1 / 14

FACILITY SECURITY PLANS (FSP’s)

FACILITY SECURITY PLANS (FSP’s). MSD STURGEON BAY MST2 JEROMY COWELL. FORMAT & CONTENT. Security Administration & Organization Personnel Training Drills & Exercises Records & Documentation Changes is MARSEC Levels Interfacing with vessels Declaration of Security Communication.

wvalley
Download Presentation

FACILITY SECURITY PLANS (FSP’s)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FACILITY SECURITY PLANS(FSP’s) MSD STURGEON BAY MST2 JEROMY COWELL

  2. FORMAT & CONTENT • Security Administration & Organization • Personnel Training • Drills & Exercises • Records & Documentation • Changes is MARSEC Levels • Interfacing with vessels • Declaration of Security • Communication

  3. FORMAT & CONTENT • Security systems/equipment • Access Control • Restricted Areas • Handling cargo • Delivery of vessel stores & bunkers • Monitoring • Audits & Amendments • Facility Security Assessments • Facility Vulnerability (CG-6025)

  4. Submission & Approval • 1 copy of the facility FSP must be submitted to the local COTP for review and approval • USCG reviewers can either approve it, return it for revisions, or disapprove it • One FSP may be submitted to cover more than one facility with similarities of design & operations • Once approved, the FSP is valid for 5 years from the date of approval

  5. Amendments • Initiated by either the facility or the COTP if deficiencies are found • For amendments initiated by the COTP, facility has at least 60 days to submit proposed amendments • Amendments by the facility must be submitted at least 30 days prior to it taking effect for COTP review • Facility change in ownership requires a amendment(s)

  6. Audits • Performed Annually • Conducted for FSP(s) if: • A change in facility ownership • Facility modifications • Auditors must have knowledge of security techniques & methods

  7. USCG Enforcement Actions • CG-835 Facility Inspection Requirements • Letter of Warnings • Notice of Violations • Class I Civil Penalties

  8. CG-835 Facility Inspection Requirements • For minor first-time infractions where on-the-spot training can correct the deficiencies • Given a specific date to correct the deficiencies • Issued at the discretion of USCG facility inspectors • Lowest level of enforcement

  9. Letter of Warning (LOW) • It’s like a written warning issued by a police officer for a traffic violation with no monetary penalty, but will stay on a facility’s record for 1 year. • Facilities can either “Accept” or “Decline” the warning • Declining a LOW will progress the violation to a Notice of Violation.

  10. Notice of Violation (NOV) • It is similar to a traffic citation given by a police officer for a traffic violation resulting in a monetary penalty • For penalties less than $10,000 • Can either “Accept” or “Decline” the NOV • Can “Decline” the NOV within 45 days, afterwards it goes to USCG collections department. • “Declining” a NOV will send the violation to a USCG Hearing Officer for a determination • Final assessment may be equal or greater than the proposed penalty

  11. QUESTIONS ?