1 / 23

Collimator Production and Installation

Stay informed about the latest progress in the production and installation of collimators for the LHC collimation system, including key dates, challenges, and achievements. Explore system complexities, installation procedures, and production schedules. Keep track of production delays, achievements, and upcoming collaboration meetings. Follow the journey from production to final installation at CERN. Get insights into the challenges faced and the commitment to meet project milestones.

wwagner
Download Presentation

Collimator Production and Installation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Collimator Production and Installation R. Assmann for the collimation team 29-Mar-2006 Special thanks to O. Aberle, S. Chemli, K. Foraz, J. Inigo-Golfin, M. Jimenez, Y. Kadi, J. Lettry, M. Mayer, R. Perret, J.P. Quesnel, C. Rathjen

  2. The Final Collimation System • The LHC collimation system is 100% frozen. • Final system is very powerful but complex: • Ring: 172 database locations (158 in collimation project). • TL: 28 database locations (all in collimation project). • 8 types of collimators plus various types of masks and absorbers. • 4 phases defined for path to nominal and ultimate intensities. • Different interfaces depending on type of neighboring equipment. • System is necessarily complex to provide the required excellent performance. It is difficult to understand and follow all system aspects (also sometimes for us). • Production of system followed by AB/ATB (collimators, motors, sensors), TS/MME (supports) and AT/VAC (mobile pumping ports)! Many thanks! • System involves 5 major production contracts!

  3. Transfer Line Collimation • Installation of several TCDI (transfer line collimators) is required! • Commitment: • 4 TCDI for installation in May/June 06. Cover difficult installation points! Collimator Delivered Ready for installationTCDI 1&2 28/3 & 10/4 8/5TCDI 3&4 ~ 20/4 11/5 & 15/5 • Installation slots:TCDIH87904, TCDIH88121, TCDIV88123, tbd • The rest of the TCDI in January 2007! • This approach: • Allows to test transfer line collimation. • Difficult installation points addressed early on! • Minimal temporary installations: the transfer line is under vacuum! • Does not impact ring installation of collimators(no production delay for the ring)! TCDIH87904: installation in the presence of both the QRL line directly above and the LHCcryomagnet in front. It is foreseen to bring the collimator underneath the cryomagnet and lift it up in position with the help of a lifting crane permanently installed at that position.TCDIH87441: installation interferes with the presence of a bus bar connecting the MBI87424 to the MQID87500. A special support foot was designed to fit under the bus bar.

  4. Planning First 4 TCDI Y. Kadi

  5. Installation Procedure Ring

  6. Collimation Tunnel Components Vacuum pump Quick-connect flanges Beam 2 Collimator tank Interconnect support Collimator support Survey reference points Motorization/sensors Production done in AB, TS, AT! R. Perret et al

  7. Installation Planning LSS • Different parts of the collimators are produced independently. • Installation planning is different for different components. • A list has been worked out, based on: • New collimator production info was sent by company on March 8th and confirmed this Monday.

  8. Other production contracts are on schedule: • Supports • Motors • Position sensors • Mobile pumping ports • No details here…  Not very detailed planning…

  9. Production Schedule Collimators Delay: 3 months behind contract!

  10. Latest Achievements in Production First collimator has been shipped to CERN! Finally!!! … and it arrived yesterday at CERN! (shock during transport detected and being analyzed)

  11. Latest Achievements in Production Parts for many collimators at CERCA!

  12. Production Problem Most urgent problem: Brazing of ring collimators! Repair of brazing oven required! CERCA looks for alternative! TS/MME has offered help: decision this week!

  13. Status Collimator Production • We are getting cautiously optimistic about the latest production schedule: • An official CERN letter was sent and caused some reactions! Things are shaken up! • Commitment from CERCA on an updated production schedule. Confirmed this Monday! • CERCA announced increase of manpower by 70%! This is GOOD! • Lots of collimator parts are now visible at the company! • CERCA director is reviewing the production contract and analyzing problems! • We heard yesterday that CERCA director believes contractual rate of 10 collimators per month is overly optimistic!?? • Follow-up meeting at CERN end of April, beginning of May with CERCA top management and CERN management. The story is not finished! • Take latest CERCA schedule as baseline! Add 2 months for work at CERN: • Final assembly of collimator. • Installation of motors, sensors, … • Transport and installation.

  14. Support Installation  Committed to install ALL supports in LSS planning!

  15. Support Installation Time for connection of supports to cables & water. Alignment campaign by sector with dummy collimator! Included in installation coordination! HW commissioning!

  16. Collimator Installation • Definition of dates (after discussion with Katy, Miguel, …): • “Collimator READY date”: CERCA delivery date plus 2 months for final assembly and installation. • “Start of mechanical installation vacuum”: Install collimators before vacuum is installed! Simplifies vacuum work. • If not possible: Fallback solution is installation of collimators before “start of bake-out”! • Thanks to the planning groups for making all the required info available to us and for taking our needs into account!

  17. Collimator Installation

  18. Detailed Tables for Planning Originates from collimation phase but changed!  PDF file for all LSS’s!

  19. Summary Installation Plan • Here 46 replacement chambers required for phase 2 and special phase 1 collimators. 40 exist! We should get 6 more! • In addition a minimum 9 replacement chambers for delayed collimators. • In total an additional 20 replacement chambers are proposed based on present planning! • Can be stainless steel ( impedance team). Flexible in usage (most collimators have the same length and flange diameter)! Almost full phase 1 system for LHC start-up! No performance limits!

  20. Fallback Solutions (Proposal) • Goal is to keep the target date, in particular to have the collimators installed before the vacuum installation starts. • If additional delay of up to2 months:  Install collimators up to the start of the actual bake-out. • If additional delay of more than 2 months: Leave IR7 partly empty, following advise by the vacuum group (try to complete sectors with new sector valves). To keep some performance we would prefer to delay a secondary collimators (TCS), if needed. If beneficial skip bake-out in IR7. No problem identified in last meeting of the MIBWG (Machine-Induced Background WG)  acceptable!

  21. Residual Problems • Many discussions around the ~200 locations over the last years. • Most (all?) have been resolved and LHC database has all collimators, absorbers, … included now! Final ECR sent! • Ongoing discussions: • Vacuum layout close to tertiary collimators in IR1 (pointed out by S. Chemli). Not enough space for standard mobile pumping ports!? • Interference with installation of air duct in IR7. Before we install collimators support we want the air ducts to be there (in schedule?).

  22. Conclusion • Many thanks to the planning team and technical groups for info, feedback, advice and for taking our special needs into account! • We are almost fully compatible with the last draft LHC schedule (for the first time since we started the collimation project). Almost full phase 1 system!? • Further feedback is welcome! Is the presented approach acceptable? • Risks still exist (collimator production) and we need to react if required. • Questions for discussion: • Is the information provided in the collimator installation tables adequate? What can be improved? • What would be the right procedure to adapt the installation planning to the collimator production progress? • What is the shortest acceptable notice for changes? • Decision on replacement chambers?

  23. Links

More Related