An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Results of short module and qualification strategy PIMS production meeting 26-27 February 2013 Rolf Wegner

  2. Production qualification, April 2012 Status of machining qualification, 19.04.2012: PIMS production meeting 26-27 February 2013 Rolf Wegner

  3. Review of steps towards qualification • Meeting at CERN in March 2012: • * machining procedures optimised (=> clamping) [parts seen 5 to 10 times out of tolerance] • * specifications very tight; small performance degradation <=> accepting certain deviations from specifications (EDMS 1209460) • * recommendation: final machining on a lathe • Meeting at NCBJ in April 2012: • * green light for rough machining of discs for series • * Quality Assurance Report form defined • Mai 2012: • * new weld qualification with cosmetic pass + repair of weld for ring G_13-14 • * preliminary metrology end disc M_1=> green light to finish end disc M_14 and disc M_6-7 • June 2012: • * brazing test finished PIMS production meeting 26-27 February 2013 Rolf Wegner

  4. Review of steps towards qualification • July 2012: • * QA report disc G_2-3 ok, end disc M_1 ok, shipment to CERN • * QA report disc M_6-7, re-machining of assembly ø524 requested • * QA report end disc M_14, agreed on adaptation of ring M_13-14 - side 14 for assembly ø524 • September 2012: • * welding of ring M_13-14 ok, defect on ring M_1-2 => sent for repair to Julich=> using ring G_13-14 as 2nd ring for short module • * brazing test evaluated at CERN (visual inspection, ultrasound & vacuum tests), very good result, => green light to produce waveguide ring cavity M • * disc G_2-3, end disc M_1 inspected at CERN => green light for finishing all discs cavity M • November 2012: • * QA report ring M_13-14 PIMS production meeting 26-27 February 2013 Rolf Wegner

  5. Review of steps towards qualification • December 2012: • * QA report re-machined ring G_13-14 => green light for finishing all rings cavity M • * end disc M_14, disc M_6-7, ring M_13-14 and ring G_13-14 arrived at CERN • January 2013: • * QA report discs M_2-3, M_12-13 • February 2013: • * QA report discs M_4-5, M_10-11 PIMS production meeting 26-27 February 2013 Rolf Wegner

  6. Quality Assurance Reports • => "Disc G_2-3 - Analysis & Comparison CERN.xlsx" • * report form from NCBJ exactly as desired • * analysis to specifications • * analysis to acceptable dimensions • * comparison to CERN measurements • metrology machine accuracy: ± 6 μm • => comparison precision: ± 12 μm • => specifications 500 mm ± 10 μm difficult to machine and difficult to measure !!! • results quite similar (a few small points to discuss tomorrow) PIMS production meeting 26-27 February 2013 Rolf Wegner

  7. Vacuum tests at CERN end discs M_1, M_14; disc G_2-3; ring M_13-14 all leak rate < 2*10-11mbar*l/s PIMS production meeting 26-27 February 2013 Rolf Wegner

  8. Brazing test at NCBJ • good visual impression • vacuum tight (leak rate <1*10^-10 mbar l/sec) • good ultrasound analyse results • Agostino: ”It is hard to do itbetter” • => Green light for brazing of WG ring of 1st cavity (25.09.12) PIMS production meeting 26-27 February 2013 Rolf Wegner

  9. Machined parts, end discs M_1 and M_14 * to acceptable dimensions PIMS production meeting 26-27 February 2013 Rolf Wegner

  10. Machined parts, disc M_6-7 * to acceptable dimensions PIMS production meeting 26-27 February 2013 Rolf Wegner

  11. Machined parts, ring M_13-14 * to acceptable dimensions PIMS production meeting 26-27 February 2013 Rolf Wegner

  12. Machined parts, disc G_2-3 * to acceptable dimensions PIMS production meeting 26-27 February 2013 Rolf Wegner

  13. Machined parts, ring G_13-14 * to acceptable dimensions • Ring G_13-14 was intended for machining tests to validate milling technology (spare material of CERN prototype) • port welding defect, weld was repaired, further machining tests • port welding defect of ring M_1-2, ring G_13-14 is used for assembly check of short module PIMS production meeting 26-27 February 2013 Rolf Wegner

  14. Machined parts, summary • discs analysed are close to acceptable dimensions=> remarkable progress made since last year (improvement of factor 5 to 10 on most tolerances) assembly diameter 524.720-0.025+0 seem to be well under control (QA reports discs M_2-3, M_4-5, M_10-11, M_12-13)however, deviations on * coaxiality axis/524/538mm (=> inter-cavity alignment – aperture reduction)* perpendicularity axis/faces (=> inter-cavity alignment – aperture reduction)* cooling channel finishing • => we need to analyse remaining discs of cavity M at CERN for qualification • ring M_13-14 is close to acceptable dimensions=> remarkable progress made since last year (machining procedures were developed [weld deformation] and most acceptable tolerances reached) assembly diameter 524.720+0.050+0.075seem to be well under control (also ring G_13-14)however, deviations on * coaxiality538/524mm (=> inter-cavity alignment – aperture reduction)* perpendicularity axis/faces (=> inter-cavity alignment – aperture reduction)* only 1 ring as sample • => we need to analyse remaining rings of cavity M at CERN for qualification PIMS production meeting 26-27 February 2013 Rolf Wegner

  15. Short module: assembly test • assembly was very smooth • only end disc M_14 was slightly difficult to place correctly, small gap remains=> Thierry will use dense point weldings before final weld end disc M_14 ring M_13-14 disc G_2-3 ring G_13-14 end disc M_1 PIMS production meeting 26-27 February 2013 Rolf Wegner

  16. Short module: RF check, preliminary results z-axis: assembly order z=0 end disc M_1 - ring G_13-14 - disc G_2-3 - ring M_13-14 - end disc M_14 … to z=max PIMS production meeting 26-27 February 2013 Rolf Wegner

  17. Short module: RF check, preliminary results • assembly had to be clamped, otherwise Q ~ 1'000, f_mode_1 ~ 349.200 MHz • Q-values reasonable, will improve with welding (~ 10% seen for prototype) • field profiles look very similar, slight deviations for mode 2 • ~ 700 kHz frequency difference between measurement and simulations • simulation uncertainty ~± 500 kHz (mesh limit, 2 cells, different geometry) • tuning range (island + plunger) for mechanical tolerances + simulation uncertainties: ± 600 kHz • =>further analysis needed to understand difference in frequency simulations/measurement • =>simulationmodel needs to be checked carefully (systematic difference 700 kHz) PIMS production meeting 26-27 February 2013 Rolf Wegner

  18. Next steps • qualification of vacuum check • * visit of NCBJ experts to CERN, March 25-26th, tests of end disc, disc, ring • * shipment of equipment to NCBJ (~ 100 kg, ~ 200 pieces, ~ 25'000 CHF) • * visit to NCBJ with CERN experts, intended before April 19th (material !)tests of end disc, disc, ring • vacuum check of discs and rings cavity Mat NCBJ • production and checks of waveguide ring cavity Mat NCBJ • check of discs and rings cavity M at CERN => qualification for series production • check of waveguide ring cavity M at CERN => qualification for series production • in order to advance production, maybeintermediate green light for finishing cavity 2 PIMS production meeting 26-27 February 2013 Rolf Wegner

  19. Production qualification, February 2013 Status of qualifications, 25.02.2013: PIMS production meeting 26-27 February 2013 Rolf Wegner