An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


    1. Pradhan Mantri Swasthya Suraksha Yojana (PMSSY) Presentation by B K Prasad JS (Proc) 16 Jan 2010

    2. PMSSY Phase- I Up gradation of 13 existing Govt. Medical College Institutions in 10 States Setting up of 6-AIIMS-like Institutions at Bhopal Bhubaneshwar Jodhpur Patna Raipur Rishikesh

    3. Phase-II AIIMS-like Institutions in Uttar Pradesh and West Bengal Up-gradation of 6 Medical Colleges Govt Medical College, Amritsar, Punjab; RP Govt. Medical College, Tanda, HP; JNMedical College Aligarh, AMU (UP); Govt Medical College, Nagpur, Mah; Govt. Medical College, Madurai, TN; Pandit BD Sharma PGIMS, Rohtak

    4. Status PMSSY-I Up-gradation of 13 Medical Colleges AIIMS Residential College and Hospital

    5. Status PMSSY-II Site for AIIMS West Bengal identified but in case of UP Land not yet identified Up-gradation of 6- Medical Colleges Amritsar HSCC Tanda HSCC Madhurai HLL Rohtak HLL Aligarh HLL Nagpur State Govt

    6. 6-AIIMS Status

    7. AIIMS-Preparatory Works Boundary wall completed by HSCC. Pre-construction survey by WAPCOS completed. Sub Soil Investigation completed. EIA Clearance obtained. Design DPR Consultant appointed. Project consultant appointed. Works for Residential Complex started for all six sites.

    8. DPR approved in Feb 09 EFC Processed Tender packages finalized Tenders invited on 23 Dec 2009 152 Tenders received Technical Evaluation in Progress

    9. Tender Packages P-1 Medical ,Nursing colleges and Hostels P-2 Hospital and Trauma Care P-3& 4 External Electrification, Sub-station and A/C P-5 External Development P-6 &7 Operation Theatre and Furniture

    10. Work Schedule Bids received for 2- Package on 23 Dec20 09 152 Bids received- 57 for Hospital and 95 for Medical College and Hostels Technical and Financial Evaluation by 30 Jan 2010 PMC approval by 28 Feb 2010 LoA by 15 Mar 2010 Work to commence by 15 Apr 2010

    11. Monitoring Structure Project Management Committee at GOI level headed by Secretary (HFW), DGHS, AS&FA etc (14 Members) State level - Committee headed by Chief Secretary At site - Project Cell

    12. Project Cell at site (16 posts sanctioned)

    13. Project Cell at site Appointed: 5 Financial Advisors 6 Superintending Engineers 1 Executive Engineer Remaining vacancies advertised

    14. Thanks