working • First magnet completely disassembled, fixes well under way in preparation for reassembly • Additional cryostat penetrations and extra vent line added • Modifications to vent line are nearly complete TLH, NFMCC Friday Meeting

  15. Current Spectrometer Considerations • Time estimate for shipment to FNAL now impossible to make • FNAL shutdown starts June 15 • Doubtful magnet can be mapped before August • Discussion at next MICE meeting about possibly moving tracker w/o magnet to MICE hall TLH, NFMCC Friday Meeting

  16. TLH, NFMCC Friday Meeting

More Related