MQXF Short model and prototype plans. P. Ferracin, G. Ambrosio. HL-LHC/LARP International Review of the MQXF Design December 10-12, 2014 CERN. Program overview Short model status and plans Long model plans “Links”. MQXF project schedule.
E N D
MQXF Short model and prototype plans P. Ferracin, G. Ambrosio HL-LHC/LARP International Review of the MQXF Design December 10-12, 2014 CERN
Paolo Ferracin, Giorgio Ambrosio Program overview Short model status and plans Long model plans “Links”
MQXF project schedule Paolo Ferracin, Giorgio Ambrosio • Short model program: 5 CERN-LARP models, 2014-2017 • Coil fabrication started in 03/2014 • First magnet test (MQXFS1) in 08/2015 (3 LARP coils, 1 CERN coil) • Long model program: 2 (CERN) + 3 (LARP) models, 2015-2018 • Coil fabrication starts in 2015: 02 (LARP), 10 (CERN) • First magnet test in 11/2016 (LARP) and 11/2017 (CERN) • Series production: 10 (CERN) + 10 (LARP) cold masses, 2018-2022 • Coil fabrication starts in 01/2018 • First magnet test in 10/2019
Paolo Ferracin, Giorgio Ambrosio Program overview Short model status and plans Long model plans “Links”
Short model program 2017 2014 2015 2016 CERN coil RRP coils, CERN 1st set RRP coils, CERN 2nd set PIT, CERN 1st set LARP coil RRP coils, LARP 1st set RRP coils, LARP 2nd set Mirror Models MQXFS1-2, 1st coil set MQXFS3-4, 2nd coil set MQXFS 5, PIT Paolo Ferracin, Giorgio Ambrosio • 3 models with first set of coils • All tested by LARP • Coil design update by March 2015 • Second set of coil start in Oct. 2015 • 2 models with 2nd set of coils • PIT coils and models in 2016-2017
Short model statusCoil fabrication LARP coil #1 completed LARP coil #2 completed LARP coil #3 Prep. for impregn. at BNL LARP coil #4 Winding CERN coil #103 Winding CERN coil #001 (Cu) completed CERN coil #101 (Low-grade) Completed CERN coil #102 Prep. for impregn. Paolo Ferracin
Short model statusModels Paolo Ferracin, Giorgio Ambrosio • 2 identical support structures fabricated • One at CERN, one shipped to LBNL • Same CAD model and same fabrication companies • 150 mm mock-up being tested • Mirror magnet to be tested in Feb.-Mar. 2015
Paolo Ferracin, Giorgio Ambrosio Program overview Short model status and plans Long model plans “Links”
LARP prototypes 2015 2016 2017 2018 RRP coils, 1st set RRP coils, 2nd set RRP coils, 3rd set Mirror MQXF1-1b MQXF2 MQXF3 Paolo Ferracin, Giorgio Ambrosio Winding in Feb. 2015 3 sets of coils 2 long prototypes before start of pre-series coil fabrication
CERN prototypes 2017 2018 2015 2016 RRP coils PIT coils Mirror MQXF1-1b MQXF2 • Winding in Oct. 2015, reaction in mid 2016 • 1 set of RRP coils, 1 set of PIT coils • 1 long prototypes before start of pre-series RRP coil fabrication Paolo Ferracin, Giorgio Ambrosio
Prototypes status Paolo Ferracin, Giorgio Ambrosio • LARP • taking the lead with 4 m coil fabrication starting in February 2015 • Equipment upgrades in progress: • Automatic (Selva) winder (FNAL) • Curing mold (FNAL) • Vertical test facility (BNL) • Coil tooling is under procurement • Structure assembly tooling under design • CERN • Coil and tooling CAD models in progress • Price inquiry in Jan./Feb. 2015
Paolo Ferracin, Giorgio Ambrosio Program overview Short model status and plans Long model plans “Links”
Links 2015 2016 2017 2018 Paolo Ferracin, Giorgio Ambrosio Short mirror LARP long coil MQXFS1 CERN long coils MQXFS3 LARP long II set MQXFS4 LARP long III set MQXFS5 CERN long PIT 3 long models results ~before start series coils