An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Truro DG5 SchemeApril 2013

  2. Integrated Urban Drainage Schemes Proposed Hendra Road surface water separation Victoria Square Kenwyn Street Proposed Redannick Lane surface water separation

  3. Drainage From New Developments To treatment

  4. Truro DG5 SchemeProgramme of Works

  5. Key Plan Frances Street New / upsized combined sewer - red Victoria Square Ferris Town Little Castle Street New / upsized surface water sewer - blue Kenwyn Street St. Dominic Street

  6. September 2013 Local hoarding within Victoria Square with buses still operating Establish site offices and compound

  7. October 2013 Local hoarding within Victoria Square with buses still operating Drive Pit for Auger Bore in Thomas Johnson Court Rebuilding buried CSO Site offices and compound Hoarding to be extended late October and Square closed to all traffic

  8. November 2013 Short length of open cut sewers Drive Pit for Auger Bore in Thomas Johnson Court Victoria Square closed to all traffic Rebuilding buried CSO Site offices and compound Sewer Laying across Calenick Street and Kenwyn Street junction Open cut surface water sewer

  9. December 2013 Victoria Square cleared of all hoarding and buses running Deep open cut sewers Site offices and compound

  10. January 2014 Surface water sewers Deep open cut sewers Site offices and compound Victoria Square closed to traffic until sewers clear the junction

  11. February 2014 February 2014 Surface water sewers Ferris Town Foul sewers along Kenwyn Street Site offices and compound Route of traffic leaving Victoria Square

  12. March 2014 Reinstatement of Kenwyn Street; 3-4 days late March Site offices and compound Surface water sewers across St Dominic Street and junction with City Road Foul sewers across Kenwyn Street junction with Little Castle Street

  13. April 2014 Little Castle Street sewers Site offices and compound Surface water sewers across St Dominic Street and junction with City Road

  14. May 2014 River outfall headwall [not affecting traffic] Frances Street sewers Site offices and compound

  15. June 2014 Deep open cut sewer from river outfall headwall to Frances Street Site offices and compound